Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Town and Country Planning Act 1990, Section 172 is up to date with all changes known to be in force on or before 19 May 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)Where—
(a)it appears to the local planning authority that there has been a breach of planning control after the end of 1963; and
(b)the authority consider it expedient to do so having regard to the provisions of the development plan and to any other material considerations,
they may issue a notice requiring the breach to be remedied.
(2)A notice under this section is referred to in this Act as an “enforcement notice”.
(3)There is a breach of planning control—
(a)if development has been carried out, whether before or after the commencement of this Act, without the grant of the planning permission required for that development in accordance with Part III (or, as the case may be, Part III of the 1962 Act or Part III of the 1971 Act); or
(b)if any conditions or limitations subject to which planning permission was granted have not been complied with.
(4)An enforcement notice which relates to a breach of planning control consisting in—
(a)the carrying out without planning permission of building, engineering, mining or other operations in, on, over or under land; or
(b)the failure to comply with any condition or limitation which relates to the carrying out of such operations and subject to which planning permission was granted for the development of that land; or
(c)the making without planning permission of a change of use of any building to use as a single dwellinghouse; or
(d)the failure to comply with a condition which prohibits or has the effect of preventing a change of use of a building to use as a single dwellinghouse,
may be issued only within the period of four years from the date of the breach.
(5)Subject to section 175(4), an enforcement notice shall take effect on a date specified in it (in this Part referred to as the “specified date”).
(6)A copy of an enforcement notice shall be served not later than 28 days after the date of its issue and not later than 28 days before the specified date—
(a)on the owner and on the occupier of the land to which it relates; and
(b)on any other person having an interest in that land, which in the opinion of the authority is an interest materially affected by the notice.
(7)The local planning authority may withdraw an enforcement notice (without prejudice to their powers to issue another) at any time before it takes effect.
(8)If they do so, they shall immediately give notice of the withdrawal to every person who was served with a copy of the notice.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: