Changes over time for: Cross Heading: Conduct of access charges reviews

 Help about opening options

Alternative versions:

Changes to legislation:

There are currently no known outstanding effects for the Railways Act 2005, Cross Heading: Conduct of access charges reviews. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Conduct of access charges reviewsE+W+S

2E+W+SFor paragraph 1 (meaning of access charges review) substitute—

Application of ScheduleE+W+S

1This Schedule applies where an access agreement provides, or is treated as providing, for the Office of Rail Regulation to undertake reviews of the terms of that agreement as to—

(a)the amounts payable under the agreement by one of the parties to the other; and

(b)the times at which, and the manner in which, those amounts are payable.

Scope of reviewE+W+S

1A(1)Where the Office of Rail Regulation undertakes such a review, it must, at the same time, review the conditions of every linked licence both—

(a)in relation to the matters mentioned in paragraph 1(a) and (b); and

(b)in relation to the matters about which that Office is provided with information under paragraph 1D.

(2)A review by that Office of both—

(a)the terms of an access agreement as to the matters mentioned in paragraph 1(a) and (b), and

(b)the conditions of a linked licence,

is referred to in this Schedule as an access charges review.

(3)An access charges review must include a consideration of—

(a)the time at which the next access charges review is to be undertaken in relation to both the access agreement in question and every linked licence; and

(b)the circumstances in which it would be appropriate to undertake such a review before that time.

(4)In this Schedule “linked licence”, in relation to an access agreement, means a licence of which the holder is—

(a)the facility owner, or installation owner, who is a party to the agreement; or

(b)a person other than that owner who has an estate or interest in the railway facility or network installation to which the agreement relates or who has a right over it.

Response to request to carry out reviewE+W+S

1BWhere—

(a)the Secretary of State or the Scottish Ministers suggest to the Office of Rail Regulation that an access charges review should be carried out in any case, but

(b)that Office decides not to carry out the suggested review,

that Office must provide the Secretary of State or Scottish Ministers with its reasons for that decision.

Notice of access charges reviewE+W+S

1C(1)Before beginning an access charges review, the Office of Rail Regulation must give notice of its proposal to undertake the review to each of the following—

(a)the Secretary of State;

(b)the Scottish Ministers;

(c)the Treasury;

(d)the parties to the access agreement in question; and

(e)such other persons as that Office considers appropriate.

(2)No notice is required to be given under sub-paragraph (1) to the Secretary of State or the Scottish Ministers—

(a)in the case of the Secretary of State, if the facility or installation to which the relevant agreement relates is situated wholly in Scotland; or

(b)in the case of the Scottish Ministers, if the facility or installation to which the relevant agreement relates is situated wholly in England and Wales.

(3)A notice under this paragraph must set out—

(a)the period to which the Office of Rail Regulation expects the review to relate (“the review period”);

(b)the date by which the Secretary of State, the Scottish Ministers or (as the case may be) each of them needs to provide the information that has to be provided under paragraph 1D; and

(c)any conditions which that Office requires to be satisfied in the period ending with that date if it is to proceed with the review.

(4)The period set out under sub-paragraph (3)(a) must be the one which—

(a)begins with the time as from which the Office of Rail Regulation expects that any changes resulting from the review would fall to be implemented; and

(b)ends with the time as from which it thinks it likely (in the absence of special circumstances making an earlier review appropriate) that any changes resulting from the next access charges review in relation to the same agreement and licence would fall to be implemented.

(5)The date set out under sub-paragraph (3)(b) must be not less than the following period after the date of the notice—

(a)in a case which the Office of Rail Regulation is satisfied is a case of urgency, four weeks; and

(b)in any other case, three months.

(6)Before setting out a date under sub-paragraph (3)(b) that is less than three months after the date of the notice, the Office of Rail Regulation must consult each of the persons to whom the notice is to be given.

Duty to notify ORR about desired outputs and financesE+W+S

1D(1)Where a notice under paragraph 1C is given to the Secretary of State, he must provide the Office of Rail Regulation with—

(a)information about what he wants to be achieved by railway activities in Great Britain as a whole during the review period; and

(b)such information as it is reasonable for him to provide about the public financial resources that are or are likely to become available to be applied during the review period for purposes that contribute (directly or indirectly) towards the achievement of what he wants.

(2)Where a notice under paragraph 1C is given to the Scottish Ministers (whether instead of or as well as to the Secretary of State), they must provide the Office of Rail Regulation with—

(a)information about what they want to be achieved by Scottish railway activities during the review period; and

(b)such information as it is reasonable for them to provide about the public financial resources that are or are likely to become available to be applied during that period for purposes that contribute (directly or indirectly) towards the achievement of what they want.

(3)The information that may be provided as falling within sub-paragraph (1)(a) or (2)(a) includes objectives and standards to be achieved in the course of carrying on railway activities.

(4)Those objectives and standards may include, in particular, objectives and standards with respect to any of the following matters—

(a)the capacity (in terms of types and numbers of trains) of networks;

(b)the frequency of railway passenger services;

(c)journey times;

(d)reliability of railway services (both in terms of punctuality and otherwise);

(e)the taking of measures to prevent or mitigate overcrowding;

(f)levels and types of fares;

(g)the quality of information provided to passengers;

(h)the accessibility of railway services to people with disabilities;

(i)the carrying out of major projects to improve railway services;

(j)the protection of persons from dangers arising from the operation of railways.

(5)In a case where information is also required to be provided by the Scottish Ministers, the information that is required to be provided by the Secretary of State does not include—

(a)any information about what he wants to be achieved by Scottish railway activities not relating to cross-border services; or

(b)information about any public financial resources so far as they appear to him to be available, or to be likely to become available, to be applied for purposes relating only to such activities.

(6)An obligation of the Secretary of State or the Scottish Ministers to provide information under this paragraph—

(a)must be discharged before the date set out in the notice given under paragraph 1C or, if a later date is fixed under sub-paragraph (7), by that later date; but

(b)may be discharged by a notification that refers that Office to information previously provided under this paragraph.

(7)The Office of Rail Regulation may at any time, by notice to each of the persons to whom the notice under paragraph 1C was given, fix a later date for the provision of information under this paragraph.

(8)Neither—

(a)the Secretary of State, nor

(b)the Scottish Ministers,

are required to provide information for the purposes of a review at any time after a decision has been made by the Office of Rail Regulation not to proceed with the review because of an actual or expected failure of the conditions set out under paragraph 1C(3)(c) to be satisfied.

(9)In this paragraph “railway activities” means activities consisting in, or involving, any of the following—

(a)providing railway services;

(b)making available railway facilities;

(c)making use of such facilities;

(d)using railway assets;

(e)allowing others to use such assets.

(10)In this paragraph “Scottish railway activities” means activities which are railway activities by reference only to—

(a)railway services which begin and end in Scotland;

(b)railway services in relation to which financial assistance is provided by the Scottish Ministers and which (without falling within paragraph (a)) begin or end in Scotland;

(c)railway facilities that are situated in Scotland; or

(d)railway assets so situated.

(11)In this paragraph “public financial resources” means any of the following—

(a)money charged on and payable out of the Consolidated Fund;

(b)money provided by Parliament;

(c)money payable out of the Scottish Consolidated Fund.

Suggestions about future reviewsE+W+S

1EWhere the Secretary of State or the Scottish Ministers provide the Office of Rail Regulation with information under paragraph 1D, he or they may also, at the same time, make a suggestion to that Office setting out his or their opinion about—

(a)when the next access charges review should be undertaken in relation to both the access agreement in question and every linked licence; and

(b)the circumstances in which it would be appropriate to undertake such a review before that time.

Revision of outputs and financial informationE+W+S

1F(1)If, at any time in the course of an access charges review, it appears to the Office of Rail Regulation that—

(a)the information that has been provided to it by the Secretary of State or the Scottish Ministers under paragraph 1D, or

(b)the information, taking it all together, that has been so provided by the Secretary of State and the Scottish Ministers,

shows that the public financial resources that are or are likely to become available will be inadequate to secure the achievement of what he or they, or both of them, want to be achieved, that Office must so notify the Secretary of State or the Scottish Ministers or (as the case may be) each of them.

(2)The Office of Rail Regulation must send a copy of every notification under sub-paragraph (1) to the Treasury.

(3)On being notified under sub-paragraph (1), the Secretary of State or the Scottish Ministers or (as the case may be) each of them—

(a)may revise any information provided to the Office of Rail Regulation, together with any suggestion made under paragraph 1E; and

(b)if the information or such a suggestion is revised, must notify the revisions to that Office.

(4)Any notification under sub-paragraph (3) must be given within whatever period is specified by the Office of Rail Regulation when notifying the Secretary of State or Scottish Ministers in accordance with sub-paragraph (1).

(5)Where the Office of Rail Regulation has already given a notification under this paragraph with respect to any information, it is required to give a further notification under this paragraph with respect to that information, or any revision of it, only if—

(a)a revision has been made in response to its previous notification; and

(b)it has not previously given a notification in respect of an earlier revision of the information.

Notification of likely adverse effect on interests of certain providers of railway servicesE+W+S

1G(1)If, at any time in the course of an access charges review, it appears to the Office of Rail Regulation that it is likely that the implementation of the review will adversely affect the interests of persons providing railway passenger services or of persons providing services for the carriage of goods by railway, that Office must so notify—

(a)the Secretary of State, in the case of a review notice of which was given to him under paragraph 1C; and

(b)the Scottish Ministers, in the case of a review notice of which was given to them under that paragraph.

(2)Where the Office of Rail Regulation gives a notification under sub-paragraph (1) in respect of a review relating to an access agreement to which a facility owner is a party, the notification must include—

(a)its assessment of the measures that the facility owner is likely to be required to take, as a consequence of the implementation of the review, in order to meet obligations of his arising under the access agreement in question or under any other access agreement to which he is a party; and

(b)its estimate of the cost to the facility owner of taking those measures.

(3)On being notified under sub-paragraph (1), the Secretary of State or the Scottish Ministers or (as the case may be) each of them—

(a)may revise any information provided under paragraph 1D to the Office of Rail Regulation, together with any suggestion made under paragraph 1E; and

(b)if the information or such a suggestion is revised, must notify the revisions to that Office.

(4)Any notification under sub-paragraph (3) must be given within whatever period is specified by the Office of Rail Regulation when notifying the Secretary of State or the Scottish Ministers in accordance with sub-paragraph (1).

(5)Where the Office of Rail Regulation has already given a notification under this paragraph, it is required to give a further notification under this paragraph only if—

(a)information provided to it has been revised in response to its notification; and

(b)it has not previously given a notification in respect of an earlier revision of that information.

Duty to have regard to information about desired outputs and finances etc.E+W+S

1H(1)The Office of Rail Regulation must conduct an access charges review in the manner that it considers is most likely to secure that the implementation of the review will make the best and most practicable contribution to the achievement of—

(a)what the Secretary of State wants to be achieved by railway activities in Great Britain as a whole; and

(b)what the Scottish Ministers want to be achieved by Scottish railway activities.

(2)Where in the case of an access charges review the Office of Rail Regulation considers (notwithstanding any notification or revision under paragraph 1F or 1G) that the public financial resources that are or are likely to become available will be inadequate to secure the achievement of, as the case may be—

(a)everything that the Secretary of State wants to be achieved,

(b)everything that the Scottish Ministers want to be achieved, or

(c)everything that both the Secretary of State and the Scottish Ministers want to be achieved,

it is to be for that Office to determine, for the purposes of the review, how much of what is wanted should be achieved using (but only for the purposes for which they may be applied) all the public financial resources that it considers are or are likely to be available.

(3)In conducting an access charges review the Office of Rail Regulation must have regard to the consequences of compliance by a facility owner who is a party to the access agreement in question with any terms—

(a)of that agreement, or

(b)of any other access agreement to which that facility owner is a party,

that it considers are relevant to a matter notified under paragraph 1G (including, in particular, a term requiring the facility owner to pay compensation or to take mitigatory measures).

(4)In considering the matters mentioned in paragraph 1A(3), the Office of Rail Regulation must have regard to any suggestion made under paragraph 1E, and to any revision of that suggestion.

(5)For the purposes of this paragraph—

(a)expressions used in this paragraph and in paragraph 1D have the same meanings in this paragraph as in that;

(b)what the Secretary of State or the Scottish Ministers want must be determined in every case in accordance with the information provided in that case under paragraph 1D, and with any revisions notified under paragraph 1F(3)(b) or 1G(3)(b); and

(c)the Office of Rail Regulation must have regard to the financial information so provided and revised whenever considering what is likely to make the best and most practicable contribution to the achievement of what the Secretary of State or the Scottish Ministers want.

Commencement Information

I1Sch. 4 para. 2 in force at 29.1.2007 by S.I. 2007/62, art. 2(2)(d)

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Notes

Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources