SCHEDULESLocation of the regulated works

4SThe routes of the cables referred to in section 1(1)(d) of this Act are to run in direct lines between any two adjacent turbines and between the electrical substation and—

(a)turbines Nos. G8 and F8; or

(b)turbine No. K1.