The Nottingham Express Transit System Order 2009

Designation of worksE+W

7.—(1) Regardless of anything in the description of the scheduled works contained in Schedule 1 (scheduled works)—

(a)the whole or any part of the authorised street tramway may be constructed within the limits of deviation for that work off-street as a tramroad, and so far as it is so constructed shall be treated for the purposes of this Order as if it were so designated; and

(b)the whole or any part of the authorised tramroad may be constructed within the limits of deviation for that work along a street as a street tramway, and so far as it is constructed shall be treated for the purposes of this Order as if it were so designated.

(2) Where, by means of the creation or extinguishment of rights of way, any part of the authorised tramway which has been constructed as a tramroad becomes a street tramway, or any part which was constructed as a street tramway becomes a tramroad, it shall be treated for the purposes of this Order as if it were so designated.

Commencement Information

I1Art. 7 in force at 9.6.2009, see art. 1