Search Legislation

The River Humber Gas Pipeline Replacement Order 2016

Changes to legislation:

There are outstanding changes not yet made by the legislation.gov.uk editorial team to The River Humber Gas Pipeline Replacement Order 2016. Those changes will be listed when you open the content using the Table of Contents below. Any changes that have already been made by the team appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the affected provisions when you open the content using the Table of Contents below.

View outstanding changes

Changes and effects yet to be applied to :

  1. Introductory Text

  2. PART 1 Preliminary

    1. 1.Citation and commencement

    2. 2.Interpretation

    3. 3.Application, modification and disapplication of legislative provisions

  3. PART 2 Works Provisions

    1. 4.Development consent, etc. granted by Order

    2. 5.Maintenance of authorised project

    3. 6.Operation of authorised project

    4. 7.Limits of deviation

    5. 8.Defence to proceedings in respect of statutory nuisance

    6. 9.Benefit of Order

    7. 10.Transfer of benefit of Order

    8. 11.Street Works

    9. 12.Power to alter layout, etc. of streets

    10. 13.Construction and maintenance of new, altered or diverted streets

    11. 14.Temporary stopping up of streets and public rights of way

    12. 15.Access to works

    13. 16.Traffic Regulation

    14. 17.Agreements with street authorities

    15. 18.Discharge of water

    16. 19.Authority to survey and investigate the land

    17. 20.Removal of human remains

  4. PART 3 Acquisition and possession of land

    1. 21.Compulsory acquisition of land

    2. 22.Compulsory acquisition of rights

    3. 23.Extinguishment and suspension of private rights

    4. 24.Acquisition of subsoil only

    5. 25.Power to override easements and other rights

    6. 26.Application of the Compulsory Purchase (Vesting Declarations) Act 1981

    7. 27.Temporary use of land for carrying out the authorised project

    8. 28.Temporary use of land for maintaining the authorised project

    9. 29.Disregard of certain interests and improvements

    10. 30.Set-off for enhancement in value of retained land

    11. 31.No double recovery

    12. 32.Acquisition of part of certain properties

    13. 33.Statutory undertakers

    14. 34.Recovery of costs of new connections

    15. 35.Time limit for exercise of authority to acquire land compulsorily

    16. 36.Rights under or over streets

    17. 37.Incorporation of the mineral code

  5. PART 4 Miscellaneous and general

    1. 38.Application of landlord and tenant law

    2. 39.Deemed consent under Part 4 (marine licensing) of the Marine and Coastal Access Act 2009

    3. 40.Operational land for purposes of the 1990 Act

    4. 41.Felling or lopping of trees or shrubs

    5. 42.Protective provisions

    6. 43.Crown rights

    7. 44.Certification of plans etc.

    8. 45.Service of notices

    9. 46.Arbitration

    10. 47.Procedure in relation to certain approvals etc.

  6. Signature

    1. SCHEDULE 1

      Authorised project

      1. PART 1 Authorised development

        1. 1.A nationally significant infrastructure project as defined in sections 14...

      2. PART 2 Further associated development and ancillary works

        1. 2.Such associated development and ancillary works within the Order limits...

    2. SCHEDULE 2

      Plans

      1. PART 1 Works plans

      2. PART 2 Land plans

      3. PART 3 Access and rights of way plans

      4. PART 4 Environmental statement

    3. SCHEDULE 3

      Requirements

      1. 1.Interpretation

      2. 2.Time limits

      3. 3.Stages of the authorised project

      4. 4.Detailed design approval

      5. 5.Site Water Management Plan

      6. 6.Site Waste Management Plan

      7. 7.Removal of trees and hedgerows

      8. 8.Hard landscaping and drainage

      9. 9.Agricultural land drainage

      10. 10.Archaeology

      11. 11.Construction hours

      12. 12.Construction Environmental Management Plan

      13. 13.Noise

      14. 14.Contaminated land and groundwater

      15. 15.Construction traffic and accesses

      16. 16.Restoration of land used temporarily for construction

      17. 17.Temporary external lighting

      18. 18.Environmental mitigation land

      19. 19.Ecological Surveys

      20. 20.Requirement for written approval

      21. 21.Approved details and amendments to approved details

    4. SCHEDULE 4

      Streets subject to street works

    5. SCHEDULE 5

      Streets subject to alteration of layout

    6. SCHEDULE 6

      Streets and public rights of way to be temporarily stopped up

    7. SCHEDULE 7

      Access to works

    8. SCHEDULE 8

      Land of which temporary possession may be taken

    9. SCHEDULE 9

      Deemed marine licence under Part 4 (Marine licensing) of the Marine and Coastal Access Act 2009

      1. PART 1 Introduction

        1. 1.Interpretation

        2. 2.Addresses

      2. PART 2 Licensed activities

        1. 3.(1) Subject to the licence conditions in Part 4 of...

      3. PART 3 Conditions

        1. 4.The licence holder must inform the MMO in writing of...

        2. 5.Should the licence holder become aware that any of the...

        3. 6.The licence holder must ensure that any coatings and treatments...

        4. 7.The licence holder must ensure that any equipment, temporary structures,...

        5. 8.The licence holder must ensure that the MMO local Marine...

        6. 9.The licence holder must notify the MMO in writing of...

    10. SCHEDULE 10

      Protective provisions

      1. PART 1 For the protection of electricity, gas, water and sewerage undertakers

        1. 1.Application

        2. 2.Interpretation

        3. 3.On-street apparatus

        4. 4.Acquisition of apparatus

        5. 5.Removal of apparatus

        6. 6.Retained apparatus: protection

        7. 7.Cathodic protection testing

        8. 8.Expenses

        9. 9.Co-operation

        10. 10.Arbitration

      2. PART 2 For the protection of operators of Electronic Communication Code Networks

        1. 1.Effect

        2. 2.Interpretation

        3. 3.On-street apparatus

        4. 4.Enactments and agreements in respect of apparatus in the undertaker’s land

        5. 5.Arbitration

      3. PART 3 For the protection of the Environment Agency

        1. 1.(1) The following provisions apply for the protection of the...

        2. 2.(1) Before beginning to construct any specified work, the undertaker...

        3. 3.Without limiting the scope of paragraph 17, the requirements which...

        4. 4.(1) Subject to sub-paragraph (2), any specified work, and all...

        5. 5.(1) Subject to sub-paragraph (5) the undertaker must from the...

        6. 6.If by reason of the construction of any specified work...

        7. 7.(1) The undertaker must indemnify the Agency in respect of...

        8. 8.The fact that any work or thing has been executed...

        9. 9.(1) The undertaker will not in the exercise of any...

        10. 10.Any dispute arising between the undertaker and the Agency under...

        11. 11.(1) Any specified work capable of interfering with or risking...

        12. 12.Within the Order limits on the south bank of the...

      4. PART 4 For the protection of Anglian Water

        1. 1.(1) For the protection of Anglian Water, the following provisions...

      5. PART 5 For the protection of Centrica

        1. 1.For the protection of Centrica the following provisions, unless otherwise...

        2. 2.Interpretation

        3. 3.Creation of rights and access for Centrica

        4. 4.Apparatus

        5. 5.Ground Subsidence Monitoring Scheme

        6. 6.Cathodic Protection Testing

        7. 7.(1) In the event that the undertaker uses an alternative...

        8. 8.Removal of apparatus

        9. 9.Facilities and rights for alternative apparatus

        10. 10.Costs

        11. 11.Requirement for agreement

        12. 12.Disputes

    11. SCHEDULE 11

      Modification of compensation and compulsory purchase enactments for the creation of new rights

      1. 1.Compensation enactments

      2. 2.(1) Without prejudice to the generality of paragraph 1, the...

      3. 3.Application of the 1965 Act

      4. 4.For section 7 of the 1965 Act (measure of compensation)...

      5. 5.The following provisions of the 1965 Act (which state the...

      6. 6.Section 11 of the 1965 Act (powers of entry) is...

      7. 7.Section 20 of the 1965 Act (protection for interests of...

      8. 8.Section 22 of the 1965 Act (protection of acquiring authority’s...

    12. SCHEDULE 12

      Procedure in relation to certain approvals etc.

      1. 1.Determination of applications for specified consents

      2. 2.Fees

      3. 3.Appeals

      4. 4.Outcome of Appeals

      5. 5.Interpretation of this Schedule

  7. Explanatory Note

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources