Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Part 2SEnvironmental reports and consultation

14Preparation of environmental reportS

(1)In relation to any qualifying plan or programme, the responsible authority shall secure the preparation of an environmental report.

(2)The report shall identify, describe and evaluate the likely significant effects on the environment of implementing—

(a)the plan or programme; and

(b)reasonable alternatives to the plan or programme,

taking into account the objectives and the geographical scope of the plan or programme.

(3)The report shall include such of the information specified in schedule 3 as may reasonably be required, taking account of—

(a)current knowledge and methods of assessment of environmental matters;

(b)the contents of, and level of detail in, the plan or programme;

(c)the stage of the plan or programme in the decision-making process; and

(d)the extent to which any matters to which the report relates would be more appropriately assessed at different levels in that process in order to avoid duplication of the assessment.

(4)Information referred to in schedule 3 may be included in the report by reference to relevant information obtained at other levels of decision-making or through [F1other [F2assimilated] law].

(5)The Scottish Ministers may by order modify schedule 3.

15ScopingS

(1)Before deciding on—

(a)the scope and level of detail of the information to be included in the environmental report to be prepared in accordance with section 14; and

(b)the consultation period it intends to—

(i)specify under section 16(1)(b); and

(ii)notify under section 16(2)(a)(iv),

the responsible authority shall send to each consultation authority such sufficient details of the qualifying plan or programme as will enable the consultation authority to form a view on those matters.

(2)Each consultation authority shall—

(a)send to the responsible authority its views on the matters referred to in subsection (1) within the period of 5 weeks beginning with the date on which the details referred to in that subsection are received by the consultation authority; and

(b)send a copy of those views to the other consultation authorities.

(3)The responsible authority shall—

(a)take account of the views expressed by the consultation authorities under subsection (2)(a); and

(b)advise the Scottish Ministers of the period it intends to specify under section 16(1)(b) and notify under section 16(2)(a)(iv).

(4)If the Scottish Ministers consider that a period referred to in subsection (3)(b) is not likely to give (as the case may be)—

(a)the consultation authorities; or

(b)the public—

(i)affected or likely to be affected by; or

(ii)having an interest in,

the plan or programme,

an early and effective opportunity to express their opinion on the plan or programme and the accompanying environmental report, the Scottish Ministers shall, within 7 days of receipt of the advice under subsection (3)(b), specify such other period as the Scottish Ministers consider will give the consultation authorities, or (as the case may be) the public, such an early and effective opportunity.

(5)Where the Scottish Ministers have specified a period under subsection (4), the responsible authority shall specify under section 16(1)(b), or (as the case may be) notify under section 16(2)(a)(iv), that period.

(6)Where the Scottish Ministers are the responsible authority in relation to a qualifying plan or programme, subsections (3)(b), (4) and (5) do not apply.

Commencement Information

I2S. 15 in force at 20.2.2006 by S.S.I. 2006/19, art. 2

16Consultation proceduresS

(1)As soon as reasonably practicable, and in any event within 14 days of the preparation of the environmental report, the responsible authority shall—

(a)send a copy of the report and the qualifying plan or programme to which it relates (“the relevant documents”) to the consultation authorities; and

(b)invite each consultation authority to express its opinion on the relevant documents within such period as the responsible authority may specify.

(2)The responsible authority shall also—

(a)within 14 days of the preparation of the environmental report, secure the publication of a notice—

(i)stating the title of the plan or programme to which it relates;

(ii)stating the address (which may include a website) at which a copy of the relevant documents may be inspected or from which a copy may be obtained;

(iii)inviting expressions of opinion on the relevant documents; and

(iv)stating the address to which, and the period within which, opinions must be sent;

(b)keep a copy of the relevant documents available at the authority's principal office for inspection by the public at all reasonable times and free of charge; and

(c)display a copy of the relevant documents on the authority's website.

(3)The periods referred to in subsections (1)(b) and (2)(a)(iv) must be of such length as will ensure that those to whom the invitation is extended are given an early and effective opportunity to express their opinion on the relevant documents.

(4)Publication of a notice under subsection (2)(a) shall be by such means (including publication in at least one newspaper circulating in the area to which the plan or programme relates) as will ensure that the contents of the notice are likely to come to the attention of the public—

(a)affected by or likely to be affected by; or

(b)having an interest in,

the plan or programme.

(5)Nothing in subsection (2)(a)(ii) shall require the responsible authority to provide a copy of any document free of charge; but where a charge is made, it shall be of a reasonable amount.

Commencement Information

I3S. 16 in force at 20.2.2006 by S.S.I. 2006/19, art. 2

17Account to be taken of environmental report etc.S

In the preparation of a qualifying plan or programme, the responsible authority shall take account of—

(a)the environmental report for that plan or programme;

(b)every opinion expressed in response to the invitations referred to in section 16(1) and (2)(a)(iii); and

(c)the outcome of any relevant consultation under regulation 14 of the Environmental Assessment of Plans and Programmes Regulations 2004 (S.I. 2004/1633).

Commencement Information

I4S. 17 in force at 20.2.2006 by S.S.I. 2006/19, art. 2

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Notes

Text created by the Scottish Government to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Acts of the Scottish Parliament except those which result from Budget Bills.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources