Planning (Wales) Act 2015

Section 35 – Duration of planning permission: general

134.This section makes a number of amendments to section 91 of the TCPA 1990 (General condition limiting duration of planning permission) and inserts new subsections (3ZA), (3ZB), (3ZC) and (3ZD).

135.Subsections (3ZA) and (3ZB) apply if planning permission is granted under section 73 of the TCPA 1990 which varies or removes conditions from a previous grant of planning permission. If the section 73 permission is granted without a time limit condition and the previous planning permission was granted subject to a time limit condition, the section 73 permission is granted subject to a deemed time limit condition that the development is started no later than the date on which the previous planning permission required the development to be started. This means that, unless a new period is stated, a new permission under section 73 lasts for the unexpired period of the original permission.

136.Subsection (3ZC) and (3ZD) define the term previous planning permission and section 73 permission.

Yn ôl i’r brig

Options/Help

Print Options

Close

Nodiadau Esboniadol

Text created by the Welsh Government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes accompany all Acts of the National Assembly for Wales.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill