Search Legislation

The Renewables Obligation (Scotland) Order 2007

Draft Legislation:

This is a draft item of legislation. This draft has since been made as a Scottish Statutory Instrument: The Renewables Obligation (Scotland) Order 2007 No. 267

PART 4Alternative Ways of Discharging Renewables Obligation

Alternative way of discharging renewables obligation: payments

11.—(1) Instead of producing certificates pursuant to article 3, a designated electricity supplier may discharge (in whole or in part) its renewables obligation in relation to a particular obligation period by making a payment to the Authority before the specified day relating to that obligation period.

(2) Subject to paragraphs (3) to (6), the payment to be made under paragraph (1) is £34.30 for each megawatt hour of electricity generated from eligible renewable sources for which the designated electricity supplier does not produce certificates pursuant to article 3, 13, 14 or NIROCs pursuant to article 12 (“the buy-out price”).

(3) If, in the case of the calendar year 2007 or any subsequent calendar year, the annual retail prices index for that year (“the later year”) is higher or lower than that for the previous year, the buy-out price relating to the obligation period beginning on the 1st April immediately following the later year shall be increased (if the index is higher) or decreased (if the index is lower) by the annual percentage inflation rate of the retail prices index for the later year.

(4) When the buy-out price is calculated under paragraph (3) the result shall be rounded to the nearest penny (with any exact half of a penny being rounded upwards).

(5) Where a designated electricity supplier does not produce certificates pursuant to articles 3, 13 or 14 as evidence that it or another electricity supplier has complied with the minimum wave requirement, if any, of its renewables obligation, the payment to be made under paragraph (1) is £175 for each megawatt hour of electricity for which no such certificate is produced (“the wave buy-out price”).

(6) Where a designated electricity supplier does not produce certificates pursuant to articles 3, 13 or 14 as evidence that it or another electricity supplier has complied with the minimum tidal requirement, if any, of its renewables obligation, the payment to be made under paragraph (1) is £105 for each megawatt hour of electricity for which no such certificate is produced (“the tidal buy-out price”).

Alternative way of discharging renewables obligation: NIROCs

12.—(1) Subject to article 15, instead of producing certificates pursuant to article 3, a designated electricity supplier may discharge (in whole, except to the extent of the minimum wave or tidal requirement, or in part) its renewables obligation in relation to a particular obligation period by producing to the Authority in accordance with this article eligible NIROCs issued in respect of electricity that has been supplied to customers during that obligation period.

(2) A NIROC referred to in paragraph (1) shall be regarded as produced to the Authority in respect of an obligation period where, before the specified day relating to that period, the Authority receives, from the designated electricity supplier which is treated as holding the NIROC for the purposes of the NIRO Order under which it was issued, a notification in writing identifying the NIROC to be so produced and giving its NIROC identifier.

(3) Without prejudice to paragraph (2), the Authority may draw up procedural guidelines for the production of NIROCs under this article.

Alternative way of discharging renewables obligation: certificates certifying the matters in section 32B(2A) or (2AA) of the Act

13.—(1) Subject to article 15, instead of producing certificates pursuant to article 3, a designated electricity supplier may discharge (in whole or in part) its renewables obligation in relation to a particular obligation period by producing to the Authority in accordance with this article certificates issued by the Authority and certifying the matters in section 32B(2A) or (2AA) of the Act, provided that such certificates relate to electricity generated from eligible renewable sources.

(2) A certificate referred to in paragraph (1) shall be regarded as produced to the Authority in respect of an obligation period where, before the specified day relating to that period the Authority receives from the designated electricity supplier which holds the certificate, a notification in writing identifying the certificate to be produced for that purpose and, in the case of a SROC, the SROC identifier.

(3) Without prejudice to paragraph (2), the Authority may draw up procedural guidelines for the production of certificates under this article.

Alternative way of discharging renewables obligation: certificates certifying the matters in section 32B(2AB) or (2AC) of the Act

14.—(1) Subject to article 15, instead of producing certificates pursuant to article 3, a designated electricity supplier may discharge (in whole or in part) its renewables obligation in relation to a particular obligation period by producing to the Authority in accordance with this article certificates issued by the Authority and certifying the matters in section 32B(2AB) or (2AC) of the Act.

(2) A certificate referred to in paragraph (1) shall be regarded as produced to the Authority in respect of an obligation period where before the specified day relating to that period the Authority receives from the designated electricity supplier which holds the certificate a notification in writing identifying the certificate to be produced for that purpose and, in the case of a SROC, the SROC identifier.

(3) Without prejudice to paragraph (3), the Authority may draw up procedural guidelines for the production of certificates under this article.

(4) For the purposes of section 32B(2AB) and (2AC) of the Act, electricity generated by any generating station is used in a permitted way if it is used in one of the ways mentioned in section 32B(2AE) of the Act.

Further provision in relation to production of certificates and NIROCs

15.—(1) A designated electricity supplier may discharge up to 25 per cent of its renewables obligation in respect of an obligation period by producing to the Authority certificates issued by the Authority under section 32B of the Act and eligible NIROCs relating to electricity supplied in the immediately preceding obligation period.

(2) Subject to paragraph (3), in respect of any obligation period which falls–

(a)from 1st April 2007 until 31st March 2011, no more than 10 per cent; and

(b)from 1st April 2011 until 31st March 2016, no more than 5 per cent,

of a designated electricity supplier’s renewables obligation may be satisfied by the production of certificates issued by the Authority under section 32B of the Act and eligible NIROCs issued in respect of generating stations which during the month to which a certificate or NIROC relates, have been fuelled partly by fossil fuel (as defined in article 9) and partly by biomass and by no other fuel.

(3) In the case of certificates or NIROCs issued in respect of a generating station which, during the month to which those certificates or NIROCs relate, has been fuelled partly by fossil fuel (as defined in article 9) and partly by biomass consisting in whole or in part of energy crops (and no other fuel), the limits set out in paragraph (2) shall not apply to the production of those certificates or NIROCs if and to the extent that they state the amount of electricity which is attributable to the energy crops.

(4) A designated electricity supplier shall not produce to the Authority a certificate issued under section 32B of the Act or a NIROC which has previously been or is simultaneously produced to the Northern Ireland Authority under a NIRO Order.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Draft Executive Notes

Draft Executive Note sets out a brief statement of the purpose of a Draft Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Draft Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2005 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources