Search Legislation

Channel Tunnel Rail Link Act 1996

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: Part I

 Help about opening options

Alternative versions:

Status:

Point in time view as at 07/07/2010.

Changes to legislation:

There are currently no known outstanding effects for the Channel Tunnel Rail Link Act 1996, Part I. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Part IU.K. Purposes for which Certain Land may be Acquired or Used

(1)(2)(3)
AreaNumber of land shown on deposited plansPurpose for which land may be acquired or used
GREATER LONDON
London Borough of Camden15, 16 and 159The provision of car parking, a working site, and access for construction purposes.
1 to 13, 149 to 151 and 153 to 158Road improvement works and alterations to ventilation shafts.
37The provision of parking, a working site and access for construction purposes.
61The provision of parking and a working site.
79The provision of access for construction purposes.
63, 64, 74 and 76 to 78The provision of access for protective works.
87The provision of access for construction purposes and a working site.
182 and 189 to 192The provision of access for construction purposes.
194, 196 and 197The provision of access for construction purposes and permanent access for operational purposes.
198 to 200The provision of access for construction purposes and permanent access for operational purposes.
203 and 204The provision of access for construction purposes.
227The provision of access for construction purposes.
London Borough of Islington1 and 2Road improvement works.
331, 333, 334, 336 and 337The construction of a ventilation shaft, provision of permanent access thereto, and a working site.
786 and 1048The provision of electricity supply apparatus, access for construction purposes and permanent access for operational purposes.
782 and 1050The provision of access for construction purposes.
787 and 788The provision of access for construction purposes.
792 and 794The provision of protective works for public utilities’ apparatus.
London Borough of Hackney184 and 212The construction of a ventilation shaft, provision of permanent access thereto, and a working site.
773 to 777The provision of access for construction purposes and river bank strengthening works.
778 and 779The provision of barge moorings and barge loading facilities.
780The provision of barge loading facilities, spoil handling plant and machinery, a temporary shaft to Work No. 6, a working site and access for construction purposes.
781 and 782The provision of access for construction purposes.
London Borough of Newham1 and 2 (part)The provision of a working site, access for construction purposes and river bank strengthening works.
2 (part), 5 (part), 7 (part) and 8 (part)Alteration of overhead electric cables for electricity supply for construction purposes.
6The provision of access for construction purposes.
7 (part)The provision of a working site.
1, 4, 5 (part) and 8 (part)The provision of a working site, drainage works and river bank strengthening works and diversion of a telephone cable.
7 (part), 8 (part) and 11 (part)The provision of permanent access for operational purposes and diversion of a telephone cable.
8 (part) and 11 (part)The provision of a working site and permanent access for operational purposes.
8 (part)The provision of a working site.
8 (part), 12 (part), 14 and 15The provision of a working site, access for construction purposes and permanent access for operational purposes.
8 (part), 12 (part) and 13The provision of a working site and access for construction purposes.
519 to 521, 541 and 550The construction of a ventilation shaft, provision of permanent access thereto, and a working site.
1237 (part), 1244 and 1245The construction of a ventilation shaft, provision of permanent access thereto, and a working site.
1237 (part) and 1239The provision of a working site.
1253 and 1254 (part)The provision of barge moorings and barge loading facilities.
1254 (part)The provision of spoil handling plant and machinery, a conveyor, a working site and access for construction purposes.
1255 and 1260The provision of spoil handling plant and machinery, a conveyor and access for construction purposes.
1261The provision of spoil handling plant and machinery and a conveyor.
1262 and 1263 (part)The provision of access for construction purposes.
1263 (part) and 1264 (part)The provision of a working site and access for construction purposes.
1264 (part), 1265 and 1268The provision of a temporary footbridge and raising of the existing footbridge.
1269The provision of a working site and access for construction purposes.
London Borough of Waltham Forest1 and 3The provision of a working site and a temporary tunnel segments manufacturing facility, a maintenance and servicing depot, access and drainage works.
5 to 8 (part)The provision of drainage works.
8 (part) and 9The provision of access for construction of drainage works.
10The provision of access for construction of drainage works.
13 and 14The provision of drainage works.
London Borough of Barking and Dagenham161, 166 (part), 167 (part), 168 and 169The provision of underground electric cables for electricity supply apparatus.
195 and 199The provision of a turning head.
196 (part) and 197 (part)Reinstatement of railway sidings.
206 and 209Alterations to a proposed service bridge and the provision of access for construction purposes.
205The provision of access for construction purposes.
182Road improvement works.
195, 198 (part), 200 (part) to 202The provision of access for construction purposes.
198 (part)The provision of a working site and diversion of high pressure gas pipelines and other public utilities’ apparatus.
208 (part)The diversion of high pressure gas pipelines, a water pipe, overhead electric cables and other public utilities’ apparatus.
208 (part) and 210The diversion of high pressure gas pipelines, a water pipe, overhead electric cables and other public utilities’ apparatus.
221 to 226 (part)The diversion of gas pipelines, overhead electric cables and other public utilities’ apparatus and provision of a working site.
215 and 226 (part)The provision of accesses for construction purposes.
217 to 219The provision of access for construction purposes.
766 and 768The construction of a ventilation shaft, provision of permanent access thereto and a working site.
787, 788 and 790 to 793The provision of protective works for public utilities’ apparatus and access for construction purposes.
789 and 795 (part)The provision of a working site, access for construction purposes and permanent access for operational purposes.
795 (part) and 798The provision of electricity supply apparatus and permanent access for operational purposes.
797The provision of electricity supply apparatus and permanent access for operational purposes.
800, 801 and 831The provision of a working site, a conveyor, spoil handling plant and machinery, diversion of overhead electric cables and other public utilities’ apparatus and access for construction purposes and permanent access for operational purposes.
802The diversion of public utilities’ apparatus
803, 804, 808 and 809The provision of a working site, a turning head and access for construction purposes, diversion of public utilities’ apparatus and alteration of watercourses.
805 to 807The provision of access for construction purposes, diversion of overhead electric cables and other public utilities’ apparatus and alteration of watercourses.
814 and 815Provision of a turning head, alteration of watercourses and access for construction purposes.
829 and 830The provision of a conveyor, spoil handling plant and machinery, and access for construction purposes.
839The use of a jetty and provision of moorings in the River Thames.
841The diversion of public utilities’ apparatus.
818, 819, 821, 822, 842 to 845 and 846 (part)The diversion of overhead electric cables and other public utilities’ apparatus.
846 (part) and 847 to 849The diversion of overhead electric cables, high pressure gas pipelines and other public utilities’ apparatus.
London Borough of Havering1 to 4The provision of access for construction purposes.
7, 8, 10 (part), 11 and 12The provision of electricity supply apparatus, diversion of gas pipelines, overhead electric cables and other public utilities’ apparatus and provision of a working site.
10 (part) and 15, 16, 17 (part) and 18 (part)The diversion of high pressure gas pipelines, overhead electric cables and other public utilities’ apparatus.
10 (part)Connection of diverted high pressure gas pipelines to the existing network.
10 (part)The provision of a balancing pond, a working site, diversion of public utilities’ apparatus and permanent access for operational purposes.
19 to 22The construction of a turning head and provision of a footbridge.
17 (part) and 18 (part)The diversion of public utilities’ apparatus.
18 (part)The provision of permanent access for operational purposes.
25 to 30 and 45The provision of a working site and access for construction purposes.
18 (part), 50 (part), 51, and 61The provision of flood storage land at Rainham Creek.
50 (part) and 59 to 66The diversion of overhead electric cables.
55 and 56The provision of access for construction purposes.
18 (part), 52, 53, 79 (part), 80 (part) and 81 to 83The diversion of high pressure gas pipelines.
57, 72 and 73The construction of a turning head and provision of a new footbridge.
79 (part) and 80 (part)The provision of a working site, alteration of watercourses and diversion of overhead electric cables.
79 (part)The diversion of a high pressure gas pipeline and alteration of watercourses.
79 (part), 80 (part) and 84 (part)The diversion of a high pressure gas pipeline and provision of access for construction purposes.
84 (part) and 86 (part)The diversion of a high pressure gas pipeline, diversion of overhead electric cables, alteration of watercourses and landscaping.
85The provision of noise barriers.
87 (part), and 88The provision of access for construction purposes and permanent access for operational purposes.
87 (part), 89 and 90 (part)The provision of noise barriers and diversion of overhead electric cables.
84 (part) and 86 (part)The provision of landscaping, alteration of watercourses and permanent access for operational purposes.
86 (part)The alteration of watercourses.
90 (part) to 92The alteration of watercourses.
93 and 94The diversion of overhead electric cables, high pressure gas pipeines and other public utilities’ apparatus.
95 to 107The diversion of overhead electric cables.
108The diversion of public utilities’ apparatus.
109The diversion of overhead electric cables.
London Borough of Hammersmith and Fulham1, 2 and 8 to 12The provision of access for construction purposes and permanent access for operational purposes.
COUNTY OF ESSEX
Borough of Thurrock4 (part)The alteration of watercourses.
42 and 44The diversion of water and gas pipes.
39 and 45The provision of a working site and permanent access for operational purposes.
47 and 48 (part)The provision of landscaping.
46, 48 (part), 49 and 51The provision of a working site, landscaping and access for construction purposes.
48 (part) and 50The provision of access for construction purposes.
54 (part) and 55 (part)The provision of access for construction purposes.
52, 54 (part) and 55 (part) to 67The provision of access for construction purposes.
81, 83, 84, 89, 93, 94, 96 and 98The provision of a working site and access for construction purposes.
91 and 92The provision of a spoil disposal site.
100The construction of a ventilation shaft, provision of permanent access thereto and a working site.
101 and 102The provision of permanent access to a ventilation shaft and a working site.
104The diversion of overhead electric cables, provision of a working site and diversion of high pressure gas pipelines.
107The provision of a working site and permanent access for operational purposes.
108 and 155The provision of access for construction purposes and permanent access for operational purposes.
109 to 114The diversion of overhead electric cables.
120 and 126The provision of landscaping, diversion of overhead electric cables and provision of access for construction purposes.
128 and 129The diversion of overhead electric cables.
130The provision of landscaping, diversion of overhead electric cables and access for construction purposes.
131, 137 and 138The diversion of overhead electric cables.
141 and 142The provision of access to public utilities’ apparatus.
COUNTY OF KENT
Borough of Dartford, Parish of Swanscombe and Greenhithe1 and 2Use of working jetty and moorings in the River Thames.
2 (part) and 3 (part)The provision of working sites, spoil settlement lagoons, and spoil disposal.
2 (part)The provision of working sites, access for construction purposes and spoil disposal.
2 (part)The provision of a ventilation shaft and permanent access thereto, and a working site.
2 (part) and 11 (part)The provision of access for construction purposes.
11, 13 and 14The provision of access for construction purposes.
15 (part)The provision of access for construction purposes.
15 (part), 18, 19, 20, 24 and 25 (part)The provision of landscaping and access for construction purposes.
25 (part), 26 to 32 and 33 (part)The provision of an international and domestic passenger station with ancillary development and parking, diversion of overhead electric cables and provision of access for construction purposes.
21, 22, 23 and 25 (part)The provision of access for construction purposes.
25 (part)The diversion of overhead electric cables.
36 and 39The diversion of overhead electric cables and provision of a new access to Northfleet West Grid sub-station.
25 (part), 41 and 42The provision of access for construction purposes and diversion of overhead electric cables.
33The diversion of overhead electric cables.
Borough of Dartford, Parish of Southfleet11Alteration of overhead electric cables.
12 and 13The provision of access for construction purposes.
16, 19 and 32 (part)The diversion of underground electric cables.
26The provision of access for construction purposes.
19 (part)The provision of a working site, access for construction purposes and landscaping.
19 (part)The provision of a working site, and diversion of overhead electric cables.
74The provision of a working site, protective works and landscaping.
49 (parts)The provision of working sites.
53The provision of a working site and access for construction purposes.
49 (part) and 54The provision of access for construction purposes and permanent access to electrical apparatus.
44The provision of a balancing pond.
11, 14 and 31, 32 (part), 33 and 34The provision of a working site, access for construction purposes and diversion of overhead electric cables.
Borough of Dartford, Parish of Longfield and New Barn2, 5 and 6The provision of a balancing pond, landscaping, diversion of a high pressure gas pipeline and access for construction purposes.
9 and 12The diversion of a high pressure gas pipeline, provision of balancing ponds and access for construction purposes.
10The provision of a working site, protective works and landscaping.
Borough of Gravesham, Town of Gravesend1The provision of spoil settlement lagoons and spoil disposal.
2, 3 and 4The provision of access for construction purposes.
10The diversion of overhead electric cables.
12 to 14The provision of access for construction purposes.
15, 16 (part) and 17 (part)The diversion of overhead electric cables.
16 (part) and 17 (part)The diversion of overhead electric cables.
16 (part), 17 (part), 22 to 30 (part), 31 (part), 32 (part), 33 (part), 34 (part), 45 (part) and 46 (part)The provision of an international and domestic passenger station with ancillary development and parking and access for construction purposes.
31 (part), 32 (part), 33 (part), 34 (part), 35 and 36The diversion of overhead electric cables, landscaping and access for construction purposes.
16 (part), 45 (part) and 46 (part)The provision of access for construction purposes.
30 (part)The provision of protective works for a pumping station and access for construction purposes.
44, 47, 48, 62 and 63The provision of a working site, spoil disposal site and use of jetty and rail access.
30 (part)The provision of landscaping.
42The provision of access for construction purposes.
70 (part)The provision of a working site.
68The provision of access for construction purposes and permanent access for operational purposes.
30 (part), 31 (part), 70 (part) and 71 (part)The provision of access for construction purposes.
37 and 74 to 79The alteration of overhead electric cables, the provision of access for construction purposes, a working site and permanent access for operational purposes.
72The alteration of overhead electric cables.
78, 80 and 81The provision of access for work on overhead electric cables.
88, 89 (part) and 90 to 93The provision of a working site, a balancing pond, diversion of overhead electric cables and permanent access for operational purposes.
99, 100 (part) and 101 (part)The provision of a working site and landscaping.
93, 100 (part), 101 (part) and 102The provision of landscaping.
97The diversion of overhead electric cables and provision of landscaping.
105, 107 and 108The provision of a spoil disposal site and landscaping.
109 to 112The provision of pedestrian access, a footbridge, a working site and access for construction purposes.
District of Sevenoaks, Parish of Horton Kirby and South Darenth3, 4 and 5The provision of an electricity supply to an existing railway and permanent access for operational purposes.
2The diversion of a high pressure gas pipeline.
District of Sevenoaks, Parish of Swanley1The provision of electricity supply apparatus to existing railway.
Borough of Gravesham, Parish of Cobham1 to 6 and 7 (part)The provision of landscaping, a spoil disposal site and permanent access for operational purposes.
7 (part)The diversion of a high pressure gas pipeline.
9 (part)The provision of a spoil disposal site and diversion of overhead electric cables.
9 (part), 10, 11 and 12The provision of a balancing pond, landscaping, diversion of a high pressure gas pipeline, overhead electric cables, a connection to electricity supply apparatus and permanent access for operational purposes.
9 (part)The provision of electricity supply apparatus, connection to the electricity supply and permanent access for operational purposes.
23, 25, and 26The diversion of a water pipe.
28The provision of a working site and temporary road diversion.
34 (part)The diversion of a footpath.
34 (part) and 40 (part)Restoration of Repton Ponds.
40 (part)The provision of a working site.
42 (part)The provision of landscaping, diversion of a high pressure gas pipeline and permanent access for operational purposes.
42 (part) and 47The provision of a working site, access for construction purposes and permanent access for operational purposes.
42 (part)The provision of electricity supply apparatus.
48The diversion of pipelines, diversion of a footpath and landscaping.
Borough of Gravesham, Parish of Higham9 and 10The provision of access to a railhead to be used for construction purposes.
Borough of Gravesham, Parish of Shorne1 and 2Alteration of overhead electric cables.
18The provision of access to a railhead to be used for construction purposes.
City of Rochester Upon Medway, Parish of Cuxton4The diversion of pipelines, diversion of a footpath and landscaping.
5 and 6The provision of a working site, new woodland planting and landscaping.
11 to 18, 21, 22, 27 and 29The provision of a working site, permanent access for operational purposes to Medway Bridge (comprised in Work No. 13), access for construction purposes and landscaping.
City of Rochester Upon Medway, Town of Rochester8, 9, 10 and 12The provision of a spoil disposal site and access for construction purposes.
27 to 30 (part), 33 (part) and 39 (part)The provision of a working site and access to the River Medway for construction purposes.
18 to 22, 30 (part), 33 (part) and 39 (part)The provision of drainage works.
36, 49, 52, 53 and 62Access for construction purposes and permanent access for operational purposes.
39 (part)The provision of a working site, access for construction purposes and landscaping.
40, 45, 46, 48, 51 and 63The provision of a working site, landscaping, and protective works to water mains.
64 and 67The provision of landscaping.
65, 68, 69 and 71The provision of access for construction purposes.
Borough of Tonbridge and Malling, Parish of Wouldham1 and 2The provision of access for construction purposes.
11 and 13The provision of new woodland planting.
Borough of Tonbridge and Malling, Parish of Aylesford1, 4, 29 and 41The provision of a working site and access for construction purposes.
190 (part)The provision of a working site and landscaping.
190 (part) and 193 to 195The provision of a working site, access for construction purposes, landscaping, a balancing pond, diversion of overhead electric cables and permanent access for operational purposes.
190 (part)The provision of electricity supply apparatus and permanent access for operational purposes.
Borough of Maidstone, Parish of Boxley38 (part)The provision of electricity supply apparatus and permanent access for operational purposes.
37, 38 (part), 39, 40, 41 and 42 (part)The diversion of overhead electric cables and landscaping.
38 (part), 42 (part) and 43The provision of drainage works, landscaping and access for construction purposes.
44 (part)The provision of landscaping and diversion of overhead electric cables.
44 (part)The provision of a balancing pond and permanent access for operational purposes.
44 (part) and 45 to 49The provision of a working site, drainage works and landscaping.
52 (part) and 53The provision of landscaping and permanent access to a balancing pond and for operational purposes.
52 (part) and 54 (part)The provision of landscaping, footpath diversion and diversion of overhead electric cables.
54 (part) and 58The provision of drainage works.
60The provision of new woodland planting.
73, 74, 80, 81, 82, and 86 (part)The provision of a balancing pond, landscaping, diversion of a gas pipeline and permanent access for operational purposes.
86 (part)The provision of a working site and a footpath diversion.
86 (part), 88 and 89 (part)The provision of access for construction purposes.
89 (part) and 90The provision of new woodland planting.
Borough of Maidstone, Parish of Detling1The provision of a working site and access for construction purposes.
4 and 7 (part)The provision of access for construction purposes.
5, 7 (part) and 8The provision of a balancing pond, landscaping and permanent access for operational purposes.
14 and 17The provision of a balancing pond and permanent access for operational purposes.
Borough of Maidstone, Parish of Thurnham1 and 3The provision of new woodland planting.
5The provision of a working site and access for construction purposes.
8The provision of a balancing pond, diversion of a footpath, landscaping and permanent access for operational purposes.
14The provision of a site for nature conservation.
18The provision of a working site, landscaping and access for construction purposes.
Borough of Maidstone, Parish of Hollingbourne1, 3, 4 (part) and 5The provision of a working site, landscaping and access for construction purposes.
4 (part), 6, 9 and 10 (part)The provision of access for construction purposes and permanent access for operational purposes.
7 (part) and 8Alteration of a watercourse, provision of a balancing pond and permanent access for operational purposes.
7 (part), 16, 17 and 18The provision of drainage works.
10 (part)The provision of drainage works, a balancing pond and permanent access for operational purposes.
11, 13 and 14The provision of landscaping.
19, 20, 24 and 26The provision of permanent access for operational purposes.
29, 32 and 33The provision of balancing ponds and permanent access for operational purposes.
Borough of Maidstone, Parish of Leeds1The provision of access for construction purposes.
Borough of Maidstone, Parish of Harrietsham8, 9 and 10The provision of a balancing pond, drainage works and permanent access for operational purposes.
13The provision of drainage works, a balancing pond and a working site.
2, 20, and 21The diversion of public utilities’ apparatus.
32, 34 and 35 to 38 (part)The provision of balancing ponds, drainage works, a working site, access for construction purposes and footpath diversions, landscaping and permanent accesses for operational purposes.
38 (part), 41 and 42The provision of landscaping and access for construction purposes.
43, 45 and 46The provision of a waste disposal site, borrow pit, protective works, landscaping and access for maintenance and construction purposes.
Borough of Maidstone, Parish of Ulcombe1The provision of a balancing pond, drainage works and permanent access for operational purposes.
Borough of Maidstone, Parish of Lenham6The provision of a waste disposal site, borrow pit, protective works, landscaping and access for maintenance and construction purposes.
10 and 11The provision of drainage works and access for construction purposes.
20 (part)The provision of a spoil disposal site and a balancing pond.
20 (part)The provision of a spoil disposal site.
33 and 34The provision of a balancing pond.
87 to 89 (part)The provision of permanent access for operational purposes.
89 (part), 90 and 91The provision of permanent access for operational purposes.
Borough of Ashford, Parish of Charing21 and 22The provision of landscaping and new woodland planting.
38 and 39The provision of landscaping.
51The provision of replacement access to premises.
66The diversion of public utilities’ apparatus.
76 and 77The provision of an accommodation access.
68, 70, 71 and 72The provision of drainage works.
Borough of Ashford, Parish of Hothfield1 and 2The provision of drainage works.
6The provision of access for construction purposes.
7, 8 (part), 10 (part) and 12 (part)The provision of access for construction purposes and permanent access for operational purposes.
8 (part), 10 (part), 11, and 12 (part)The provision of a working site, landscaping and permanent access for operational purposes.
12 (part), 14 and 16The provision of a working site, landscaping and permanent access for operational purposes.
Borough of Ashford, Parish of Westwell1, 4, 5, and 20 (part)The provision of a working site, spoil disposal site, landscaping and permanent access for operational purposes.
16, 17, 18, 19, 20 (part) and 21 (part)The provision of a working site and landscaping.
21 (part), 24, 25, 26, 27, 40, 41 and 42The provision of access for construction purposes, a working site and landscaping.
44 and 45The provision of landscaping.
47 and 48The provision a spoil disposal site and landscaping.
56, 57, 60 (part), 65 and 67The provision of a borrow pit, spoil disposal site, access for construction purposes, an accommodation access and landscaping.
49 and 60 (part)The provision of access for construction purposes and permanent access for operational purposes.
Borough of Ashford, Town of Ashford8The provision of a working site and landscaping.
6, 10, 12 (part) and 13The provision of drainage works and diversion of a gas main.
12 (part) and 14 (part)The provision of accommodation access to premises, landscaping and a working site.
14 (part) and 16The provision of a working site.
14 (part) and 15The provision of a working site and access for construction purposes.
34 to 37 and 48The provision of a working site and access for construction purposes.
59 to 73 and 76The provision of a working site and access for construction purposes.
78 (part)The provision of a working site and access for construction purposes.
46, 78 (part), 79 and 80The provision of a working site and access for construction purposes.
85, 86, 89, 94 and 95The provision of a working site and access for construction purposes.
84 and 88The provision of access for construction purposes and permanent emergency access to the gas holder station and depot.
92, 93, 98 (part), 99 and 100The provision of access for construction purposes and permanent emergency access to the gas holder station and depot.
110, 111, 117 and 122The provision of a working site and access for construction purposes.
125 (part) and 131The provision of a working site and access for construction purposes.
178, 181, 183, 194 and 195The provision of flood storage lands and access for construction purposes.
144, 145, 177, 179, 180, 184, 185 and 186The provision of drainage works and access for construction purposes.
238 to 241The provision of a working site and access for construction purposes.
Borough of Ashford, Parish of Sevington5The provision of drainage works, a balancing pond and permanent access for operational purposes.
7 and 8The provision of a working site, access for construction purposes and permanent access for operational purposes.
9 and 12 (part)The provision of drainage works, a balancing pond and permanent access for operational purposes.
12 (part), 16 and 19The provision of a railhead, a working site, a balancing pond, access for construction purposes and permanent access for operational purposes.
28The provision of a working site.
34The provision of drainage works and access for construction purposes.
33The provision of a spoil disposal site.
35The provision of access for construction purposes, permanent access for operational purposes and dedication of road as a public highway connecting to Bad Munstereifel Road.
Borough of Ashford, Parish of Mersham1The provision of a spoil disposal site.
4The provision of drainage works, noise barriers and access for construction purposes.
11, 14, 15, 17, 20 and 27The provision of drainage works, a balancing pond, noise barriers, landscaping, access for construction purposes and permanent access for operational purposes.
19, 21, 22, 25 and 26The provision of landscaping, access for construction purposes and permanent access for operational purposes.
37, 41, 42, 45 and 46The provision of a working site, access for construction purposes, diversion of public utilities’ apparatus, a balancing pond and permanent access for operational purposes.
43The provision of noise barriers and drainage works and access for construction purposes.
Borough of Ashford, Parish of Smeeth6, 8, 13 and 16The provision of drainage works, footpath diversions, landscaping and permanent access for construction purposes.
24, 27The provision of access for construction purposes.
9, 10, 11 and 12The provision of drainage works, a balancing pond, landscaping and permanent access for operational purposes.
21 and 28The provision of flood storage lands.
30 (part) and 31The provision of a working site and access for construction purposes.
30 (part)The provision of electricity supply apparatus, landscaping and permanent access for operational purposes.
32 to 34The provision of access for construction purposes and alteration of overhead electric cables.
35The provision of noise barriers and access for construction purposes.
Borough of Ashford, Parish of Aldington5 and 7 (part)The provision of electricity supply apparatus, landscaping and permanent access for operational purposes.
7 (part), 12, 13 (part) and 14The provision of electricity supply apparatus and access for construction purposes.
3, 6 and 10The diversion of overhead electric cables.
13 (part), 19 and 20The provision of a working site, landscaping and access for construction purposes.
District of Shepway, Parish of Sellindge3, 4 and 5The provision of noise barriers and access for construction purposes.
1, 2 and 6The provision of a working site, diversion of overhead electric cables and access for construction purposes.
8Strengthening of railway embankment and diversion of overhead electric cables.
9 and 11The diversion of electric high voltage underground cables.
12, 14 and 15The diversion of electric high voltage underground cables and access for construction purposes.
16, 26 and 32 (part)The diversion of electric high voltage underground cables, the provision of noise barriers and access for construction purposes.
32 (part), 33, 46 and 47The alteration of overhead electric cables, provision of noise barriers and access for construction purposes.
30The alteration of overhead electric cables.
44, 45 and 60The provision of access for construction purposes.
District of Shepway, Parish of Stanford1 (part)The provision of noise barriers and access for construction purposes.
1 (part) and 2The provision of landscaping and access for construction purposes.
8 and 9 (part)The provision of drainage works, noise barriers, a working site and access for construction purposes.
7, 9 (part), 17, 18 and 19The provision of access for construction purposes.
District of Shepway, Parish of Saltwood1 and 3The provision of a working site, accommodation works and access for construction purposes.
7The provision of a balancing pond and permanent access for operational purposes.
13 to 16The provision of a working site and access for construction purposes.
26The provision of a footpath.
30The provision of drainage works.
37, 38 and 39The provision of a bridleway diversion, reconstruction of a bridleway bridge, provision of a working site, diversion of public utilities’ apparatus and access for construction purposes.
District of Shepway, Parish of Postling6 and 8The provision of permanent access for operational purposes.
11 and 14 to 18The provision of a working site and access for construction purposes.
District of Shepway, Parish of Newington3 and 4The provision of a working site and access for construction purposes.
6 and 9The provision of access for construction purposes.
17 and 27 (part)The provision of a spoil disposal site and access for construction purposes.
14, 15, 16, 19, 20, 21, 32 and 37The provision of access for construction purposes.
31 and 40The provision of working sites and access for construction purposes.
27 (part)The provision of access for construction purposes.
13, 25 and 29The provision of access for construction purposes, and permanent access to a balancing pond and for operational purposes.
60 and 61The provision of access for construction purposes and permanent access for operational purposes.
62The provision of access for construction purposes.
District of Shepway, Parish of Hythe1The provision of access for construction purposes.
District of Shepway, Town of Folkestone1Alteration of railway track equipment.
2 and 3The provision of access for construction purposes, and permanent access to a balancing pond and for operational purposes.
4 (part)The provision of access for construction purposes and permanent access for operational purposes.
4 (part)The provision of lineside equipment and permanent access for operational purposes.
6The provision of a working site and access for construction purposes.
District of Thanet, Parish of Minster2The provision of access to a railhead to be used for construction purposes.
Borough of Dover, Parish of Sandwich1The provision of access to a railhead to be used for construction purposes.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources