FIRST SCHEDULEMANNER IN WHICH, FOR THE PURPOSE OF THE DEFINITION OF “LEAD PAINT”, MATERIAL IS TO BE TREATED WITH A VIEW TO ASCERTAINING THE PERCENTAGE OF COMPOUND OF LEAD PRESENT

Regulation 3 (2)

The material is to be treated with suitable solvents to remove the oil, varnish and other media, and the residue to be dried at one hundred degrees Centigrade and thoroughly mixed. A weighed quantity of this extracted, dried and mixed material is to be continuously shaken for one hour, at the common temperature, with one thousand times its weight of an aqueous solution of hydrochloric acid containing 0·25 per cent. by weight of hydrogen chloride. This solution is thereafter to be allowed to stand for one hour and then filtered. The lead salt contained in the clear filtrate is then to be precipitated as lead sulphide and weighed as lead sulphate.

SECOND SCHEDULEMANNER OF TEST AND EXAMINATION BEFORE TAKING ANY CHAIN, WIRE ROPE, LIFTING APPLIANCE OR LIFTING GEAR INTO USE

Regulations 34 (1), 36 (1) and 40

  1. a

    Every winch, and every derrick with the whole of the gear accessory thereto, shall be tested with a proof load which shall not be less than the following—

    Safe working load

    Proof load

    Under 20 tons

    25 per cent.

    in excess of the safe working load

    20–50 tons

    5 tons

    over 50 tons

    10 per cent.

    In the case of a derrick with its accessory gear the proof load shall be applied as follows:—

    1. i

      where reasonably practicable by hoisting movable weights; or

    2. ii

      in other cases by maintaining the load by means of an accurate spring or hydraulic balance or similar device for a period of not less than five minutes. Where movable test weights are used the derrick shall be swung, with the load suspended, as far as possible in both directions. Where a spring or hydraulic balance or similar device is employed it shall be sufficient if the proof load is applied with the derrick swung as far as practicable first in one direction and then in the other. In each case the derrick shall be tested at the smallest angle to the horizontal at which it will operate and this angle shall be stated in the certificate of the test.

  2. b

    Every crane, crab, sheer-legs, teagle, transporter or runway, with its accessory gear, shall be tested with a proof load which shall not be less than the following—

    Safe working load

    Proof load

    Under 20 tons

    25 per cent.

    in excess of the safe working load

    20–50 tons

    5 tons

    over 50 tons

    10 per cent.

    In the case of a crane having a variable radius it shall be tested with a proof load applied at the maximum and minimum working radii. At each such radius the crane shall be swung as far as possible in both directions with the corresponding proof load suspended. In the case of hydraulic cranes where, owing to the limitation of pressure it is impossible to hoist a load 25 per cent. in excess of the safe working load, it shall be sufficient to hoist the greatest possible load.

  3. c

    Every article of lifting gear (whether it is accessory to any lifting appliance or not) and every pulley block other than a pulley block specially constructed for use with a crane to which it is permanently attached, and every chain shall be tested with a proof load at least equal to that shown against it in the following table:—

    Article of gear

    Safe working load

    Proof load

    Chain sling

    Twice the safe working load

    Rope sling

    Plate clamp

    Ring

    Link

    Hook (other than a ramshorn hook)

    Shackle

    Swivel

    Eye-bolt

    Ramshorn hook

    Under 50 tons

    Twice the safe working load

    50 tons to 100 tons

    Safe working loads plus 50 tons

    Over 100 tons

    One and a half times the safe working load

    Pulley blocks

    Single sheave block

    Four times the safe working load

    Multiple sheave block with safe working load up to and including 20 tons

    Twice the safe working load

    Multiple sheave block with safe working load over 20 tons up to and including 40 tons

    20 tons in excess of the safe working load

    Multiple sheave block with safe working load over 40 tons

    One and a half times the safe working load

    Chains (other than calibrated load chains)

    Twice the safe working load

    Calibrated load chains

    One and a half times the safe working load

  4. d

    After being tested as aforesaid, every lifting appliance with the whole of the gear accessory thereto, every article of lifting gear and every chain shall be examined, and the sheaves and the pins of the pulley blocks shall be removed for the purpose of the examination, to see that no part is injured or permanently deformed by the test.

  5. e

    In the case of wire ropes, a sample shall be tested to destruction.

THIRD SCHEDULEEQUIPMENT OF AMBULANCE ROOMS

Regulation 79 (3)

1

A glazed sink with hot and cold water available during working hours.

2

A table with smooth top.

3

Means for sterilising instruments.

4

A supply of suitable dressings, bandages and splints.

5

A couch.

6

A stretcher.

7

Blankets and hot-water bottles.

8

A foot bath.