Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Section 5

SCHEDULE 5U.K.Temporary possession and use of land

This schedule has no associated Explanatory Notes

Occupation and use for construction of worksU.K.

1(1)The nominated undertaker may, in connection with the construction of the works specified in column (1) of the following table (or any works which are necessary or expedient for the purposes of or in connection with those works)—U.K.

(a)enter upon and take possession of the land specified in relation to those works in columns (2) and (3) of that table for such purposes as are so specified in column (4) of that table, and

(b)for such purposes as are so specified—

(i)remove from the land any structure or vegetation, and

(ii)construct on the land temporary works (including the provision of means of access) and structures.

(1)(2)(3)(4)
WorksAreaNumber of land shown on deposited plansPurpose for which temporary possession may be taken
1/3A and 1/3BCity of Westminster217The provision of a working site.
1/3A and 1/3B451The provision of a working site.
1/3A and 1/3B692The provision of a working site.
1/9D30cThe provision of a working site.
1/3A and 1/3BCity of London104a and 104bThe provision of a working site.
1/3A and 1/3B104cThe provision of a working site.
Proposed Whitechapel Station comprised in Works Nos. 1/3A and 1/3BLondon Borough of Tower Hamlets245bThe provision of access for construction.
Any of the works authorised by this ActLondon Borough of Tower Hamlets972 and 976The provision of access and a working site.
Any of the works authorised by this Act753, 774, 775, 788, 789 and 796The provision of access and barge loading facilities.
1/7, 1/33A and 1/33BLondon Borough of Greenwich160, 165 and 170The provision of a working site.
Any of the works authorised by this ActLondon Borough of Bexley83aThe provision of a working site.
The provision of overhead electrification equipment and works to Maidenhead BridgeRoyal Borough of Windsor & Maidenhead62 and 72The provision of a working site and access for construction.
3/3ABorough of Slough81The provision of access and a working site.
3/6172 and 173The provision of a working site.
3/7A and 3/7B187The provision of a working site.
The provision and renewal of railway systems and station facilities for operational purposes (Ealing Broadway Station)London Borough of Ealing111The provision of a working site.

(2)Not less than 28 days before entering upon and taking possession of land under this paragraph, the nominated undertaker shall give notice to the owners and occupiers of the land of its intention to do so.

(3)The nominated undertaker may not remain in possession of any land under this paragraph after the end of the period of one year beginning with the date of completion of the works specified in relation to the land in column (1) of the table in sub-paragraph (1) unless the owners of the land agree.

(4)The nominated undertaker shall pay compensation to the owners and occupiers of land of which possession is taken under this paragraph for any loss which they may suffer by reason of the exercise in relation to the land of the power or powers conferred by this paragraph.

(5)Any dispute as to a person's entitlement to compensation under sub-paragraph (4), or as to the amount of compensation, shall be determined under and in accordance with Part 1 of the Land Compensation Act 1961 (c. 33).

(6)Nothing in this paragraph shall affect any liability to pay compensation under section 10(2) of the Compulsory Purchase Act 1965 (c. 56), as applied to the acquisition of land under section 6(1), or under any other enactment, otherwise than for loss for which compensation is payable under sub-paragraph (4).

(7)In this paragraph, “structure” includes any erection.

2(1)Before giving up possession of land of which possession has been taken under paragraph 1, the nominated undertaker shall, in accordance with a scheme agreed with the owners of the land and the relevant planning authority, put the land into such condition as the scheme may provide.U.K.

(2)If, in relation to any land of which possession has been taken under paragraph 1, no scheme has been agreed for the purposes of this paragraph within 6 months of the date of completion of the works specified in relation to the land in column (1) of the table in paragraph 1(1), the scheme shall be such as may be determined by the appropriate Ministers after consultation with the nominated undertaker, the owners of the land and the relevant planning authority.

(3)Unless the owners of the land and the nominated undertaker otherwise agree, a scheme determined under sub-paragraph (2) shall provide for land to be restored to its former condition.

(4)Unless the nominated undertaker otherwise agrees, a scheme determined under sub-paragraph (2) shall not provide for the nominated undertaker to replace any structure removed under paragraph 1, other than a fence.

(5)Where the appropriate Ministers ask the relevant planning authority for assistance in connection with the carrying out by them of their function under sub-paragraph (2), they may require the nominated undertaker to reimburse to the planning authority any expenses which it reasonably incurs in meeting the request.

(6)The duty under sub-paragraph (1) in relation to any land shall be owed separately to the owners of the land and to the relevant planning authority.

(7)Where a scheme for the purposes of this paragraph provides for any step to be taken by the nominated undertaker before a specified date and that step has not been taken before that date, the relevant planning authority may—

(a)enter the land concerned and take that step, and

(b)require the nominated undertaker to reimburse to it any expenses which it reasonably incurs in acting under paragraph (a).

(8)In this paragraph—

  • appropriate Ministers” means the Secretary of State for [F1Levelling Up, Housing and Communities] and the Secretary of State for Transport acting jointly;

  • relevant planning authority” means—

    (a)

    in relation to land in the area of a unitary authority, the local planning authority;

    (b)

    in relation to land not in the area of a unitary authority, the district planning authority;

  • structure” includes any erection.

3(1)The nominated undertaker may use any road situated on land specified in the table in paragraph 8 of Schedule 6 for the passage of persons or vehicles (with or without materials, plant and machinery) for the purpose of or in connection with the construction of the works authorised by this Act.U.K.

(2)The nominated undertaker shall compensate the person having the management of a road to which sub-paragraph (1) applies for any loss which he may suffer by reason of the exercise of the power conferred by that sub-paragraph.

(3)Any dispute as to a person's entitlement to compensation under sub-paragraph (2), or as to the amount of such compensation, shall be determined under and in accordance with Part 1 of the Land Compensation Act 1961 (c. 33).

Occupation and use for maintenance of worksU.K.

4(1)At any time during the maintenance period relating to any of the scheduled works, the nominated undertaker may—U.K.

(a)enter upon and take possession of any land which is—

(i)within 20 metres from that work, and

(ii)within the limits of deviation for the scheduled works or the limits of land to be acquired or used,

if such possession is reasonably required for the purpose of or in connection with maintaining the work or any ancillary works connected with it, and

(b)construct on the land such temporary works (including the provision of means of access) and structures as may be reasonably so required.

(2)Sub-paragraph (1) shall not authorise the nominated undertaker to take possession of—

(a)a house, any other structure which is for the time being occupied, or a garden belonging to a house,

(b)land specified in the table in paragraph 8, 9, 11(1) or 12 of Schedule 6, or

(c)such of the land specified in columns (1) and (2) of the table in paragraph 10 of Schedule 6 as falls outside the description specified in relation to it in column (3) of the table.

(3)Not less than 28 days before entering upon and taking possession of land under this paragraph, the nominated undertaker shall give notice to the owners and occupiers of the land of its intention to do so.

(4)The nominated undertaker may only remain in possession of land under this paragraph for so long as may be reasonably required to carry out the maintenance works for which possession of the land was taken.

(5)Before giving up possession of land of which possession has been taken under this paragraph, the nominated undertaker shall restore the land to the reasonable satisfaction of the owners of the land.

(6)The nominated undertaker shall pay compensation to the owners and occupiers of land of which possession is taken under this paragraph for any loss which they may suffer by reason of the exercise in relation to the land of the powers conferred by this paragraph.

(7)Any dispute as to a person's entitlement to compensation under sub-paragraph (6), or as to the amount of the compensation, shall be determined under and in accordance with Part 1 of the Land Compensation Act 1961.

(8)Nothing in this paragraph shall affect any liability to pay compensation under section 10(2) of the Compulsory Purchase Act 1965 (c. 56), as applied to the acquisition of land under section 6(1), or under any other enactment, otherwise than for loss for which compensation is payable under sub-paragraph (6).

(9)In this paragraph—

(a)the maintenance period”, in relation to any work, means the period beginning with the date on which the work is completed and ending 5 years after the date on which it is brought into general use;

(b)structure” includes any erection;

(c)any reference to land within a specified distance of a work includes, in the case of a work under the surface of the ground, a reference to land within the specified distance of any point on the surface below which the work is situated.

Suspension of private rights of wayU.K.

5(1)Subject to sub-paragraph (2), all private rights of way over land of which the nominated undertaker takes possession under paragraph 1 or 4 above shall be suspended and unenforceable for as long as it remains in lawful possession of the land.U.K.

(2)The nominated undertaker may, in relation to a right of way, by direction provide—

(a)that sub-paragraph (1) shall not apply to the right, or

(b)that sub-paragraph (1) shall apply to the right only to such extent as may be specified in the direction.

(3)The nominated undertaker shall compensate any person who suffers loss by reason of the suspension of any right under sub-paragraph (1).

(4)Any dispute as to a person's entitlement to compensation under sub-paragraph (3), or as to the amount of the compensation, shall be determined under and in accordance with Part 1 of the Land Compensation Act 1961 (c. 33).

EnforcementU.K.

6U.K.Section 13 of the Compulsory Purchase Act 1965 (c. 56) (refusal to give possession to acquiring authority) applies for the purposes of this Schedule as if—

(a)references to the acquiring authority were references to the nominated undertaker,

(b)references to compensation payable to the person refusing to give possession were references to compensation payable under this Schedule, and

(c)in subsection (1) for “this Act” there were substituted “ Schedule 5 to the Crossrail Act 2008” ”.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Notes

Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources