CHAPTER 3Ongoing obligations relating to other matters

Ongoing obligations: general

34.  Participants must comply with the following ongoing obligations, as applicable—

(a)they must keep and provide upon request by the Authority records of type of fuel used and fuel purchased for the duration of their participation in the scheme;

(b)they must keep and provide upon request by the Authority written records of fossil fuel used for the permitted ancillary purposes specified in Chapters 1 and 2;

(c)they must submit an annual declaration as requested by the Authority confirming, as appropriate, that they are using their accredited RHI installations in accordance with the eligibility criteria and are complying with the relevant ongoing obligations;

(d)they must notify the Authority if any of the information provided in support of their application for accreditation or registration was incorrect;

(e)they must ensure that their accredited RHI installation continues to meet the eligibility criteria;

(f)they must comply with any condition attached to their accreditation or registration;

(g)they must keep their accredited RHI installation maintained to the Authority’s satisfaction and keep evidence of this including service and maintenance documents;

(h)participants combusting biogas must not deliver heat by air from their accredited RHI installation to the biogas production plant producing the biogas used for combustion;

(i)they must allow the Authority or its authorised agent reasonable access in accordance with Part 9;

(j)participants generating heat from solid biomass must comply with the regulation specified by the Authority in accordance with regulation 22(6)(e);

(k)they must notify the Authority within 28 days where they have ceased to comply with an ongoing obligation or have become aware that they will not be able so to comply, or where there has been any change in circumstances which may affect their eligibility to receive periodic support payments;

(l)they must notify the Authority within 28 days of the addition or removal of a plant supplying heat to a heating system of which their accredited RHI installation forms part;

(m)they must notify the Authority within 28 days of a change in ownership of all or part of their accredited RHI installation;

(n)they must repay any overpayment in accordance with any notice served under regulation 48;

(o)they must, if requested, provide evidence that the heat for which periodic support payments are made is used for an eligible purpose;

(p)they must not generate heat for the predominant purpose of increasing their periodic support payments;

(q)they must comply with such other administrative requirements that the Authority may specify in relation to the effective administration of the scheme.

Ongoing obligations in relation to metering

35.—(1) Participants must keep all meters and steam measuring equipment required to be used in accordance with these Regulations—

(a)continuously operating,

(b)properly maintained and periodically checked for errors, and

(c)re-calibrated every 10 years or within such period of time as may be specified in accordance with manufacturers’ instructions where available, whichever is the sooner,

and must retain evidence of this, including service and maintenance invoices, receipts or certificates for the duration of their participation in the scheme.

(2) The Authority may, by the date (if any) specified by it, or at such regular intervals as it may require to enable it to carry out its functions under these Regulations, require participants to provide the following information—

(a)meter readings and other data collected in accordance with these Regulations from all steam measuring equipment, class 2 heat meters and other heat meters used in accordance with these Regulations in such format as the Authority may reasonably require;

(b)in relation to participants using steam measuring equipment, a kWhth figure of both the heat generated and the heat used for eligible purposes together with supporting data and calculations; and

(c)the evidence and service and maintenance documentation specified in paragraph (1).

(3) Participants using heat pumps to provide both heating and cooling must ensure that their meters for those pumps enable them to—

(a)measure heat used for eligible purposes only, and

(b)where appropriate, measure (in order to discount) any cooling generated by the reverse operation of the heat pump,

and must provide upon request an explanation of how their metering arrangements have enabled the cooling in sub-paragraph (b) to be discounted.

(4) The data referred to in paragraph (2)(a) and (b) may be estimated in exceptional circumstances if the Authority has agreed in writing to an estimate being provided and to the way in which those estimates are to be calculated.

(5) Nothing in this regulation prevents the Authority from accepting further data from a participant, if the Authority considers it appropriate to do so.

Ongoing obligations in relation to the provision of information

36.—(1) A participant must provide to the Authority on request any information which the participant holds and which the Authority requires in order to discharge its functions under these Regulations.

(2) Participants must retain the information referred to in Schedule 1, including such information as may reasonably be required by the Authority under paragraph 1(2)(e), (f), (h), (k), (n), (v) or (w) and whether or not copies of that documentation have been supplied to the Authority, for the duration of their participation in the scheme.

(3) Information requested under paragraph (1) must be provided within 7 days of the request or such later date as the Authority may specify.

(4) Information provided to the Authority under these Regulations must be accurate to the best of the participant’s knowledge and belief.

(5) Sub-paragraphs (3) and (4) of paragraph 1 of Schedule 1 have effect.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Draft Explanatory Memorandum

Draft Explanatory Memorandum sets out a brief statement of the purpose of a Draft Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Draft Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as draft version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources