Search Legislation

Levelling-up and Regeneration Act 2023

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: Section 114

 Help about opening options

Alternative versions:

Changes to legislation:

There are currently no known outstanding effects for the Levelling-up and Regeneration Act 2023, Section 114. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

114Condition relating to development progress reportsU.K.

This section has no associated Explanatory Notes

(1)TCPA 1990 is amended as follows.

(2)In section 56(3) (time when development begun), after “89,” insert “90B,”.

(3)Before section 91 (including the italic heading before that section) insert—

Development progress reportsU.K.
90BCondition relating to development progress reports in England

(1)This section applies where relevant planning permission is granted for relevant residential development in England.

(2)The relevant planning permission must be granted subject to a condition that a development progress report must be provided to the local planning authority in whose area the development is to be carried out for each reporting period.

(3)The first reporting period in relation to the development is to be a period—

(a)beginning at a prescribed time or by reference to a prescribed event, and

(b)during which the development is begun.

(4)A new reporting period is to begin immediately after the end of a reporting period which is not the last reporting period.

(5)A reporting period which is not the last reporting period is to be a period of 12 months.

(6)The last reporting period is to be a period ending with the day on which the development is completed (subject to any provision made under subsection (9)).

(7)A “development progress report”, in relation to relevant residential development, means a report which sets out—

(a)the progress that has been made, and that remains to be made, towards completing the dwellings the creation of which the development is to involve, as at the end of the reporting period to which the report relates,

(b)the progress which is predicted to be made towards completing those dwellings over each subsequent reporting period up to and including the last reporting period, and

(c)such other information as may be prescribed in regulations under subsection (9).

(8)If relevant planning permission is granted without the condition required by subsection (2), it is to be treated as having been granted subject to that condition.

(9)The Secretary of State may by regulations make provision—

(a)about the form and content of development progress reports;

(b)about when and how development progress reports are to be provided to local planning authorities;

(c)about who may or must provide development progress reports to local planning authorities;

(d)about the provision of development progress reports and other information to local planning authorities where there is a change in circumstances in connection with relevant residential development, such as (for example) where the development is no longer intended to be completed in accordance with—

(i)the relevant planning permission;

(ii)a previous development progress report;

(iii)any timescales specified in a commencement notice given under section 93G;

(e)about when a condition under subsection (2) is to be treated as being discharged;

(f)about when relevant residential development is to be treated as being completed for the purposes of this section.

(10)In this section—

  • relevant planning permission” means planning permission other than—

    (a)

    planning permission granted by a development order;

    (b)

    planning permission granted for development carried out before the grant of that permission;

    (c)

    planning permission granted for a limited period;

    (d)

    planning permission granted by an enterprise zone scheme;

    (e)

    planning permission granted by a simplified planning zone scheme;

  • relevant residential development” means development which—

    (a)

    involves the creation of one or more dwellings, and

    (b)

    is of a prescribed description.

(4)In section 69 (register of applications etc)—

(a)in subsection (1), after paragraph (e) insert—

(f)development progress reports under section 90B;;

(b)in subsection (2), after paragraph (b) insert—

(c)such information as is prescribed with respect to development progress reports under section 90B that are provided to the local planning authority;.

(5)In section 70 (determination of applications: general considerations), in subsection (1)(a), after “sections” insert “90B,”.

(6)In section 73 (determination of applications to develop land after non-compliance), before subsection (4) insert—

(2E)Nothing in this section authorises the disapplication of the condition under section 90B (condition relating to development progress reports in England).

(7)In section 96A (power to make non-material changes to planning permission), before subsection (4) insert—

(3B)The conditions referred to in subsection (3)(b) do not include the condition under section 90B (condition relating to development progress reports in England).

(8)In section 97 (revocation or modification of planning permission), at the end insert—

(9)Subsection (1) does not permit the revocation or modification of the condition under section 90B (condition relating to development progress reports in England).

(9)In section 100ZA(13)(c) (restrictions on power to impose planning conditions in England), as amended by paragraph 3(12) of Schedule 14 to the Environment Act 2021, at the end insert “or the condition under section 90B (condition relating to development progress reports in England)”.

(10)Until paragraph 3(12) of Schedule 14 to the Environment Act 2021 comes into force, section 100ZA(13)(c) has effect as if at the end there were inserted “but do not include the condition under section 90B (condition relating to development progress reports in England)”.

Commencement Information

I1S. 114 in force at 26.12.2023 for specified purposes, see s. 255(3)(a)

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act without Schedules as a PDF

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open the Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Notes

Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources