(1)Development for which development consent is granted must be begun before the end of—
(a)the prescribed period, or
(b)such other period (whether longer or shorter than that prescribed) as is specified in the order granting the consent.
(2)If the development is not begun before the end of the period applicable under subsection (1), the order granting development consent ceases to have effect at the end of that period.
(3)Where an order granting development consent authorises the compulsory acquisition of land, steps of a prescribed description must be taken in relation to the compulsory acquisition before the end of—
(a)the prescribed period, or
(b)such other period (whether longer or shorter than that prescribed) as is specified in the order.
(4)If steps of the prescribed description are not taken before the end of the period applicable under subsection (3), the authority to compulsorily acquire the land under the order ceases to have effect.
(1)For the purposes of this Act (except Part 11) development is taken to begin on the earliest date on which any material operation comprised in, or carried out for the purposes of, the development begins to be carried out.
(2)“Material operation” means any operation except an operation of a prescribed description.
(1)If an order granting development consent is made in respect of any land, the order has effect for the benefit of the land and all persons for the time being interested in the land.
(2)Subsection (1) is subject to subsection (3) and any contrary provision made in the order.
(3)To the extent that the development for which development consent is granted is development within section 17(3), the order granting the consent has effect for the benefit of a person for the time being interested in the land only if the person is a gas transporter.
(1)If development consent is granted for development which includes the erection, extension, alteration or re-erection of a building, the order granting consent may specify the purposes for which the building is authorised to be used.
(2)If no purpose is so specified, the consent is taken to authorise the use of the building for the purpose for which it is designed.
(1)This subsection confers statutory authority for—
(a)carrying out development for which consent is granted by an order granting development consent;
(b)doing anything else authorised by an order granting development consent.
(2)Statutory authority under subsection (1) is conferred only for the purpose of providing a defence in civil or criminal proceedings for nuisance.
(3)Subsections (1) and (2) are subject to any contrary provision made in any particular case by an order granting development consent.
(1)This section applies for the purposes of this Part.
(2)“Land” includes any interest in or right over land.
(3)Acquiring a right over land includes acquiring it by the creation of a new right as well as by the acquisition of an existing one.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: