SCHEDULE 1PARTICULARS TO BE INCLUDED IN A DESIGN NOTIFICATION OR A RELOCATION NOTIFICATION

3.  A description of—

(a)the chosen design concept, including suitable diagrams, and a summary of the other design options which were considered;

(b)how the chosen design concept is intended to ensure—

(i)compliance with the requirements set out in regulations 5 and 10 of the Offshore Installations and Wells (Design and Construction, etc.) Regulations 1996(1); and

(ii)that risks with the potential to cause a major accident are reduced to the lowest level that is reasonably practicable; and

(c)the criteria used to select the chosen design concept and the process by which the selection was made.