xmlns:atom="http://www.w3.org/2005/Atom"

1.  The new highways which the Secretary of State proposes to construct along the routes described in the Schedule to this Order shall become trunk roads as from the date when this Order comes into force.

2.  The centre lines of the new trunk roads are indicated by heavy black lines on the deposited plan.

3.  In this Order: —

(i)“the deposited plan”means the plan numbered HA 10/2, WO7, marked “The A470 Cardiff-Glan Conwy Trunk Road (Improvement between Pen-Isa'r-Waen and the Brecon By-Pass) Order 1987”, signed by authority of the Secretary of State and deposited at the Welsh Office Repository, Curran Embankment, Cardiff, where it is open to inspection free of charge at all reasonable hours.

(ii)“the new trunk roads” means the highways mentioned in article 1 of this Order;

(iii)“the trunk road” means the A470 Cardiff-Glan Conwy Trunk Road.

4.  This Order shall come into force on 25th February 1988 and may be cited as The A470 Cardiff-Glan Conwy Trunk Road (Improvement between Pen-Isa'r-Waen and the Brecon By-pass) Order 1987.

Signed by authority of the Secretary of State for Wales

G. Mercer

Director of Highways 1987 Welsh Office