Search Legislation

Climate Change Act 2008

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: SCHEDULE 8

 Help about opening options

Alternative versions:

Changes to legislation:

Climate Change Act 2008, SCHEDULE 8 is up to date with all changes known to be in force on or before 19 March 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to the whole Act associated Parts and Chapters:

Whole provisions yet to be inserted into this Act (including any effects on those provisions):

Section 79

SCHEDULE 8E+W+SCarbon emissions reduction targets

This schedule has no associated Explanatory Notes

Gas Act 1986 (c. 44)E+W+S

1(1)Section 33BC of the Gas Act 1986 (promotion of reductions in carbon emissions: gas transporters and gas suppliers) is amended as follows.E+W+S

(2)After subsection (1) insert—

(1A)The power to make orders under this section may be exercised so as to impose more than one carbon emissions reduction obligation on a person in relation to the same period or to periods that overlap to any extent..

(3)In subsection (5) (provision that may be made by an order under section 33BC in relation to the obligations it imposes), after paragraph (b) insert—

(ba)requiring the whole or any part of a carbon emissions reductions target to be met by action relating to—

(i)persons of a specified description,

(ii)specified areas or areas of a specified description, or

(iii)persons of a specified description in specified areas or areas of a specified description;.

(4)In subsection (13) (interpretation), at the appropriate place insert—

specified” means specified in the order..

Electricity Act 1989 (c. 29)E+W+S

2E+W+SIn section 6(9) of the Electricity Act 1989 (definition of “electricity distributor” and “electricity supplier”), at the appropriate place insert—

electricity generator” means any person who is authorised by a generation licence to generate electricity except where that person is acting otherwise than for purposes connected with the carrying on of activities authorised by the licence;.

3(1)Section 41A of that Act (promotion of reductions in carbon emissions: electricity distributors and electricity suppliers) is amended as follows.E+W+S

(2)In subsection (1) (power by order to impose obligations on distributors and suppliers to achieve carbon emissions reductions targets)—

(a)before paragraph (a) insert—

(za)on each electricity generator (or each electricity generator of a specified description);, and

(b)in the closing words, before “distributor” insert “ generator, ”.

(3)After that subsection insert—

(1A)The power to make orders under this section may be exercised so as to impose more than one carbon emissions reduction obligation on a person in relation to the same period or to periods that overlap to any extent..

(4)In subsection (3) (power for order to specify criteria by reference to which the Gas and Electricity Markets Authority is to determine targets), before “electricity distributors” insert “ electricity generators, ”.

(5)In subsection (4) (duty of the Secretary of State and the Authority to carry out functions under the section in a way that does not inhibit competition), for the words from “no electricity distributor” to the end of the subsection substitute

(a)no electricity generator is unduly disadvantaged in competing with other electricity generators,

(b)no electricity distributor is unduly disadvantaged in competing with other electricity distributors, and

(c)no electricity supplier is unduly disadvantaged in competing with other electricity suppliers..

(6)In subsection (5) (provision that may be made by an order in relation to the obligations it imposes)—

(a)in paragraph (a), before “electricity distributors” insert “ electricity generators, ”,

(b)after paragraph (b) insert—

(ba)requiring the whole or any part of a carbon emissions reductions target to be met by action relating to—

(i)persons of a specified description,

(ii)specified areas or areas of a specified description, or

(iii)persons of a specified description in specified areas or areas of a specified description;,

(c)in paragraph (d), before “distributors” insert “ generators, ”, and

(d)in paragraph (f), before “distributors” insert “ generators, ”.

(7)In subsection (6) (power for order to authorise the Authority to require the provision of information), before “distributor” insert “ generator, ”.

(8)In subsection (7)(d) (power for order to make provision for transfer of person's target to another distributor or supplier or to a gas transporter or supplier), before “electricity distributor” insert “ electricity generator, ”.

(9)In subsection (8)(d) (power for order to make different provision in relation to different distributors or suppliers), before “distributors” insert “ generators, ”.

(10)In subsection (11) (duty to consult before making order), before “electricity distributors” insert “ electricity generators, ”.

(11)In subsection (13) (interpretation), at the appropriate place insert—

specified” means specified in the order..

(12)In the heading, before “electricity distributors” insert “ electricity generators, ”.

4(1)Section 42AA of that Act (publication of statistical information about performance of suppliers and distributors) is amended as follows.E+W+S

(2)In subsection (1) (duty of Gas and Electricity Consumer Council to publish information about performance and consumer complaints)—

(a)in paragraph (a), before “electricity suppliers” insert “ electricity generators, ”, and

(b)in paragraph (b), before “suppliers” insert “ generators, ”.

(3)In subsection (2) (definition of “complaints”), before “electricity suppliers” insert “ electricity generators, ”.

5E+W+SIn section 64(1) of that Act (interpretation etc of Part 1), in the definition of “electricity distributor” and “electricity supplier”, after “ “electricity distributor”” insert “ , “electricity generator” .

Utilities Act 2000 (c. 27)E+W+S

6(1)Section 103 of the Utilities Act 2000 (overall carbon emissions reduction targets) is amended as follows.E+W+S

(2)In subsection (1)(b) (power by order to specify overall target for the promotion of measures mentioned in section 41A(2) of the 1989 Act), before “distributors” insert “ generators, ”.

(3)After subsection (1) insert—

(1A)The power conferred by this section may be exercised so as to specify more than one overall target in relation to the same period or to periods that overlap to any extent..

(4)In subsection (2)(b) (power for order to specify criteria for apportionment of overall target between electricity and gas sectors), before “electricity distributors” insert “ electricity generators, ”.

(5)In subsection (4) (duty to consult before making order), before “electricity distributors” insert “ electricity generators, ”.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Notes

Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources