The Storage of Carbon Dioxide (Licensing etc.) (Scotland) Regulations 2011

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)
 Help about advanced features

Advanced Features

Changes over time for: Storage permits

 Help about opening options

Alternative versions:

Changes to legislation:

There are outstanding changes not yet made by the legislation.gov.uk editorial team to The Storage of Carbon Dioxide (Licensing etc.) (Scotland) Regulations 2011. Any changes that have already been made by the team appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to Part 3:

Changes and effects yet to be applied to the whole Instrument associated Parts and Chapters:

Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):

Storage permitsS

Applications for a storage permitS

6.—(1) The licence holder may, under the conditions laid down by the licence, apply to the authority for a storage permit in respect of a place within the licensed area.

(2) Where the licence includes an appraisal term, the application may not be made unless any necessary exploration has been completed, and the terms and conditions of the licence have been complied with.

(3) An application must contain—

(a)the name and address of the proposed operator;

(b)evidence of the matters referred to in regulation 7(1);

(c)in relation to the CO2 that is to be contained within the storage site—

(i)the total quantity that is to be injected and stored;

(ii)a proposed date on which injection is to commence;

(iii)the prospective sources and transport methods;

(iv)the composition of the CO2 streams that are to be injected;

(v)the proposed injection rates and pressures; and

(vi)the proposed location of the injection facilities;

(d)a description of measures to be taken to prevent any significant irregularities;

(e)a proposed monitoring plan drawn up in accordance with Annex II to the Directive and that takes into account the obligations imposed on the operator under legislation implementing Article 14 of the ETS Directive;

(f)a proposed corrective measures plan;

(g)the proposed provisional post-closure plan drawn up in accordance with regulation 12(1);

(h)the information required to be provided in relation to the storage site under legislation implementing Article 5 of Council Directive 85/337/EEC M1; and

(i)details of a financial security that will satisfy the requirements in paragraph 7(1) of Schedule 2, including proof that (if the storage permit is granted) such a security will be in force before the proposed date on which injection is to commence.

(4) The authority must forward to the European Commission—

(a)the permit application (within one month of receipt); and

(b)any other related material that the authority proposes to take into account when it seeks to make a decision on the award of a storage permit.

Marginal Citations

M1Council Directive 85/337/EEC of 27 June 1985 on the assessment of the effects of certain public and private projects on the environment (O.J. No. L 175, 5.7.1985, p.40); amended by Council Directive 97/11/EC (O.J. No. L 73, 14.03.1997, p.5) and by European Parliament and Council Directives 2003/35/EC (O.J. No. L 156, 25.6.2003, p.17) and 2009/31/EC.

Grant of storage permitsS

7.—(1) Before granting a storage permit the authority must be satisfied that—

(a)the storage complex and surrounding area have been sufficiently characterised and assessed in accordance with the criteria set out in Annex I to the Directive;

(b)no part of the storage complex extends beyond the territories of the member States;

(c)under the proposed conditions of use of the storage site, there is no significant risk of leakage or of harm to the environment or human health; and

(d)the conditions in paragraph (3) are met.

(2) For the purposes of paragraph (1)(b), the territory of a member State includes its exclusive economic zone and continental shelf within the meaning of Articles 55 and 76 of the United Nations Convention on the Law of the Sea M2.

(3) The conditions are that the proposed operator—

(a)is technically competent (including in the operation of environmental management systems), financially sound and can be relied upon to carry out the functions of an operator; and

(b)has in place an appropriate programme of professional and technical development and training.

(4) Where more than one storage site is contained within the same hydraulic unit, before granting a storage permit for either site the authority must be satisfied that the requirements for the grant of a permit can be met simultaneously.

(5) In considering the application for the storage permit the authority may—

(a)approve the proposed monitoring plan; or

(b)require the applicant to make such modifications to it as the authority (after consulting the applicant) considers necessary,

and (if the permit is granted) the monitoring plan is the plan as so approved or modified.

(6) In considering the application for the storage permit the authority may—

(a)approve the proposed corrective measures plan; or

(b)require the applicant to make such modifications to it as the authority (after consulting the applicant) considers necessary,

and (if the permit is granted) the corrective measures plan is the plan as so approved or modified.

(7) If the authority is minded to grant a storage permit—

(a)the authority must forward a draft of the proposed permit to the European Commission, together with any material taken into consideration that has not already been provided under regulation 6(4); and

(b)the authority must before granting the permit consider any opinion on the draft that is issued under Article 10(1) of the Directive.

Marginal Citations

M2Cmnd. 8941.

Content of storage permitsS

8.—(1) A storage permit must include—

(a)the name and address of a person who is a licence holder and who is designated as the operator of the site;

(b)the precise location and delimitation of the storage site and the storage complex, and any relevant information concerning the hydraulic unit;

(c)the operational requirements for storage, including—

(i)the total quantity of CO2 authorised to be stored;

(ii)the reservoir pressure limits; and

(iii)the maximum injection rates and pressures;

(d)the provisions in Schedule 2;

(e)any requirements in addition to those in Schedule 2 relating to injection and storage that the authority considers necessary, in particular to prevent significant irregularities;

(f)requirements designed to prevent any undue interference with other uses of the area surrounding the storage site;

(g)the corrective measures plan;

(h)the conditions for closure of the storage site; and

(i)the provisional post-closure plan.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Executive Note

Executive Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2005 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources