428.This section requires the Secretary of State to publish an annual report on the availability of electricity and gas for meeting the reasonable demands of consumers in Great Britain, and to lay that report before Parliament. The report must deal with both the short and long term, and must cover in particular:

  • electricity generating capacity;

  • the availability of capacity in electricity transmission and distribution systems;

  • the availability of capacity in gas infrastructure; and

  • the availability of capacity in licensed gas pipe-line systems.

The report must be prepared jointly by the Secretary of State and GEMA.

Section 173: Appeals to the Competition Commission

429.This section sets out on what grounds a permission for an appeal may be granted, and by whom, and gives the Secretary of State powers to designate by order what codes come within the scope of the appeals procedure and what sort of decisions are excluded.

430.Subsection (2) restricts appeals to decisions on modifications to those codes designated by the Secretary of State, which do not match the description of decisions that are excluded by the Secretary of State under subsection (2)(d). It enables the Secretary of State to make an order by negative resolution designating the codes where modification decisions are to be appealable. The Government will consult on the codes to be designated, but its initial view is that the appeals mechanism is to be applicable to modifications to the Transco Network Code for gas, and the Balancing and Settlement Code (“BSC”) and the Connection and Use of System Code (“CUSC”) for electricity.

431.Subsection (3) restricts the right of appeal to people “materially affected” by the decision or bodies representing people so “materially affected”. Those “materially affected” are likely to include but may not be restricted to: parties to the framework agreement applicable to the code which is the subject of the appeal; persons holding licences granted under section 6 of the Electricity Act 1989 (c.29) and sections 7 and 7A of the Gas Act 1986 (c.44) who are obliged by licence condition to comply with the relevant code; Energywatch and other interested groups representing consumer, licensee or other trading party interests. All applicants for appeal will have to meet the “materially affected” test in the circumstances of the particular appeal.

432.Subsections (4) and (5) provide that the Competition Commission may refuse permission to appeal if the appeal is trivial or vexatious or has no reasonable prospect of success.

433.Subsection (6) requires the Secretary of State, when making an order under subsection (2) which designates a code or excludes certain types of decision from the appeals process, to consult with GEMA and other appropriate persons. Subsection (8) provides that such an order is to be subject to the negative resolution procedure. The Government will consult on the terms of the order, but its initial view is that decisions should be excluded which are urgent or where the delay occasioned by an appeal could impact on security of supply or where GEMA’s decision agrees with the recommendation of the panel in the case of the BSC, or with a certain proportion of code participants in the case of the CUSC and the Transco Network Code.

Section 174 and Schedule 22: Procedure on appeals

434.The effect of section 174 and Schedule 22 is to set out an appeals procedure whereby applicants have 15 working days (counting from the day after the day on which GEMA’s decision is published) to submit an appeal against a GEMA decision on a code modification to the Competition Commission. An application for permission to appeal must be accompanied by all such information as the Competition Commission may require under its appeal rules. The Competition Commission has 10 working days from the submission of the application to decide whether to grant or refuse the application for permission to appeal. GEMA has 15 working days after the submission of the application for permission to appeal to submit its representations or observations, should it choose to do so. The Competition Commission will then carry out a review to a tight timetable of whether GEMA discharged its duties correctly; this may include a hearing at which the parties can make representations and answer questions, and a further hearing to determine the appeal. It must normally reach its decision within 30 working days following the last day for the making of representations or observations by GEMA but it can extend this period by a maximum of 10 working days if necessary. The Competition Commission will be able to confirm or quash the original decision, or remit it to GEMA with directions to reconsider taking into account certain factors. This time line is presented below:

435.Further information can be found in the notes to Schedule 22.

Section 175: Determination of appeals

436.This section sets out how the Competition Commission is to reach its decisions on appeals and what it must do on reaching a decision.

437.Subsection (2) provides that in determining the appeal the Competition Commission must have regard, to the same extent as GEMA, to the statutory duties which are placed on GEMA. Subsection (3) provides that the Competition Commission must not have regard to any matter which GEMA was not entitled to have regard to when making its decision, though it may consider fresh evidence if GEMA would have been entitled to have regard to it had it had the opportunity to do so. Subsection (4) provides that the Competition Commission may allow the appeal only if it is satisfied: that GEMA failed to have proper regard to the applicable code objectives, or to the regulator’s statutory obligations, or failed to give the proper weight to one or more of the above; that the decision was based on an error of fact and/or that the decision was wrong in law.

438.Subsection (6) provides that if the appeal is successful then the Competition Commission must do one or more of the following: (i) quash the decision, (ii) remit it to GEMA with directions for reconsideration and determination or, (iii) if it is quashing a refusal of consent, give appropriate directions for securing that the relevant condition has effect as if the consent had been given.

439.Subsection (9) sets out the way in which the Competition Commission is required to publish its decision, including the reasons for the decision.

440.Subsection (10) allows the Commission to exclude certain information from the reasons for its decision on the grounds of confidentiality when publishing its decision for the attention of persons beyond the parties under subsection (9).

Section 176: Specialist members of Competition Commission

441.This section provides that the Competition Commission’s functions with respect to appeals are to be treated as functions of the Competition Commission under section 104 of the Utilities Act 2000 (c.27).

Section 177: Modifications of standard conditions for funding appeals and references

442.This section gives the Secretary of State power, after consulting licence holders, to make an order amending gas and electricity licences to change the licence charges in order to fund the appeals mechanism provided for in sections 173 to 176, and the existing arrangements for licence modification references. It is intended to use this power in respect of appeals to allow GEMA to raise the funds it needs to pay the costs of an appeal as ordered by the Commission. Where an appeal is upheld this will consist of its own costs, possibly the costs of the appellant and the costs of the Competition Commission. It is intended to use this power in respect of licence condition references to give the Competition Commission, rather than GEMA, the discretion to allocate the Competition Commission’s costs in licence modification references. These costs will then be recovered by GEMA, after the Competition Commission has indicated the proportions that individual licensees should pay of the Competition Commission’s costs.

Section 178: Duty to have regard to best regulatory practice

443.Section 178 inserts a subsection into section 4AA of the Gas Act 1986 and section 3A of the Electricity Act 1989 which provides that the Secretary of State and GEMA are to have regard to the principles of best regulatory practice when performing their functions in accordance with the principal objective and general duties. The key principles of best regulatory practice are: transparency, accountability, proportionality, consistency and targeting.

Section 179: Meaning of electricity supply

444.Section 179 provides for electricity conveyed by a transmission system to a substation, and then supplied from there to premises, to be brought within the definition of supply in section 4 of the Electricity Act 1989, as amended by the Utilities Act. This will close an anomaly in the definition of supply which defines electricity supply as supply by means of a distribution system and therefore excludes the conveyance of electricity to customers whose supply of electricity does not pass through a distribution network.

Section 180: Meaning of “high voltage line”

445.This section defines “high voltage line” in respect of offshore electric lines as such lines which are of a nominal voltage of 132 kilovolts or more. This is the same as the definition of high voltage lines in Scotland. The section does not change the definition of “high voltage line” in respect of onshore electric lines in Great Britain.

Section 181: Prepayment meters

446.Section 181 provides GEMA with the power, with the consent of the Secretary of State, to make regulations to extend the range of sums that could be collected from a prepayment meter. GEMA is required to consult interested parties, including the Gas and Electricity Consumers Council, before making regulations.

447.At present, sums recovered through a prepayment meter may only be in respect of an individual fuel and may only be in respect of supply to the premises at which the meter is sited or the provision of the meter. The section makes clear that the extended range of sums that could be collected includes debts owed to a person other than the current gas or electricity supplier, debts accrued in respect of other premises, or debts accrued in respect of the supply of other fuels. Any sums covered by the new regulations may only be recovered with the agreement of the consumer, the circumstances in which such an agreement may be made being set out in the regulations.

Section 182: Additional inspectors

448.Section 182 fulfils the Government’s commitment set out in paragraph 4.33 of the Energy White Paper, “Our energy future – creating a low carbon economy” (Cm 5761), to apply proposals by Government for major infrastructure projects handled in the planning process in England to major energy projects in England and Wales where consents are awarded by the Secretary of State. The proposals are to streamline the public inquiry process by allowing lead inspectors to be assisted by further inspectors to share the work and allow issues to be considered concurrently rather than sequentially as at present. These proposals for major infrastructure projects are contained in section 44 of the Planning and Compulsory Purchase Act 2004 (c.5). This section seeks to allow that approach to be adopted for power stations and overhead line developments considered by the Secretary of State under section 36 and section 37 respectively of the Electricity Act.

449.The Energy White Paper noted that such an approach should help streamline planning processes for large renewable energy developments and other large generation plant and for major upgrades of the transmission network. It was not anticipated that it would be used for all public inquiries into power stations and overhead line developments since some inquiries could be adequately handled by a single inspector. But it would be an option available if a particular development warranted it.

450.The section provides for the Secretary of State to direct an inspector appointed for a public inquiry into a particular development to expressly consider the handling of that inquiry and for that inspector to then make recommendations on that to the Secretary of State. It is anticipated that one of the handling issues would be whether the inquiry could be effectively, and more efficiently, handled by having some issues handled concurrently. In the light of the inspector’s recommendations the Secretary of State would then appoint an appropriate number of additional inspectors for the public inquiry. These additional inspectors would then work to the inspector initially appointed (the lead inspector) handling particular issues. The lead inspector would then report to the Secretary of State taking account of the reports of the additional inspectors on particular issues.

451.This alternative approach to the handling of a public inquiry it is anticipated will require some adjustment to the current public inquiry rules governing procedural matters which are based on a single inspector considering matters, the Electricity Generating Stations and Overhead Lines (Inquiries Procedure) Rules 1990 (SI 1990/528). Revised rules would therefore need to be drawn up in consultation with the Department for Constitutional Affairs and placed before Parliament for scrutiny in due course.

452.The section covers the exercise of the Secretary of State’s powers and as such would extend to proposals in England and Wales, the territorial sea adjacent to England and Wales, and to proposals in Renewable Energy Zones established under Part 2 of this Act. Decisions on section 36 and 37 developments in Scotland and in the territorial sea adjacent to Scotland are handled by Scottish Ministers.

Section 183: Exclusion of confidential information from registers

453.Section 183 inserts new subsections into the Electricity Act 1989 and the Gas Act 1986 which allow GEMA, when entering information on the registers it is required to maintain under section 49 of the Electricity Act 1989 and section 36 of the Gas Act 1986, to exclude details in certain circumstances. GEMA can exclude such details as it considers appropriate to maintain the confidentiality of matters, relating either to an individual or a body of persons, where publication of those details might, in GEMA's opinion, seriously and prejudicially affect the individual or body of persons.

Section 184: Assistance for areas with high distribution costs

454.This section gives the Secretary of State the power to make an order to establish a scheme requiring authorised transmitters (in practice the Great Britain System Operator) to make a payment to a distributor when that distributor faces costs that are significantly higher than in other areas of Britain. The power will be exercisable in respect of a single area to be specified in the order. In order to qualify for a payment, the distributor must be one which distributes electricity by means of a distribution network when at least 100,000 premises are connected to that same network. The payment must be passed from the distributor to suppliers within the relevant area. The scheme will be funded by charges on suppliers across Britain.

455.The Secretary of State must consult before establishing a scheme, and must carry out a review of the scheme every three years.

456.This section is intended to replace a licence condition formerly imposed on SSE Generation Limited known as “Hydrobenefit” which was removed in January 2004. It is intended that this section will benefit customers in the north of Scotland, where there are the highest distribution costs in Britain by a significant margin.

Section 185: Adjustment of transmission charges

457.Section 185 provides the Secretary of State with the power to adjust electricity transmission charges for renewable generators within a single area that can be shown to be of high renewable energy potential, and where evidence would indicate that unadjusted transmission charges might have a material impact on development of the generation of electricity from renewable sources. Subsection (2)(b) requires any costs arising from the scheme to be spread across all GB supply companies. The area to which the scheme is to be applied must be specified (subsection (3)) and there can only be one scheme in operation at any one time (subsection (10)). Subsections (11) and (12) specify that any one scheme can be applied for a maximum of 5 years. There is a power to renew a scheme at any time by a further order, but no scheme may be applied in relation to a time more than ten years from the commencement of the section. Subsection (15) provides for an order establishing any scheme to be subject to the affirmative resolution procedure.

Section 186: Restrictions on disclosure of information

458.This section provides for the protection of information provided under the Hydrobenefit replacement scheme (Section 184 – assistance for areas with high distribution costs) and the adjustment of transmission charges for renewable generators scheme (Section 185) through the application of section 105 of the Utilities Act 2000. It will be an offence to disclose information provided under these schemes, except in those circumstances specified under section 105.

Section 187: Payments of sums raised by fossil fuel levy

459.Section 187 provides a power for Scottish Ministers to direct GEMA to pay into the Scottish Consolidated Fund monies from funds paid to GEMA and arising from the auctioning of electricity generated under Scottish Renewables Obligation (“SRO”) contracts. There is also a corresponding duty on Scottish Ministers to include provision in budget proposals to the Scottish Parliament that monies thus raised shall be used to promote the use of energy from renewable sources. This will enable the Scottish Executive to provide the additional support necessary to meet its commitment to increasing the amount of renewable energy produced in Scotland. Similar powers as regards monies arising from the auctioning of electricity generated under NFFO (Non Fossil Fuel Obligation) contracts in England and Wales are contained in section 7 of the Sustainable Energy Act 2003 (c.30).

460.The SRO was the support scheme for electricity generated from renewable sources that was introduced under the original sections 32 and 33 of the Electricity Act 1989, which were executively devolved to Scottish Ministers. Under the SRO scheme, Orders were made which required Scottish public electricity suppliers (the successors to the old nationalised electricity boards) to buy electricity generated from renewable sources under "SRO contracts". The price paid for the electricity under those contracts was above the market price for electricity and the public electricity suppliers were compensated for this by payments out of the money collected through the Fossil Fuel Levy that was provided for in section 33 of the Electricity Act. The levy was charged on the electricity supplies of all licensed electricity suppliers and was paid out to the smaller number of electricity suppliers which were subject to the SRO Orders.

461.Sections 62 to 65 of the Utilities Act inserted into the Electricity Act new sections 32 to 32C, which contain provisions allowing the introduction of the GB Renewables Obligations, the successor to the SRO scheme and its English / Welsh equivalent. This scheme has been implemented in Scotland by the Renewables Obligation (Scotland) Order 2002 (S.S.I. 2002/163). The scheme requires each licensed electricity supplier to produce evidence that it has supplied a specified proportion of its electricity from renewable sources or that other electricity suppliers have done so. The evidence that it has to produce is Renewable Obligation Certificates (“ROCs”) issued by GEMA. If the supplier does not produce the necessary number of Certificates, it has to make a payment (the buy-out price) to GEMA. It is this that gives the Certificates a value.

462.The SRO contracts are long-term, and the last of them will not expire until 2018. The price paid by the suppliers for the electricity under those contracts is above the market price, and they are compensated by payments out of the Fossil Fuel Levy. SRO output is also eligible for ROCs under the Renewables Obligation (Scotland) Order, and the proceeds of the sale by auction of such ROCs is now used to reduce Fossil Fuel Levy costs. As a result, there is no need at present to raise Levy funds via electricity bills, and the Levy rate (set by GEMA) is currently set at zero.

463.The income currently being realised through the auction of SRO ROCs exceeds its expenditure, owing to the value of the Renewable Obligation Certificates associated with the NFFO electricity. The Scottish supply successor companies are required, under subsection (5A) of section 33 of the Electricity Act (as that section is now amended and preserved in Scotland by Orders under section 67 of the Utilities Act), to pay to GEMA (the person prescribed under section 33(1)(b) of the Electricity Act) the surplus that arises from the auctioning of ROCs for electricity generated under SRO contracts, thereby avoiding a double subsidy to electricity generators with SRO contracts. Section 33 does not, however, make provision for the disposal of this surplus by GEMA, but this is now addressed by this section.

464.In order to give Scottish Ministers the required power over the surpluses in the Scottish Levy fund, a separate section, covering section 33 of the Electricity Act as it applies in Scotland, required to be inserted in the Act at Westminster. Although the existing powers under section 33 were executively devolved to Scottish Ministers, and have subsequently been amended, the legislation on using the surplus in Scotland had to be obtained through the Westminster procedures because it amends the Electricity Act in a way that is not consistent with the Executive’s limited devolved power to amend section 33 of that Act.

Back to top

Options/Help

Print Options

Close

Explanatory Notes

Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources