SCHEDULETHE SCHEME FOR CONSTRUCTION CONTRACTS

PART II—PAYMENT

Notice of intention to withhold payment10

Any notice of intention to withhold payment mentioned in section 111 of the Act shall be given not later than the prescribed period, which is to say not later than 7 days before the final date for payment determined either in accordance with the construction contract, or where no such provision is made in the contract, in accordance with paragraph 8 above.