Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):
25.—(1) An approved person who proposes the delegation of their functions to another person under regulation 24(3) must apply for approval to SEPA on a form supplied for that purpose by SEPA, signed by the approved person.
(2) An application for approval under paragraph (1) must, within 28 days of receipt of the application—
(a)be granted where SEPA is satisfied that the proposed delegate, taking into account the factors specified in paragraph (3), is capable of carrying out the functions on behalf of the approved person,
(b)otherwise be refused.
(3) The factors mentioned in paragraph (2)(a) are—
(a)if the proposed delegate is an employee of the producer or the operator of the scheme, the proposed delegate’s level of seniority,
(b)if the proposed delegate is not an employee of the producer or the operator of the scheme, the nature of the proposed delegate’s relationship with the approved person,
(c)the degree of the proposed delegate’s knowledge of, or access to, information necessary for the purposes of carrying out the functions on behalf of the approved person,
(d)any other factor which SEPA reasonably thinks is relevant.
(4) An approval granted in accordance with paragraph (2)(a) may be for such period, or subject to such other conditions, as SEPA may specify.
(5) Where an application for approval is granted in accordance with paragraph (2)(a), SEPA must notify the approved person in writing of this, and of any conditions it has imposed pursuant to paragraph (4), within 28 days of its decision.
(6) SEPA may decide to withdraw approval granted under paragraph (2)(a) and, if such a decision is taken, must serve on the approved person written notice of—
(a)the decision to withdraw approval,
(b)the reasons for the decision,
(c)the date on which the withdrawal takes effect, not being earlier than 28 days from the date of the notice.
(7) If an approved person proposes to revoke a delegation granted under paragraph (2)(a), the person must serve written notice on SEPA of this and of the date when the revocation takes effect, not being earlier than 28 days from the date of the notice.
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Policy Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2012 onwards. Prior to this date these type of notes existed as ‘Executive Notes’ and accompanied Scottish Statutory Instruments from July 2005 until July 2012.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys