The A38 Derby Junctions Development Consent Order 2023

 Help about what version

Pa Fersiwn

  • Y Diweddaraf sydd Ar Gael (Diwygiedig)
  • Gwreiddiol (a wnaed Fel)

Status:

Dyma’r fersiwn wreiddiol (fel y’i gwnaed yn wreiddiol). This item of legislation is currently only available in its original format.

Article 33

SCHEDULE 7LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

(1)(2)(3)
Plot Reference Number shown on land plansPurpose for which temporary possession may be takenRelevant part of the authorised development
Land Plans – Sheet 1
1/3cRequired for the establishment of environmental mitigation and enhancementWork No. 8
1/4aRequired for the establishment of environmental mitigation and enhancementWork No. 8
Land Plans – Sheet 2
2/1aRequired for the establishment of environmental mitigation and enhancementWork No. 8
2/1dRequired for the construction of a northbound merge slip road and construction and realignment of a cycle trackWork No. 3
2/1nRequired for the construction of a link road and the construction and maintenance of a noise barrierWork No. 7
2/1rRequired for the widening of the Brackensdale Avenue east and west underbridges, the alteration of part of the entry and exit lanes off Brackensdale Avenue which connects to the A38 and the reconfiguration of the existing junction between Lyttelton Street and Kingsway Park CloseWork No. 1 and 7
2/1sRequired for the alteration of part of the entry and exit lanes off Brackensdale Avenue which connects to the A38 and works to effect the stopping up of part of the entry and exit lanes off Brackensdale Avenue which connect to the A38Work No. 1
2/1tRequired for works to effect the stopping up of part of the entry and exit lanes off Brackensdale Avenue which connect to the A38Work No. 1
2/1uRequired for the alteration, realignment and grading of highwayWork No. 1
2/3Required for the establishment of environmental mitigation and enhancementWork No. 8
2/6Required for the construction of a cycle track and establishment of environmental mitigation and enhancementWork No. 3 and 8
2/13cRequired to construct a link roadWork No. 7
Land Plans – Sheet 3
3/1aaRequired for the diversion and construction of a utility corridorWork No. 21
3/1b, 3/1c and 3/1dRequired for the alteration, realignment and grading of the A38Work No. 10
3/1g and 3/1hRequired for works to effect the stopping up of the entry and exit lanes of Raleigh Street which connect to the A38; and the improvement and realignment of a cycle trackWork No. 1 and 15
3/1iRequired for the alteration, realignment and grading of highway and the construction, improvement and realignment of a cycle trackWork No. 10 and 15
3/1jRequired for the alteration, realignment and grading of the A38Work No. 10
3/1nRequired for the construction of the A38 and the northbound diverge slip roadWork No. 10 and 11
3/1t and 3/8bRequired for alterations to the access and egress from the filling station and fast-food siteWork No. 16
3/1vRequired for the construction of a new junction for access to and egress from Markeaton Park including a roundabout and a park & ride bus stop; works to effect the stopping up of the entrance to Markeaton Park; new emergency access from Markeaton Park and relocation of the boundary wall to Markeaton ParkWork No. 16
3/4Required for the alteration, realignment and grading of highway and the construction, improvement and realignment of the existing cycle track and access to undertake utility diversion worksWork No. 10, 15 and 22
3/5bRequired for the alteration, realignment and grading of highway and the construction of a southbound merge slip roadWork No. 10 and 14
3/5dRequired for the construction of a temporary construction compoundWork No. 19
3/8a and 3/9aRequired for amendments to the access to and egress from the filling station and fast-food siteWork No. 11
3/15aRequired for the construction and alteration of a private means of accessWork No. 16
Land Plans – Sheet 4
4/1cRequired for the construction of a southbound merge slip road and access to undertake utility diversion worksWork No. 14 and 21
4/1fRequired for the establishment of environmental mitigation and enhancement areasWork No. 20
4/1h and 4/7dRequired to establish environmental mitigation and enhancement areasWork No. 20
4/13bRequired for the establishment of environmental mitigation and enhancement areasWork No. 20
Land Plans – Sheet 5
5/1 and 5/2Required to establish environmental mitigation and enhancement areasWork No. 20
Land Plans – Sheet 7
7/1a, 7/1b, 7/2, 7/1d and7/1cRequired for the reconfiguration of highway and a junctionWork No. 34
7/1f and 7/12Required for the realignment of Ford Land and the reconfiguration of the junction with Lambourn Drive and the alteration of Ford Lane BridgeWork No. 29 and 33
7/6, 7/7a and 7/7bRequired for the construction of flood compensation areaWork No. 31
7/17aRequired for the alteration, realignment and grading of carriageway and the construction of a southbound merge slip road and works to effect the stopping up and diversion of a section of a footpath and works to effect the stopping up and diversion of a private means of accessWork No. 23 and 27
7/14Required for the alteration, realignment and grading of the carriageway and the construction of a southbound merge slip roadWork No. 23 and 27
7/17cRequired for the alteration, realignment and grading of the northbound and southbound lanes of the carriageway and the southbound merge slip roadWork No. 23 and 27
7/9, 7/8, 7/1e, 7/10 and 7/11Required for the realignment of Ford Lane and the reconfiguration of the junction with Lambourn DriveWork No. 33
7/1gRequired for the establishment of environmental mitigation areasWork No. 37
7/1h and 7/1iRequired for alterations to a bridge on Ford LaneWork No. 29
7/1j and 7/13Required for works to stop up a highway and carry out works on a bridgeWork No. 28 and 29
Land Plans – Sheet 8
8/1Required for the erection and accommodation of a temporary works compoundWork No. 32
8/2, 8/3a and 8/3cRequired for the alteration, realignment and grading of the northbound and southbound carriageways and the construction of a southbound merge slip roadWork No. 23 and 27
8/5 and 8/8Required for the alteration, realignment and grading of the northbound and southbound carriageway and alteration and extension to an existing railway bridgeWork No. 23
8/18 and 8/19Required for the realignment and grading of Ford Lane to connect to the Little Eaton RoundaboutWork No. 30
8/10bRequired for the alteration, realignment and grading of the northbound and southbound lanes, construction of a southbound merge slip road and the alteration, realignment and grading of carriagewayWork No. 23, 27 and 30
8/10c and 8/11Required for the construction of a southbound diverge slip road and the alteration, realignment and grading of carriagewayWork No. 26 and 30
8/4h, 8/15, 8/16b, 8/24b and 8/25bRequired for the alteration, realignment and grading of northbound and southbound carriageway, construction of a southbound diverge slip road and the erection and accommodation of a works compoundWork No. 23 and 26
Land Plans – Sheet 9
9/1, 9/2, 9/3 and 9/4Required for the erection and accommodation of a temporary works compoundWork No. 32

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill