Town and Country Planning (Scotland) Act 1972 (repealed 27.5.1997)

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: Cross Heading: General provisions

 Help about opening options

Version Superseded: 25/09/1991

Status:

Point in time view as at 01/02/1991.

Changes to legislation:

There are currently no known outstanding effects for the Town and Country Planning (Scotland) Act 1972 (repealed 27.5.1997), Cross Heading: General provisions. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

General provisionsS

214 Applications for planning permission by statutory undertakers. S

(1)Where—

(a)an application for planning permission to develop land to which this subsection applies is made by statutory undertakers and is referred to the Secretary of State under Part III of this Act; or

(b)an appeal is made to the Secretary of State under Part III of this Act from the decision on such an application; or

(c)such an application is deemed to be made under subsection (7) of section 85 of this Act on an appeal under that section by statutory undertakers,

the application or appeal shall be dealt with by the Secretary of State and the appropriate Minister.

(2)Subsection (1) of this section applies—

(a)to operational land; and

(b)to land in which the statutory undertakers hold, or propose to acquire, an interest with a view to its being used for the purpose of carrying on their undertaking where the planning permission, if granted on the application or appeal, would be for development involving the use of the land for that purpose.

(3)An application for planning permission which is deemed to have been made by virtue of section 91(5) of this Act shall be determined by the Secretary of State and the appropriate Minister.

(4)Notwithstanding anything in Part III of this Act, planning permission to develop operational land of statutory undertakers shall not, except with their consent, be granted subject to conditions requiring that any buildings or works authorised by the permission shall be removed, or that any use of the land so authorised shall be discontinued, at the end of a specified period.

(5)Subject to the provisions of this Part of this Act as to compensation, the provisions of this Act shall apply to an application which is dealt with under this section by the Secretary of State and the appropriate Minister as if it had been dealt with by the Secretary of State.

215 Development requiring sanction of government department. S

(1)Where the sanction of a government department F1 is required in respect of any development of operational land, then, except where that sanction has been granted without any direction as to the grant of planning permission, the Secretary of State and the appropriate Minister shall not be required to deal with an application for planning permission under section 214(1) of this Act.

(2)The provisions of subsection (3) of section 37 of this Act shall have effect for the purposes of this section as they have effect for the purposes of that section.

216 Revocation or modification of permission to develop operational land. S

In relation to any planning permission, granted on the application of statutory undertakers, for the development of operational land, the provisions of Part III of this Act with respect to the revocation and modification of planning permission shall have effect as if, for any reference therein to the Secretary of State, there were substituted a reference to the Secretary of State and the appropriate Minister.

217 Order requiring discontinuance of use etc. of operational land. S

The provisions of Part III of this Act with respect to the making of orders requiring the discontinuance of any use of land or imposing conditions on the continuance thereof, or requiring buildings or works on land to be altered or removed, shall have effect, in relation to operational land of statutory undertakers, as if, for any reference therein to the Secretary of State, there were substituted a reference to the Secretary of State and the appropriate Minister.

218 Acquisition of land of statutory undertakers. S

(1)Notwithstanding anything in paragraph 10 of Schedule 1 to the M1Acquisition of Land (Authorisation Procedure) (Scotland) Act 1947 a compulsory purchase order to which this section applies may be confirmed or made without the appropriate Minister’s certificate.

(2)This section applies to any compulsory purchase order under this Act authorising the acquisition of land which has been acquired by statutory undertakers for the purposes of their undertaking.

(3)Except where the appropriate Minister’s certificate is given, a compulsory purchase order to which this section applies shall be of no effect unless it is confirmed or made by the appropriate Minister jointly with the Minister or Ministers who would apart from this subsection have power to make or confirm it.

(4)In this section “the appropriate Minister’s certificate” means such a certificate as is mentioned in paragraph 10 of Schedule 1 to the said Act of 1947.

219 Extinguishment of rights of way, and rights as to apparatus, of statutory undertakers. S

(1)Where any land has been acquired by a Minister, a F2 Planning authority or statutory undertakers under Part VI of this Act or compulsorily under any other enactment, or has been appropriated by a F2 planning authority for planning purposes, and—

(a)there subsists over that land a right vested in or belonging to statutory undertakers for the purpose of the carrying on of their undertaking, being a right of way or a right of laying down, erecting, continuing or maintaining apparatus on, under or over the land; or

(b)there is on, under or over the land apparatus vested in or belonging to statutory undertakers for the purpose of the carrying on of their undertaking,

the acquiring or appropriating authority, if satisfied that the extinguishment of the right or, as the case may be, the removal of the apparatus, is necessary for the purpose of carrying out any development with a view to which the land was acquired or appropriated, may serve on the statutory undertakers a notice stating that, at the end of the period of twenty-eight days from the date of service of the notice or such longer period as may be specified therein, the right will be extinguished or requiring that, before the end of such period as aforesaid, the apparatus shall be removed.

(2)The statutory undertakers on whom a notice is served under subsection (1) of this section may, before the end of the period of twenty-eight days from the service of the notice, serve a counter-notice on the acquiring or appropriating authority stating that they object to all or any of the provisions of the notice and specifying the grounds of their objection.

(3)If no counter-notice is served under subsection (2) of this section—

(a)any right to which the notice relates shall be extinguished at the end of the period specified in that behalf in the notice; and

(b)if, at the end of the period so specified in relation to any apparatus, any requirement of the notice as to the removal of the apparatus has not been complied with, the acquiring or appropriating authority may remove the apparatus and dispose of it in any way the authority may think fit.

(4)If a counter-notice is served under subsection (2) of this section on a F2 planning authority or on statutory undertakers, the authority or undertakers may either withdraw the notice (without prejudice to the service of a further notice) or may apply to the Secretary of State and the appropriate Minister for an order under this section embodying the provisions of the notice, with or without modification.

(5)If a counter-notice is served under subsection (2) of this section on a Minister, he may withdraw the notice (without prejudice to the service of a further notice) or he and the appropriate Minister may make an order under this section embodying the provisions of the notice, with or without modification.

(6)In this section any reference to the appropriation of land for planning purposes shall be construed in accordance with section 122(1) of this Act as if this section were in Part VI of this Act.

[F3(7)In subsection (1) above—

(a)the references in paragraph (a) to a right vested in or belonging to statutory undertakers for the purpose of the carrying on of their undertaking shall include a reference to a right conferred by or in accordance with the telecommunications code on the operator of a telecommunications code system; and

(b)the reference in paragraph (b) to apparatus vested in or belonging to statutory undertakers for the purpose of the carrying on of their undertaking shall include a reference to telecommunication apparatus kept installed for the purposes of any such system;

and for the purposes of this subsection, in this section (except, without prejudice to section 35(4) of the Telecommunications Act 1984, in those paragraphs and the words preceding them) and in sections 220, 226(2) and 227 of this Act references to statutory undertakers shall have effect as references to the operator of any such system, references, in relation to such an operator, to the carrying on of his undertaking shall have effect as references to the running of the telecommunications code system in question and references to the appropriate Minister shall have effect as references to the Secretary of State for Trade and Industry.]

Textual Amendments

Modifications etc. (not altering text)

C29S. 219 applied (with modifications) by Roads (Scotland) Act 1984 (c. 54, SIF 108), ss. 134, 135 (with s. 128(1))

C31Ss. 214–227, 266(6)(b), 275(2), Sch. 8 modified by Gas Act 1986 (c. 44, SIF 44:2), s. 67(1)(3), Sch. 7 para. 2(9)(f) (with Sch. 8 para. 33)

Ss. 214-227 modified (1.3.1996) by 1995 c. 45, s. 16(1), Sch. 4 para. 2(10)(d); S.I. 1996/218, art. 2

220 Orders under s. 219. S

(1)Where a Minister and the appropriate Minister propose to make an order under section 219(5) of this Act, they shall prepare a draft of the order.

(2)Before making an order under subsection (4) or subsection (5) of section 219 of this Act, the Ministers proposing to make the order—

(a)shall afford to the statutory undertakers on whom notice was served under subsection (1) of that section an opportunity of objecting to the application for, or proposal to make, the order; and

(b)if any objection is made, shall cause an inquiry to be held,

and may then, if they think fit, make the order in accordance with the application or in accordance with the draft order, as the case may be, either with or without modification.

(3)Where an order is made under section 219 of this Act—

(a)any right to which the order relates shall be extinguished at the end of the period specified in that behalf in the order; and

(b)if, at the end of the period so specified in relation to any apparatus, any requirement of the order as to the removal of the apparatus has not been complied with, the acquiring or appropriating authority may remove the apparatus and dispose of it in any way the authority may think fit.

221 Notice for same purposes as s. 219 but given by statutory undertakers to developing authority. S

(1)Subject to the provisions of this section, where land has been acquired or appropriated as mentioned in section 219(1) of this Act, and—

(a)there is on, under or over the land any apparatus vested in or belonging to statutory undertakers; and

(b)the undertakers claim that development to be carried out on the land is such as to require, on technical or other grounds connected with the carrying on of their undertaking, the removal or re-siting of the apparatus affected by the development,

the undertakers may serve on the acquiring or appropriating authority a notice claiming the right to enter on the land and carry out such works for the removal or re-siting of the apparatus or any part of it as may be specified in the notice.

(2)Where, after the land has been acquired or appropriated as aforesaid, development of the land is begun to be carried out, no notice under this section shall be served later than twenty-one days after the beginning of the development.

(3)Where a notice is served under this section, the authority on whom it is served may, before the end of the period of twenty-eight days from the date of service, serve on the statutory undertakers a counter-notice stating that they object to all or any of the provisions of the notice and specifying the grounds of their objection.

(4)If no counter-notice is served under subsection (3) of this section, the statutory undertakers shall, after the end of the period of twenty-eight days therein mentioned, have the rights claimed in their notice.

(5)If a counter-notice is served under subsection (3) of this section, the statutory undertakers who served the notice under this section may either withdraw it or may apply to the Secretary of State and the appropriate Minister for an order under this section conferring on the undertakers the rights claimed in the notice or such modified rights as the Secretary of State and the appropriate Minister think it expedient to confer on them.

(6)Where, by virtue of this section or of an order of Ministers thereunder, statutory undertakers have the right to execute works for the removal or re-siting of apparatus, they may arrange with the acquiring or appropriating authority for the works to be carried out by that authority, under the superintendence of the undertakers, instead of by the undertakers themselves.

[F4(7)In subsection (1)(a) above the reference to apparatus vested in or belonging to statutory undertakers shall include a reference to telecommunication apparatus kept installed for the purposes of a telecommunications code system; and, for the purposes of this subsection, in this section references (except in the said subsection (1)(a)) to statutory undertakers shall have effect as references to the operator of any such system and references to the appropriate Minister shall have effect as references to the Secretary of State for Trade and Industry.]

222 Extension or modification of functions of statutory undertakers. S

(1)The powers conferred by this section shall be exercisable where, on a representation made by statutory undertakers, it appears to the Secretary of State and the appropriate Minister to be expedient that the powers and duties of those undertakers should be extended or modified, in order—

(a)to secure the provision of services which would not otherwise be provided, or satisfactorily provided, for any purpose in connection with which a F5 planning authority or Minister may be authorised under Part VI of this Act to acquire land or in connection with which any such person may compulsorily acquire land under any other enactment; or

(b)to facilitate an adjustment of the carrying on of the undertaking necessitated by any of the acts and events mentioned in subsection (2) of this section.

(2)The said acts and events are—

(a)the acquisition under Part VI of this Act or compulsorily under any other enactment of any land in which an interest was held, or which was used, for the purpose of the carrying on of the undertaking of the statutory undertakers in question;

(b)the extinguishment of a right or the imposition of any requirement by virtue of section 219 of this Act;

(c)a decision on an application made by the statutory undertakers for planning permission to develop any such land as is mentioned in paragraph (a) of this subsection;

(d)the revocation or modification of planning permission granted on any such application;

(e)the making of an order under section 49 of this Act in relation to any such land.

(3)The powers conferred by this section shall also be exercisable where, on a representation made by a F5 planning authority or Minister, it appears to the Secretary of State and the appropriate Minister to be expedient that the powers and duties of statutory undertakers should be extended or modified, in order to secure the provision of new services, or the extension of existing services, for any purpose in connection with which the F5 planning authority or Minister making the representation may be authorised under Part VI of this Act to acquire land or in Connection with which the local authority or Minister may compulsorily acquire land under any other enactment.

(4)Where the powers conferred by this section are exercisable, the Secretary of State and the appropriate Minister may, if they think fit, by order provide for such extension or modification of the powers and duties of the statutory undertakers as appears to them to be requisite in order to secure the services in question, as mentioned in subsection (1)(a) or (3) of this section, or to facilitate the adjustment in question, as mentioned in subsection (1)(b) of this section, as the case may be.

(5)Without prejudice to the generality of subsection (4) of this section, an order under this section may make provision—

(a)for empowering the statutory undertakers to acquire (whether compulsorily or by agreement) any land specified in the order, and to erect or construct any buildings or works so specified;

(b)for applying, in relation to the acquisition of any such land or the construction of any such works, enactments relating to the acquisition of land and the construction of works;

(c)where it has been represented that the making of the order is expedient for the purposes mentioned in subsection (1)(a) or (3) of this section, for giving effect to such financial arrangements between the F5 planning authority or Minister and the statutory undertakers as they may agree, or as, in default of agreement, may be determined to be equitable in such manner and by such tribunal as may be specified in the order;

(d)for such incidental and supplemental matters as appear to the Secretary of State and the appropriate Minister to be expedient for the purposes of the order.

Textual Amendments

Modifications etc. (not altering text)

C50Ss. 222—225 amended by Mineral Workings Act 1951 (c. 60, SIF 86), s. 32 as substituted by Roads (Scotland) Act 1984 (c. 54, SIF 108), 156(1), Sch. 9 para. 41(3) (with s. 128(1))

C52Ss. 214–227, 266(6)(b), 275(2), Sch. 8 modified by Gas Act 1986 (c. 44, SIF 44:2), s. 67(1)(3), Sch. 7 para. 2(9)(f) (with Sch. 8 para. 33)

Ss. 214-227 modified (1.3.1996) by 1995 c. 45, s. 16(1), Sch. 4 para. 2(10)(d); S.I. 1996/218, art. 2

223 Procedure in relation to orders under s. 222. S

(1)As soon as may be after making such a representation as is mentioned in subsection (1) or subsection (3) of section 222 of this Act—

(a)the statutory undertakers, in a case falling within subsection (1) of that section; or

(b)the F6 planning authority or Minister making the representation, in a case falling within subsection (3) thereof,

shall publish, in such form and manner as may be directed by the Secretary of State and the appropriate Minister, a notice giving such particulars as may be so directed of the matters to which the representation relates, and specifying the time (not being less than twenty-eight days) within which, and the manner in which, objections to the making of an order on the representation may be made, and shall serve a like notice on any persons appearing from the valuation roll to have an interest in any land to which the representation relates, and shall also, if it is so directed by the Secretary of State and the appropriate Minister, serve a like notice on such persons, or persons of such classes, as may be so directed.

(2)Orders under section 222 of this Act shall be subject to special parliamentary procedure.

Textual Amendments

Modifications etc. (not altering text)

C57Ss. 222—225 amended by Mineral Workings Act 1951 (c. 60, SIF 86), s. 32 as substituted by Roads (Scotland) Act 1984 (c. 54, SIF 108), 156(1), Sch. 9 para. 41(3) (with s. 128(1))

C59Ss. 214–227, 266(6)(b), 275(2), Sch. 8 modified by Gas Act 1986 (c. 44, SIF 44:2), s. 67(1)(3), Sch. 7 para. 2(9)(f) (with Sch. 8 para. 33)

Ss. 214-227 modified (1.3.1996) by 1995 c. 45, s. 16(1), Sch. 4 para. 2(10)(d); S.I. 1996/218, art. 2

224 Relief of statutory undertakers from obligations rendered impracticable. S

(1)Where, on a representation made by statutory undertakers, the appropriate Minister is satisfied that the fulfilment of any obligation incurred by those undertakers in connection with the carrying on of their undertaking has been rendered impracticable by an act or event to which this subsection applies, the appropriate Minister may, if he thinks fit, by order direct that the statutory undertakers shall be relieved of the fulfilment of that obligation, either absolutely or to such extent as may be specified in the order.

(2)Subsection (1) of this section applies to the following acts and events, that is to say—

(a)the compulsory acquisition under Part VI of this Act or under any other enactment of any land in which an interest was held, or which was used, for the purpose of the carrying on of the undertaking of the statutory undertakers; and

(b)the acts and events specified in section 222(2)(b) to (e) of this Act.

(3)As soon as may be after making a representation to the appropriate Minister under subsection (1) of this section, the statutory undertakers shall, as may be directed by the appropriate Minister, either publish (in such form and manner as may be so directed) a notice giving such particulars as may be so directed of the matters to which the representation relates, and specify the time (not being less than twenty-eight days) within which, and the manner in which, objections to the making of an order on the representation may be made, or serve such a notice on such persons, or persons of such classes, as may be so directed, or both publish and serve such notices.

(4)If any objection to the making of an order under this section is duly made and is not withdrawn before the order is made, the order shall be subject to special parliamentary procedure.

(5)Immediately after an order is made under this section by the appropriate Minister, he shall publish a notice stating that the order has been made and naming a place where a copy of it may be seen at all reasonable hours, and shall serve a like notice—

(a)on any person who duly made an objection to the order and has sent to the appropriate Minister a request in writing to serve him with the notice required by this subsection, specifying an address for service; and

(b)on such other persons (if any) as the appropriate Minister thinks fit.

(6)Subject to subsection (7) of this section, and to the provisions of Part XII of this Act, an order under this section shall become operative, on the date on which the notice required by subsection (5) of this section is first published.

(7)Where in accordance with subsection (4) of this section the order is subject to special parliamentary procedure, subsection (6) of this section shall not apply.

Modifications etc. (not altering text)

C64Ss. 222—225 amended by Mineral Workings Act 1951 (c. 60, SIF 86), s. 32 as substituted by Roads (Scotland) Act 1984 (c. 54, SIF 108), 156(1), Sch. 9 para. 41(3) (with s. 128(1))

C66Ss. 214–227, 266(6)(b), 275(2), Sch. 8 modified by Gas Act 1986 (c. 44, SIF 44:2), s. 67(1)(3), Sch. 7 para. 2(9)(f) (with Sch. 8 para. 33)

Ss. 214-227 modified (1.3.1996) by 1995 c. 45, s. 16(1), Sch. 4 para. 2(10)(d); S.I. 1996/218, art. 2

225 Objections to orders under ss. 222 and 224. S

(1)For the purposes of sections 222 and 224 of this Act, an objection to the making of an order thereunder shall not be treated as duly made unless—

(a)the objection is made within the time and in the manner specified in the notice required by the section under which the order is proposed to be made; and

(b)a statement in writing of the grounds of the objection is comprised in or submitted with the objection.

(2)Where an objection to the making of such an order is duly made in accordance with subsection (1) of this section and is not withdrawn, the following provisions of this section shall have effect in relation thereto:

Provided that, in the application of those provisions to an order under section 222 of this Act, any reference to the appropriate Minister shall be construed as a reference to the Secretary of State and the appropriate Minister.

(3)Unless the appropriate Minister decides apart from the objection not to make the order, or decides to make a modification which is agreed to by the objector as meeting the objection, the appropriate Minister, before making a final decision, shall consider the grounds of the objection as set out in the statement, and may, if he thinks fit, require the objector to submit within a specified period a further statement in writing as to any of the matters to which the objection relates.

(4)In so far as the appropriate Minister, after considering the grounds of the objection as set out in the original statement and in any such further statement, is satisfied that the objection relates to a matter which can be dealt with in the assessment of compensation, the appropriate Minister may treat the objection as irrelevant for the purpose of making a final decision.

(5)If, after considering the grounds of the objection as set out in the original statement and in any such further statement, the appropriate Minister is satisfied that, for the purpose of making a final decision, he is sufficiently informed as to the matters to which the objection relates, or if, where a further statement has been required, it is not submitted within the specified period, the appropriate Minister may make a final decision without further investigation as to those matters.

(6)Subject to subsections (4) and (5) of this section, the appropriate Minister, before making a final decision, shall afford to the objector an opportunity of appearing before, and being heard by, a person appointed for the purpose by the appropriate Minister; and if the objector avails himself of that opportunity, the appropriate Minister shall afford an opportunity of appearing and being heard on the same occasion to the statutory undertakers, F7 planning authority or Minister on whose representation the order is proposed to be made, and to any other persons to whom it appears to the appropriate Minister to be expedient to afford such an opportunity.

(7)Notwithstanding anything in the preceding provisions of this section, if it appears to the appropriate Minister that the matters to which the objection relates are such as to require investigation by public local inquiry before he makes a final decision, he shall cause such an inquiry to be held; and where he determines to cause such an inquiry to be held, any of the requirements of those provisions to which effect has not been given at the time of that determination shall be dispensed with.

(8)In this section any reference to making a final decision, in relation to an order, is a reference to deciding whether to make the order or what modification (if any) ought to be made.

Textual Amendments

Modifications etc. (not altering text)

C71Ss. 222—225 amended by Mineral Workings Act 1951 (c. 60, SIF 86), s. 32 as substituted by Roads (Scotland) Act 1984 (c. 54, SIF 108), 156(1), Sch. 9 para. 41(3) (with s. 128(1))

C73Ss. 214–227, 266(6)(b), 275(2), Sch. 8 modified by Gas Act 1986 (c. 44, SIF 44:2), s. 67(1)(3), Sch. 7 para. 2(9)(f) (with Sch. 8 para. 33)

Ss. 214-227 modified (1.3.1996) by 1995 c. 45, s. 16(1), Sch. 4 para. 2(10)(d); S.I. 1996/218, art. 2

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act without Schedules as a PDF

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open the Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources