Verification schemes19
1
The duty holder for an installation shall ensure that a record of the safety-critical elements and the specified plant is made.
2
After a record has been made in accordance with paragraph (1), the duty holder shall ensure that, in accordance with paragraph (3)—
a
comment on that record by an independent and competent person is invited;
b
a verification scheme providing for the matters contained in Schedule 7 is drawn up by or in consultation with such person;
c
a note is made of any reservation expressed by such person as to the contents of—
i
that record; or
ii
that scheme; and
d
that scheme is put into effect.
3
The matters set out in paragraph (2) shall be completed—
a
in the case of a production installation, before completion of its design; and
b
in the case of a non-production installation, before it is moved into F1internal waters with a view to its being operated there.