Search Legislation

The Renewables Obligation Order (Northern Ireland) 2009

Status:

This is the original version (as it was originally made).

  1. Introductory Text

  2. PART 1 Introductory Provisions

    1. 1.Citation and commencement

    2. 2.Interpretation

    3. 3.Waste as a renewable energy source

    4. 4.Biomass and fuels which are to be treated as biomass

  3. PART 2 The Renewables Obligation

    1. 5.The renewables obligation

    2. 6.Part of calculation A referable to Great Britain

    3. 7.Part of calculation A referable to Northern Ireland

    4. 8.Calculation A

    5. 9.Calculation B

    6. 10.Calculation C

    7. 11.Determining the number of renewables obligation certificates to be produced in an obligation period

    8. 12.Determining the number of renewables obligation certificates to be produced by a designated electricity supplier in order to discharge his renewables obligation

    9. 13.Further provision in relation to the production of renewables obligation certificates

  4. PART 3 Matters to be certified by and content of NIROCs

    1. 14.Matters to be certified by NIROCs

    2. 15.When electricity is to be regarded as supplied to customers in Northern Ireland

    3. 16.When electricity used in a permitted way for NIROCs certifying matters within Article 54(5) or (6) of the Energy Order

  5. PART 4 Cases and circumstances when a NIROC must not be issued

    1. 17.Excluded generating stations

    2. 18.Generating stations first commissioned before 1st January 1990

    3. 19.Generating stations in respect of which a NFFO arrangement applied but was terminated

    4. 20.Non-commissioned generating stations in respect of which a NFFO arrangement applies

    5. 21.Circumstances in which no NIROCs are to be issued in respect of electricity generated from renewable sources

  6. PART 5 NIROCs to be issued by Authority in respect of renewable output

    1. 22.NIROCs to be issued by Authority in respect of a generation station’s renewable output

    2. 23.Calculating a generating station’s renewable output

    3. 24.Renewable output of a qualifying combined heat and power generating station

  7. PART 6 Banding and Grandfathering

    1. 25.The amount of electricity to be stated in each NIROC

    2. 26.Qualifying combined heat and power generating stations

    3. 27.Microgenerators

    4. 28.Generating stations which were accredited as at 11th July 2006

    5. 29.Generating stations which were accredited, or held preliminary accreditation, as at 31st March 2009

    6. 30.Generating stations in respect of which a statutory grant has been awarded

    7. 31.Review of banding provisions

  8. PART 7 Issue and Revocation of NIROCs

    1. 32.Issue of NIROCs to generators and suppliers

    2. 33.Issue of NIROCs to agents

    3. 34.General criteria for the issue of NIROCs

    4. 35.Further criteria applicable to NIROCs certifying matters within Article 54(3) and (4) of the Energy Order

    5. 36.Further criteria applicable to NIROCs certifying matters within Article 54 (4) and (6) of the Energy Order

    6. 37.Refusing to issue and revoking NIROCs

    7. 38.NIROCs: financial bids

  9. PART 8 Payments to discharge the renewables obligation, dealing with the buy-out and late payment funds

    1. 39.Interpretation

    2. 40.Payments to discharge the renewables obligation

    3. 41.Late Payments to discharge the renewables obligation

    4. 42.Dealing with the buy-out fund: payments into the Consolidated Fund and to the Great Britain authority

    5. 43.Dealing with the late payment fund: payments into the Consolidated Fund and to the Great Britain authority

    6. 44.Dealing with the buy-out and late payment funds: payments to United Kingdom suppliers

  10. PART 9 Provision of information, functions of the Authority and modifications of this Order in relation to microgenerators in certain circumstances

    1. 45.Provisions of information to the Authority

    2. 46.Information to be provided to the Authority where electricity is generated from biomass

    3. 47.Provision of information to the Department

    4. 48.Exchange of information with the Great Britain authority

    5. 49.Functions of the Authority

    6. 50.Preliminary accreditation and accreditation of generating stations

    7. 51.NIROC Register

    8. 52.Modification of this Order in relation to microgenerators in certain circumstances

    9. 53.Revocation, transitional and savings

  11. Signature

    1. SCHEDULE 1

      CALCULATION OF THE OBLIGATION

    2. SCHEDULE 2

      ELECTRICITY TO BE STATED IN NIROCs

      1. PART 1 INTERPRETATION

        1. 1.(1) In this Schedule— “AD” means electricity generated from gas...

      2. PART 2 AMOUNT OF ELECTRICITY TO BE STATED IN NIROCs GENERALLY

      3. PART 3 AMOUNT OF ELECTRICITY TO BE STATED IN NIROCs WHERE ARTICLE 28(3) APPLIES

      4. PART 4 AMOUNT OF ELECTRICITY TO BE STATED IN NIROCs WHERE ARTICLE 28(5) OR ARTICLE 29(4) APPLIES

    3. SCHEDULE 3

      The NIROC Register

      1. 1.The Authority must maintain the Register referred to in Article...

      2. 2.The Register must identify whether or not a NIROC subsists...

      3. 3.Particulars of a NIROC comprise— (a) the name of the...

      4. 4.A person may only be the registered holder of a...

      5. 5.The Authority may from time to time draw up procedural...

      6. 6.The Authority must delete from the Register—

      7. 7.Where the registered holder of a NIROC and a person...

      8. 8.Where the Authority receives requests under paragraph 7(a) it must...

      9. 9.Where— (a) a NIROC is issued under this Order, or...

      10. 10.The substitute cannot be the registered holder of a NIROC...

      11. 11.The Register may be amended by a decision of the...

      12. 12.The contents of the Register (including the entries referred to...

      13. 13.Where any person considers that an entry maintained in respect...

      14. 14.The Authority must in any procedural guidelines which it produces...

      15. 15.“Banking day” means a day on which banks are generally...

  12. Explanatory Note

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources