4. After section 13 insert—
13A.—(1) This section defines certain terms used in this Part.
(2) “The EIA Directive” means Directive 2011/92/EU of the European Parliament and of the Council of 13 December 2011 on the assessment of the effects of certain public and private projects on the environment.
(3) “EIA information”, in relation to an application under section 6, or proposal under section 7, for an EIA order, means—
(a)the environmental statement,
(b)any other information which the Secretary of State reasonably requires for the purpose of reaching a reasoned conclusion (see section 13B), and
(c)any representations made by any person about the environmental effects of the proposed works or other projects.
(4) “EIA order” means an order authorising works or other projects—
(a)which are—
(i)in a class listed in Annex I to the EIA Directive, or
(ii)in a class listed in Annex II to the EIA Directive and, by virtue of their nature, size or location, likely to have significant effects on the environment, and
(b)which are not exempt works.
(5) For the purposes of subsection (4), works or other projects are exempt if the Secretary of State directs or decides (in accordance with rules made under section 6) that an environmental impact assessment is not required in respect of those works or projects.
(6) “Environmental statement” means a statement which, by rules under section 6, is required—
(a)to accompany an application for, or be prepared in connection with the publication of a proposal to make, an EIA order, and
(b)amongst other matters, to set out the likely significant effects of the implementation of the EIA order applied for or proposed on the environment.
(7) “Reasoned conclusion” means a reasoned conclusion under section 13B(1)(b).
13B.—(1) Before making a determination under section 13(1) in respect of an application or proposal for an EIA order, the Secretary of State—
(a)must consider the EIA information, and
(b)following that consideration, must reach a reasoned conclusion about the likely significant effects of the proposed works or other projects on the environment.
(2) The Secretary of State must obtain such expert advice as appears to the Secretary of State to be necessary for the purposes of considering the environmental statement.
(3) When making a determination under section 13(1) in respect of an application or proposal for an EIA order, the Secretary of State must take into account the reasoned conclusion.
(4) But the Secretary of State may determine to make an EIA order (whether with or without modifications) only if satisfied that the reasoned conclusion is up to date.
13C.—(1) If the Secretary of State proposes to make an EIA order (whether with or without modifications), the Secretary of State must consider whether monitoring of the significant adverse effects of the works or other projects on the environment to be authorised by the order is appropriate and, if so, must consider—
(a)whether it is appropriate to impose a monitoring measure, and
(b)whether it is appropriate to impose a requirement to take remedial action.
(2) In this section, “monitoring measure”, in relation to proposed works or other projects, means a requirement to monitor any significant adverse effects of the works or projects on the environment.
(3) For the purposes of subsection (1)(a), the Secretary of State must take into account any monitoring arrangements which are required to be carried out under the law of any part of the United Kingdom (other than a provision implementing the EIA Directive).
(4) The Secretary of State may impose a monitoring measure or a requirement to take remedial action in the EIA order or, if the Secretary of State gives a direction under section 90(2A) of the Town and Country Planning Act 1990 on the making of the EIA order, by way of condition specified in that direction.
(5) But the Secretary of State may impose a monitoring measure only if satisfied that the type of parameters which will be required to be monitored and the duration of such monitoring are proportionate having regard to—
(a)the nature, location and size of the proposed works or other projects, and
(b)the significance of the effects of the works or other projects on the environment.
13D. The Secretary of State must make a determination under section 13(1) in relation to an application or proposal for an EIA order within a reasonable period of time (having regard to the nature and complexity of the works or other project to which it relates) beginning on the day on which the Secretary of State has all of the information necessary to reach the reasoned conclusion.”
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: