39Final certificates

This section has no associated Explanatory Notes

(1)Where the controlled reservoir is being constructed or is subject to alteration but is not being discontinued or abandoned, the construction engineer must give the reservoir manager a final certificate not later than 28 days after being satisfied that the reservoir is sound and satisfactory and may safely be used for the collection and storage of water.

(2)A final certificate given under subsection (1)—

(a)must state that the engineer considers the reservoir is sound and satisfactory and may safely be used for the collection and storage of water,

(b)where the reservoir is a high-risk reservoir and the construction engineer considers that there should be an early inspection of the reservoir, must state when the engineer recommends the inspection should take place,

(c)where the reservoir is a high-risk reservoir or medium-risk reservoir, must specify any matter the construction engineer considers should be monitored, until the first inspection of the reservoir under section 46, by the supervising engineer appointed in relation to the reservoir under section 49,

(d)impose the requirements mentioned in subsection (7).

(3)Where the reservoir is being discontinued, the construction engineer must give the reservoir manager a final certificate, not later than 28 days after being satisfied—

(a)that the discontinuance has been safely completed,

(b)that the resulting structure or area is incapable of holding 10,000 cubic metres of water above the natural level of any part of the surrounding land,

(c)that the resulting structure or area is sound and satisfactory and may safely be used for the collection and storage of water.

(4)A final certificate given under subsection (3) must—

(a)state that the construction engineer is satisfied as to the matters referred to in paragraphs (a) to (c) of that subsection,

(b)impose the requirements mentioned in subsection (7).

(5)Where the reservoir is being abandoned, the construction engineer must give the reservoir manager a final certificate, not later than 28 days after being satisfied—

(a)that the abandonment has been safely completed,

(b)that the resulting structure or area is incapable of filling with water above the natural level of any part of the surrounding land.

(6)A final certificate issued under subsection (5) must state that the engineer is satisfied as to the matters referred to in paragraphs (a) and (b) of that subsection.

(7)The requirements referred to in subsection (2)(d) and (4)(b) are—

(a)that water in the reservoir must not exceed a level specified in the certificate (the “specified level”),

(b)that the reservoir manager must ensure that the level of water does not exceed the specified level,

(c)any requirements the construction engineer considers appropriate as to the manner in which the level of water in the reservoir may be increased or decreased.

(8)A copy of the construction certificate issued in respect of the construction or (as the case may be) alteration must be attached to the final certificate.

(9)The construction engineer must, not later than 28 days after issuing a final certificate, give SEPA a copy of the certificate.

(10)If a final certificate is not issued by the end of the period of 5 years beginning with the date of the first preliminary certificate, the construction engineer must—

(a)not later than 28 days after the expiry of the 5 year period, give the reservoir manager a written statement of the reasons,

(b)at intervals of not more than 12 months thereafter until the final certificate is issued, give the reservoir manager subsequent written statements of the reasons,

(c)not later than 28 days after any such statement is given, give SEPA a copy of the statement.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Show Explanatory Notes for Sections: Displays relevant parts of the explanatory notes interweaved within the legislation content.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Notes

Text created by the Scottish Government to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Acts of the Scottish Parliament except those which result from Budget Bills.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources