- Latest available (Revised)
- Original (As made)
There are multiple versions of this provision on screen. These apply to different geographical extents.
The term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Sometimes the text of a provision is changed, but the change(s) only apply to a particular geographical area. In some limited cases where this happens, the editorial team create a version for each different geographical area. Multiple versions are only created in this way where the change in question is a substitution so that there are different versions of the text for the different extents. Insertions and repeals of text do not give rise to such multiple versions.
The Building Regulations 2010, Section 15 is up to date with all changes known to be in force on or before 29 May 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):
15.—(1) This regulation applies where [F1an application for building control approval with full plans has been given to the relevant authority] and paragraph H4 of Schedule 1 imposes requirements in relation to the building work which is the subject of those plans.
(2) Where this regulation applies the [F2relevant authority] shall consult the sewerage undertaker—
(a)as soon as practicable after [F3the application for building control approval with full plans has been given]; and
(b)before issuing any completion certificate in relation to the building work in accordance with regulation 17 F4[F5or 17A].
(3) Where a [F6relevant authority] are required by paragraph (2) to consult the sewerage undertaker they shall—
(a)give to the sewerage undertaker, in a case where the authority are consulting them following [F7the giving of an application for building control approval with full plans], sufficient plans to show whether the work would, if carried out in accordance with those plans, comply with the applicable requirements of paragraph H4 of Schedule 1;
(b)have regard to any views expressed by the sewerage undertaker; and
(c)not [F8grant the application for building control approval] or issue a completion certificate until 15 days have elapsed from the date on which they consulted the sewerage undertaker, unless the sewerage undertaker has expressed its views to them before the expiry of that period.
Extent Information
E1This version of this provision applies to England only; a separate version has been created for Wales only
Textual Amendments
F1Words in reg. 15(1) substituted (E.) (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 7(4)(a) (with regs. 22-24)
F2Words in reg. 15(2) substituted (E.) (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 7(4)(b)(i) (with regs. 22-24)
F3Words in reg. 15(2) substituted (E.) (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 7(4)(b)(ii) (with regs. 22-24)
F4Words in reg. 15(2)(b) substituted (W. for remaining purposes) (19.4.2013) by The Building Regulations &c. (Amendment) (Wales) Regulations 2013 (S.I. 2013/747), regs. 1(4), 6 (with reg. 1(2)(3))
F5Words in reg. 15(2)(b) substituted (E., but only in relation to excepted energy buildings in W.) (9.1.2013) by The Building Regulations &c. (Amendment) Regulations 2012 (S.I. 2012/3119), reg. 8, Sch. 1 (with regs. 1(3), 45-47)
F6Words in reg. 15(3) substituted (E.) (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 7(4)(c)(i) (with regs. 22-24)
F7Words in reg. 15(3) substituted (E.) (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 7(4)(c)(ii) (with regs. 22-24)
F8Words in reg. 15(3) substituted (E.) (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 7(4)(c)(iii) (with regs. 22-24)
15.—(1) This regulation applies where full plans have been deposited with the local authority and paragraph H4 of Schedule 1 imposes requirements in relation to the building work which is the subject of those plans.
(2) Where this regulation applies the local authority shall consult the sewerage undertaker—
(a)as soon as practicable after the plans have been deposited; and
(b)before issuing any completion certificate in relation to the building work in accordance with regulation 17 [F9or 17A].
(3) Where a local authority are required by paragraph (2) to consult the sewerage undertaker they shall—
(a)give to the sewerage undertaker, in a case where the authority are consulting them following the deposit of full plans, sufficient plans to show whether the work would, if carried out in accordance with those plans, comply with the applicable requirements of paragraph H4 of Schedule 1;
(b)have regard to any views expressed by the sewerage undertaker; and
(c)not pass plans or issue a completion certificate until 15 days have elapsed from the date on which they consulted the sewerage undertaker, unless the sewerage undertaker has expressed its views to them before the expiry of that period.
Extent Information
E2This version of this provision applies to Wales only; a separate version has been created for England only
Textual Amendments
F9Words in reg. 15(2)(b) substituted (E., but only in relation to excepted energy buildings in W.) (9.1.2013) by The Building Regulations &c. (Amendment) Regulations 2012 (S.I. 2012/3119), reg. 8, Sch. 1 (with regs. 1(3), 45-47)
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: