PART 5MOVEMENT OF HAZARDOUS WASTE

Packaging and labelling

Removal of wastes by pipeline

30.—(1) This regulation applies where hazardous waste is removed from any premises (other than a ship) on which it is produced or stored by pipeline other than in a case to which regulation 28 or 29 applies.

(2) Before the waste is first piped, and, where the piping is continuous and exceeds one quarter in duration, at the commencement of each further quarter the producer, or holder, as the case may be, shall ensure that—

(a)one copy of the consignment note is prepared for each of the following: the producer or holder, as the case may be, where different from the consignor, the consignor, the consignee and the Department;

(b)on each of the copies Parts A, B and D are completed, provided that in Part B5 the average flow rate shall be recorded, together with an estimate of the total volume of waste to be piped per week or calendar month.

(3) Part C shall not be completed.

(4) Subject to regulation 31, the consignee shall complete Part E on each copy of the note, the application of which is modified as follows—

(a)in Part E1, the reference to the date on which the waste was received shall be taken to be a reference to the last date on which waste was received by the consignee pursuant to that consignment note; and

(b)in Part E3, the particulars of the vehicle registration are not required.

(5) The consignee shall retain one copy of the consignment note and ensure that a copy is given to the consignor, to the hazardous waste producer or holder, where different from the consignor, and to the Department.