296.Paragraph 9 requires the local authority to make a final decision in relation to the proposed scheme by either confirming it with or without modifications, or rejecting it, unless the scheme has been called in by the Scottish Ministers.

297.Sub-paragraph (2) lists matters which the local authority is to take into account.

298.Sub-paragraph (3) prohibits a local authority from confirming a scheme with modifications unless it has notified the relevant objectors and anyone else considered to be affected of the proposed modifications at least 28 days before confirming the scheme, given them an opportunity to make objections about the proposed modifications, and considered any objections made.

Back to top

Options/Help

Print Options

Close

Explanatory Notes

Text created by the Scottish Government to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Acts of the Scottish Parliament except those which result from Budget Bills.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources