Search Legislation

Town and Country Planning Act 1990

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes to legislation:

Town and Country Planning Act 1990, Cross Heading: Other controls over development is up to date with all changes known to be in force on or before 28 March 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to the whole Act associated Parts and Chapters:

Whole provisions yet to be inserted into this Act (including any effects on those provisions):

Other controls over developmentE+W

102 Orders requiring discontinuance of use or alteration or removal of buildings or works.E+W

(1)If, having regard to the development plan and to any other material considerations, it appears to a local planning authority that it is expedient in the interests of the proper planning of their area (including the interests of amenity)—

(a)that any use of land should be discontinued or that any conditions should be imposed on the continuance of a use of land; or

(b)that any buildings or works should be altered or removed,

they may by order—

(i)require the discontinuance of that use, or

(ii)impose such conditions as may be specified in the order on the continuance of it, or

(iii)require such steps as may be so specified to be taken for the alteration or removal of the buildings or works,

as the case may be.

(2)An order under this section may grant planning permission for any development of the land to which the order relates, subject to such conditions as may be specified in the order.

[F1(2A)Section 71ZA applies where planning permission is granted by an order under this section as if the references to the decision notice were to the order.]

(3)Section 97 shall apply in relation to any planning permission granted by an order under this section as it applies in relation to planning permission granted by the local planning authority on an application made under this Part.

F2[(4)The planning permission which may be granted by an order under this section includes planning permission, subject to such conditions as may be specified in the order, for development carried out before the date on which the order was submitted to the Secretary of State under section 103.

(5)Planning permission for such development may be granted so as to have effect from—

(a)the date on which the development was carried out; or

(b)if it was carried out in accordance with planning permission granted for a limited period, the end of that period.]

(6)Where the requirements of an order under this section will involve the displacement of persons residing in any premises, it shall be the duty of the local planning authority, in so far as there is no other residential accommodation suitable to the reasonable requirements of those persons available on reasonable terms, to secure the provision of such accommodation in advance of the displacement.

(7)Subject to section 103(8), in the case of planning permission granted by an order under this section, the authority referred to in sections 91(1)(b) and 92(4) is the local planning authority making the order.

(8)The previous provisions of this section do not apply to the use of any land for development [F3consisting of the winning and working of minerals or involving the depositing of refuse or waste materials] except as provided in Schedule 9, and that Schedule shall have effect for the purpose of making provision as respects land which is or has been so used.

Textual Amendments

F1S. 102(2A) inserted (6.9.2015 for specified purposes, 1.3.2016 for specified purposes, 16.3.2016 in so far as not already in force) by Planning (Wales) Act 2015 (anaw 4), ss. 33(4), 58(2)(b)(4)(b); S.I. 2016/52, arts. 3(b), 5(b) (with art. 12)

F3Words in s. 102(8) substituted (25.9.1991) by Planning and Compensation Act 1991 (c. 34, SIF 123:1), s. 21, Sch. 1 para. 6 (with s. 84(5)); S.I. 1991/2067, art. 3 (subject to art. 4)

Modifications etc. (not altering text)

C1S. 102: functions of local authority not to be responsibility of an executive of the authority (E.)(16.11.2000) by virtue of S.I. 2000/2853, reg. 2(1), Sch. 1

103 Confirmation by Secretary of State of s. 102 orders.E+W

(1)An order under section 102 shall not take effect unless it is confirmed by the Secretary of State, either without modification or subject to such modifications as he considers expedient.

(2)The power of the Secretary of State under this section to confirm an order subject to modifications includes power—

(a)to modify any provision of the order granting planning permission, as mentioned in subsections (2) to (5) of section 102;

(b)to include in the order any grant of planning permission which might have been included in the order as submitted to him.

(3)Where a local planning authority submit an order to the Secretary of State for his confirmation under this section, they shall serve notice—

(a)on the owner of the land affected,

(b)on the occupier of that land, and

(c)on any other person who in their opinion will be affected by the order.

(4)The notice shall specify the period within which any person on whom it is served may require the Secretary of State to give him an opportunity of appearing before, and being heard by, a person appointed by the Secretary of State for the purpose.

(5)If within that period such a person so requires, before the Secretary of State confirms the order, he shall give such an opportunity both to him and to the local planning authority.

(6)The period referred to in subsection (4) must not be less than 28 days from the service of the notice.

(7)Where an order under section 102 has been confirmed by the Secretary of State, the local planning authority shall serve a copy of the order on the owner and occupier of the land to which the order relates.

(8)Where the Secretary of State exercises his powers under subsection (2) in confirming an order granting planning permission, he is the authority referred to in sections 91(1)(b) and 92(4).

104 Power of the Secretary of State to make s. 102 orders.E+W

(1)If it appears to the Secretary of State that it is expedient that an order should be made under section 102, he may himself make such an order.

(2)Such an order made by the Secretary of State shall have the same effect as if it had been made by the local planning authority and confirmed by the Secretary of State.

(3)The Secretary of State shall not make such an order without consulting the local planning authority.

(4)Where the Secretary of State proposes to make such an order he shall serve notice on the local planning authority.

(5)The notice shall specify the period within which the authority may require an opportunity of appearing before and being heard by a person appointed by the Secretary of State for the purpose.

(6)If within that period the authority so require, before the Secretary of State makes the order he shall give the authority such an opportunity.

(7)The period referred to in subsection (5) must not be less than 28 days from the date of the service of the notice.

(8)The provisions of this Part and of any regulations made under this Act with respect to the procedure to be followed in connection with the submission by the local planning authority of any order under section 102, its confirmation by the Secretary of State and the service of copies of it as confirmed shall have effect, subject to any necessary modifications, in relation to any proposal by the Secretary of State to make such an order, its making by him and the service of copies of it.

F4105. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .E+W

Textual Amendments

F4S. 105 repealed (1.11.1995) by 1995 c. 25, ss. 96(4), 120(3), Sch. 24 (with ss. 7(6), 115, 117); S.I. 1995/2765, art. 2

[106F5 Planning obligations.E+W

(1) Any person interested in land in the area of a local planning authority may, by agreement or otherwise, enter into an obligation (referred to in this section and sections 106A [F6to 106C] [F7, Schedule 7A] as “ a planning obligation ”), enforceable to the extent mentioned in subsection (3)—

(a)restricting the development or use of the land in any specified way;

(b)requiring specified operations or activities to be carried out in, on, under or over the land;

(c)requiring the land to be used in any specified way; or

(d)requiring a sum or sums to be paid to the authority [F8(or, in a case where section 2E applies, to the Greater London Authority)] on a specified date or dates or periodically.

[F9(1A)In the case of a development consent obligation, the reference to development in subsection (1)(a) includes anything that constitutes development for the purposes of the Planning Act 2008.]

(2)A planning obligation may—

(a)be unconditional or subject to conditions;

(b)impose any restriction or requirement mentioned in subsection (1)(a) to (c) either indefinitely or for such period or periods as may be specified; and

(c)if it requires a sum or sums to be paid, require the payment of a specified amount or an amount determined in accordance with the instrument by which the obligation is entered into and, if it requires the payment of periodical sums, require them to be paid indefinitely or for a specified period.

(3)Subject to subsection (4) a planning obligation is enforceable by the authority identified in accordance with subsection (9)(d)—

(a)against the person entering into the obligation; and

(b)against any person deriving title from that person.

(4)The instrument by which a planning obligation is entered into may provide that a person shall not be bound by the obligation in respect of any period during which he no longer has an interest in the land.

(5)A restriction or requirement imposed under a planning obligation is enforceable by injunction.

(6)Without prejudice to subsection (5), if there is a breach of a requirement in a planning obligation to carry out any operations in, on, under or over the land to which the obligation relates, the authority by whom the obligation is enforceable may—

(a)enter the land and carry out the operations; and

(b)recover from the person or persons against whom the obligation is enforceable any expenses reasonably incurred by them in doing so.

(7)Before an authority exercise their power under subsection (6)(a) they shall give not less than twenty-one days’ notice of their intention to do so to any person against whom the planning obligation is enforceable.

(8)Any person who wilfully obstructs a person acting in the exercise of a power under subsection (6)(a) shall be guilty of an offence and liable on summary conviction to a fine not exceeding level 3 on the standard scale.

(9)A planning obligation may not be entered into except by an instrument executed as a deed which—

(a)states that the obligation is a planning obligation for the purposes of this section;

[F10(aa)if the obligation is a development consent obligation, contains a statement to that effect;]

(b)identifies the land in which the person entering into the obligation is interested;

(c)identifies the person entering into the obligation and states what his interest in the land is; and

(d)identifies the local planning authority by whom the obligation is enforceable. [F11and, in a case where section 2E applies, identifies the Mayor of London as an authority by whom the obligation is also enforceable]

(10)A copy of any such instrument shall be given to the [F12authority so identified ][F12local planning authority so identified and, in a case where section 2E applies, to the Mayor of London] .

(11)A planning obligation shall be a local land charge and for the purposes of the M1Local Land Charges Act 1975 the authority by whom the obligation is enforceable shall be treated as the originating authority as respects such a charge.

(12)Regulations may provide for the charging on the land of—

(a)any sum or sums required to be paid under a planning obligation; and

(b)any expenses recoverable by a local planning authority [F13or the Mayor of London] under subsection (6)(b),

and this section and sections 106A [F14to 106BC] shall have effect subject to any such regulations.

(13) In this section “ specified ” means specified in the instrument by which the planning obligation is entered into and in this section and section 106A “ land ” has the same meaning as in the M2 Local Land Charges Act 1975.

[F15(14) In this section and section 106A “ development consent obligation ” means a planning obligation entered into in connection with an application (or a proposed application) for an order granting development consent. ]]

Textual Amendments

F5Ss. 106-106B substituted for s. 106 (25.10.1991 so far as substituting the new s. 106, 25.11.1991 for certain purposes and otherwise 9.11.1992) by Planning and Compensation Act 1991 (c. 34, SIF 123:1), s. 12(1) (with s. 84(5)); S.I. 1991/2272, art. 3(1)(a); S.I. 1991/2728, art. 2; S.I. 1992/2831, art. 2

F6Words in s. 106(1) substituted (25.4.2013) by Growth and Infrastructure Act 2013 (c. 27), s. 35(2), Sch. 2 para. 3(2)

F8Words in s. 106(1)(d) inserted (6.4.2008) by Greater London Authority Act 2007 (c. 24), ss. 33(2), 59; S.I. 2008/582, art. 2(a)

F9S. 106(1A) inserted (1.3.2010) by Planning Act 2008 (c. 29), ss. 174(2)(a), 241 (with s. 226); S.I. 2010/101, art. 3(k) (with art. 6)

F10S. 106(9)(aa) inserted (1.3.2010) by Planning Act 2008 (c. 29), ss. 174(2)(b), 241 (with s. 226); S.I. 2010/101, art. 3(k) (with art. 6)

F11Words in s. 106(9)(d) inserted (6.4.2008) by Greater London Authority Act 2007 (c. 24), ss. 33(3), 59; S.I. 2008/582, art. 2(a)

F12Words in s. 106(10) substituted (6.4.2008) by Greater London Authority Act 2007 (c. 24), ss. 33(4), 59; S.I. 2008/582, art. 2(a)

F13Words in s. 106(12)(b) inserted (6.4.2008) by Greater London Authority Act 2007 (c. 24), ss. 33(5), 59; S.I. 2008/582, art. 2(a)

F14Words in s. 106(12) substituted (25.4.2013) by Growth and Infrastructure Act 2013 (c. 27), s. 35(2), Sch. 2 para. 3(3)

F15S. 106(14) inserted (1.3.2010) by Planning Act 2008 (c. 29), ss. 174(2)(c), 241 (with s. 226); S.I. 2010/101, art. 3(k) (with art. 6)

Modifications etc. (not altering text)

C3S. 106: functions of local authority not to be responsibility of an executive of the authority (E.)(16.11.2000) by virtue of S.I. 2000/2853, reg. 2(1), Sch. 1

Marginal Citations

[F16106A Modification and discharge of planning obligations.E+W

(1)A planning obligation may not be modified or discharged except—

(a)by agreement between [F17the authority by whom the obligation is enforceable] [F17the appropriate authority (see subsection (11))] and the person or persons against whom the obligation is enforceable; or

(b)in accordance with [F18

(i)]this section and section 106B [F19, or

(ii)sections 106BA and 106BC.]

(2)An agreement falling within subsection (1)(a) shall not be entered into except by an instrument executed as a deed.

(3)A person against whom a planning obligation is enforceable may, at any time after the expiry of the relevant period, apply to [F20the local planning authority by whom the obligation is enforceable] [F20the appropriate authority] for the obligation—

(a)to have effect subject to such modifications as may be specified in the application; or

(b)to be discharged.

(4) In subsection (3) “ the relevant period ” means—

(a)such period as may be prescribed; or

(b)if no period is prescribed, the period of five years beginning with the date on which the obligation is entered into.

(5)An application under subsection (3) for the modification of a planning obligation may not specify a modification imposing an obligation on any other person against whom the obligation is enforceable.

(6)Where an application is made to an authority under subsection (3), the authority may determine—

(a)that the planning obligation shall continue to have effect without modification;

(b)if the obligation no longer serves a useful purpose, that it shall be discharged; or

(c)if the obligation continues to serve a useful purpose, but would serve that purpose equally well if it had effect subject to the modifications specified in the application, that it shall have effect subject to those modifications.

[F21(6A)Except in such cases as may be prescribed, the authority may not under subsection (6) discharge or modify the planning obligation if the authority considers that doing so would—

(a)prevent the biodiversity gain objective referred to in paragraph 2 of Schedule 7A from being met in relation to any development, or

(b)give rise to a significant risk of that objective not being met in relation to any development.]

(7)The authority shall give notice of their determination to the applicant within such period as may be prescribed.

(8)Where an authority determine [F22under this section] that a planning obligation shall have effect subject to modifications specified in the application, the obligation as modified shall be enforceable as if it had been entered into on the date on which notice of the determination was given to the applicant.

(9)Regulations may make provision with respect to—

(a)the form and content of applications under subsection (3);

(b)the publication of notices of such applications;

(c)the procedures for considering any representations made with respect to such applications; and

(d)the notices to be given to applicants of determinations under subsection (6).

(10)Section 84 of the M3Law of Property Act 1925 (power to discharge or modify restrictive covenants affecting land) does not apply to a planning obligation.

[F23(11) In this section “ the appropriate authority ” means—

(a)the Mayor of London, in the case of any planning obligation enforceable by him;

[F24(aa)the Secretary of State, in the case of any development consent obligation F25...;

F26(ab). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .]

(b)in the case of any other planning obligation, the local planning authority by whom it is enforceable.

(12)The Mayor of London must consult the local planning authority before exercising any function under this section.]]

Textual Amendments

F16S. 106- 106B substituted for s. 106 (25.10.1991 so far as substituting the new s. 106, 25.11.1991 for certain purposes and otherwise 9.11.1992) by Planning and Compensation Act 1991 (c. 34, SIF 123:1), s. 12(1); S.I. 1991/2272, art. 3(1)(a); S.I. 1991/2728, art. 2; S.I. 1992/2831, art. 2

F17Words in s. 106A(1)(a) substituted (6.4.2008) by Greater London Authority Act 2007 (c. 24), ss. 34(2), 59; S.I. 2008/582, art. 2(a)

F20Words in s. 106A(3) substituted (6.4.2008) by Greater London Authority Act 2007 (c. 24), ss. 34(3), 59; S.I. 2008/582, art. 2(a)

F22Words in s. 106A(8) inserted (25.4.2013) by Growth and Infrastructure Act 2013 (c. 27), s. 35(2), Sch. 2 para. 4(3)

F24S. 106A(11)(aa)(ab) inserted (1.3.2010) by Planning Act 2008 (c. 29), ss. 174(3), 241 (with s. 226); S.I. 2010/101, art. 3(k) (with art. 6)

Marginal Citations

106BF27Appeals [F28in relation to applications under section 106A].E+W

(1)Where [F29an authority][F30 (other than the Secretary of State F31...)]

(a)fail to give notice as mentioned in section 106A(7); or

(b)determine [F32under section 106A] that a planning obligation shall continue to have effect without modification,

the applicant may appeal to the Secretary of State.

(2)For the purposes of an appeal under subsection (1)(a), it shall be assumed that the authority have determined that the planning obligation shall continue to have effect without modification.

(3)An appeal under this section shall be made by notice served within such period and in such manner as may be prescribed.

(4)Subsections (6) to (9) of section 106A apply in relation to appeals to the Secretary of State under this section as they apply in relation to applications to authorities under that section.

(5)Before determining the appeal the Secretary of State shall, if either the applicant or the authority so wish, give each of them an opportunity of appearing before and being heard by a person appointed by the Secretary of State for the purpose.

(6)The determination of an appeal by the Secretary of State under this section shall be final.

(7)Schedule 6 applies to appeals under this section.

[F33(8)In the application of Schedule 6 to an appeal under this section in a case where the authority mentioned in subsection (1) is the Mayor of London, references in that Schedule to the local planning authority are references to the Mayor of London.]

Textual Amendments

F27Ss. 106-106B substituted for s. 106 (25.10.1991 so far as substituting the new s. 106, 25.11.1991 for certain purposes and otherwise 9.11.1992) by Planning and Compensation Act 1991 (c. 34, SIF 123:1), s. 12(1); S.I. 1991/2272, art. 3(1)(a); S.I. 1991/2728, art.2; S.I. 1992/2831, art. 2

F28Words in s. 106B heading inserted (25.4.2013) by Growth and Infrastructure Act 2013 (c. 27), s. 35(2), Sch. 2 para. 5(2)

F29Words in s. 106B(1) substituted (6.4.2008) by Greater London Authority Act 2007 (c. 24), ss. 34(6), 59; S.I. 2008/582, art. 2(a)

F30Words in s. 106B(1) inserted (1.3.2010) by Planning Act 2008 (c. 29), ss. 174(4), 241 (with s. 226); S.I. 2010/101, art. 3(k) (with art. 6)

F32Words in s. 106B(1)(b) inserted (25.4.2013) by Growth and Infrastructure Act 2013 (c. 27), s. 35(2), Sch. 2 para. 5(3)

F34106BAModification or discharge of affordable housing requirementsE+W

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Textual Amendments

F35106BBDuty to notify the Mayor of London of certain applications under section 106BAE+W

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Textual Amendments

F36106BCAppeals in relation to applications under section 106BAE+W

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Textual Amendments

106CLegal challenges relating to development consent obligationsE+W

(1)A court may entertain proceedings for questioning a failure by the Secretary of State F37... to give notice as mentioned in section 106A(7) [F38or 106BA(9)] only if—

(a)the proceedings are brought by a claim for judicial review, and

(b)the claim form is filed [F39before the end of] the period of 6 weeks beginning with [F40the day after] the day on which the period prescribed under section 106A(7) [F38or 106BA(9)] ends.

[F41(1A)If no period is prescribed under section 106BA(9), the period of 6 weeks referred to in subsection (1)(b) that applies in relation to proceedings for failure to give notice as mentioned in subsection (9) of section 106BA begins with [F42the day after] the expiry of the period mentioned in that subsection that applies in the applicant's case.]

(2)A court may entertain proceedings for questioning a determination by the Secretary of State F37... that a planning obligation shall continue to have effect without modification only if—

(a)the proceedings are brought by a claim for judicial review, and

(b)the claim form is filed [F43before the end of] the period of 6 weeks beginning with [F44the day after] the day on which notice of the determination is given under section 106A(7) [F45or 106BA(9)].

[F46(3)A court may entertain proceedings for questioning a determination by the Secretary of State on an application under section 106BA that a planning obligation shall be modified otherwise than in accordance with the application only if—

(a)the proceedings are brought by a claim for judicial review, and

(b)the claim form is filed [F47before the end of] the period of 6 weeks beginning with [F48the day after] the day on which notice of the determination is given under section 106BA(9).]

Textual Amendments

F38Words in s. 106C(1) inserted (25.4.2013) by Growth and Infrastructure Act 2013 (c. 27), s. 35(2), Sch. 2 para. 6(2)

F45Words in s. 106C(2) inserted (25.4.2013) by Growth and Infrastructure Act 2013 (c. 27), s. 35(2), Sch. 2 para. 6(4)

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act without Schedules as a PDF

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open the Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources