(1)A relevant planning authority shall secure that any developer contribution it obtains towards the cost of providing the authorised works is paid to the burdened undertaker within 12 months of its receipt.
(2)A developer contribution that is not paid to the burdened undertaker within 12 months of its receipt as required by subsection (1) shall on the expiry of that period be repayable to the person from whom it was obtained.
(3)For the purposes of this section the burdened undertaker is a person or persons to whose account is debited the capital cost of constructing the authorised works, or any debt or other charge or encumbrance in respect of or by way of funding for such cost and who is—
(a)notified from time to time by the authorised undertaker to the relevant planning authority as the burdened undertaker to whom developer contributions should be paid, and if more than one in what proportions; or
(b)in the absence of such notification, the authorised undertaker.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: