Article 4
(1) | (2) |
---|---|
Number of Work | Description of Work |
In the Borough of Wigan | |
Work No. 1 | A guided busway 431 metres in length commencing at the junction of East Bond Street and Princess Street and running in a north-easterly direction before terminating at Holden Road, where the busway crosses the existing highway. |
Work No. 2 | A guided busway 1613 metres in length commencing by the termination of Work No. 1, running in a north-easterly direction along part of the former Leigh to Patricroft rail line formation, crossing Green Lane before terminating at the crossing of Millers Lane. |
Work No. 3 | A guided busway 755 metres in length commencing by the termination of Work No. 2, running in an easterly direction along part of the former Leigh to Patricroft rail line formation before terminating at the crossing of Cooling Lane. |
Work No. 4 | A guided busway 742 metres in length commencing by the termination of Work No. 3, running in an easterly direction along part of the former Leigh to Patricroft rail line formation before terminating at the crossing of Astley Street. |
Work No. 5 | A guided busway 915 metres in length commencing by the termination of Work No. 4 at Astley Street becoming guided after 120m and, running in an easterly direction along part of the former Leigh to Patricroft rail line formation, crossing Well Street before terminating at the crossing of Upton Lane. |
Work No. 5A | A realignment of the Well Street carriageway commencing 85 metres south of Manchester Road for a distance of 115 metres in a southerly direction. |
Work No. 6 | A guided busway 448 metres in length commencing by the termination of Work No. 5 at Upton Lane, running in an easterly direction along part of the former Leigh to Patricroft rail line formation before terminating at the crossing of Hough Lane. |
Work No. 7 | A guided busway 774 metres in length commencing by the termination of Work No. 6 at Hough Lane, running in an easterly direction along part of the former Leigh to Patricroft rail line formation before terminating at the crossing of Sale Lane. |
Work No. 8 | A guided busway 1025 metres in length commencing by the termination of Work No. 7 at Sale Lane, running in an easterly direction along part of the former Leigh to Patricroft rail line formation before terminating where the former rail line crossed over City Road. |
In the Borough of Wigan and City of Salford | |
Work No. 9 | A guided busway 447.5 metres in length commencing by the termination of Work No. 8 at City Road, running in an easterly direction along part of the former Leigh to Patricroft rail line formation before terminating where it meets Newearth Road. |
In the Borough of Wigan | |
Work No. 10 | A guided busway 401 metres in length commencing 7 metres to the east of the termination of Work No. 3 and the commencement of Work No. 4, running in a southerly direction along Cooling Lane before terminating 33 metres north of Richmond Drive. |
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: