Regulation 11(1)

SCHEDULE 6N.I.PARTICULARS TO BE INCLUDED IN A SAFETY CASE FOR THE DISMANTLING OF A FIXED INSTALLATION

1.  The name and address of the operator of the installation.N.I.

Commencement Information

I1Sch. 6 para. 1 in operation at 21.5.2007, see reg. 1

2.  The dates on which dismantling is expected to commence and finish.N.I.

Commencement Information

I2Sch. 6 para. 2 in operation at 21.5.2007, see reg. 1

3.  A summary of how any safety representatives for that installation were consulted with regard to the revision of the safety case pursuant to regulation 23(2)(c)(i) of the Offshore Installations (Safety Representatives and Safety Committees) Regulations 1989.N.I.

Commencement Information

I3Sch. 6 para. 3 in operation at 21.5.2007, see reg. 1

4.  The maximum number of persons expected to be on the installation at any time during its dismantling.N.I.

Commencement Information

I4Sch. 6 para. 4 in operation at 21.5.2007, see reg. 1

5.  A description of how the duty holder will comply with regulation 4(1) of the PFEER Regulations with regard to the dismantling of the installation.N.I.

Commencement Information

I5Sch. 6 para. 5 in operation at 21.5.2007, see reg. 1

6.  A description of arrangements made for protecting persons on the installation from toxic gas at all times other than during any period while they may need to remain on the installation following an incident which is beyond immediate control.N.I.

Commencement Information

I6Sch. 6 para. 6 in operation at 21.5.2007, see reg. 1

7.  A description of how the proposed arrangements, methods and procedures for dismantling the installation and connected pipelines take adequate account of the design and method of construction of the installation and its plant.N.I.

Commencement Information

I7Sch. 6 para. 7 in operation at 21.5.2007, see reg. 1