The North Killingholme Haven Harbour Empowerment Order 1994

Power to construct works

5.—(1) Subject to the provisions of this Order, the Company may, in the lines or situations and within the limits of deviation and according to the levels shown on the deposited sections, make and maintain the works hereinafter described, in the district of Glanford, with all necessary works and conveniences connected therewith—

  • Work No. 1

    A fixed jetty of open construction with bearing piles, breasting and mooring structures, ramps and pontoons, and a reinforced concrete and steel platform commencing at point TA 1667020702 and terminating at point TA 1699420291, and having an overall length of 523 metres and an overall width of 104 metres.

  • Work No. 2

    An approach bridge to Work No. 1 of open construction with bearing piles and a reinforced concrete and steel platform, commencing at point TA1653220264 and terminating at point TA1678820467, and having an overall length of 327 metres and an overall width of 40 metres.

(2) Subject to the provisions of this Order, the Company may within the limits of deviation reconstruct, renew, alter, extend, enlarge, add to, replace or relay the works and may maintain the same as reconstructed, renewed, altered, extended, enlarged, added to, replaced or relaid.

(3) The points specified in paragraph (1) above are Ordnance Survey National Grid reference points.