Local Government (Wales) Measure 2011

Timetable for implementation of change to mayor and cabinet executive

This section has no associated Explanatory Notes

6(1)This paragraph applies to a local authority’s proposals if the proposed form of executive is a mayor and cabinet executive (and accordingly is subject to approval in a referendum).

(2)The timetable with respect to the implementation of the proposals must comply with sub-paragraphs (3) and (4).

(3)The timetable must be such as to secure that the local authority will hold the referendum within the period that—

(a)begins two months after, and

(b)ends six months after,

the day on which the local authority sends the Welsh Ministers the copy of the proposals.

(4)The timetable must be such as to secure that, if the result of the referendum is to approve the change to executive arrangements, the local authority will make that change within the period of six months beginning with the day on which the referendum is held.