Time periods for decision

This section has no associated Explanatory Memorandum

29.—(1) Subject to paragraph (7), where a valid application has been received by a local planning authority, they shall within the period specified or referred to in paragraph (2)(1) give the applicant notice of their decision or determination or notice that the application has been referred to the Secretary of State.

(2) The period specified or referred to in this paragraph is—

(a)in relation to an application for major development, 13 weeks beginning with the day immediately following that on which the application is received by the local planning authority;

(b)in relation to an application for development which is not major development, 8 weeks beginning with the day immediately following that on which the application is received by the local planning authority; or

(c)in relation to any development, unless the applicant has already given notice of appeal to the Secretary of State, such extended period as may be agreed in writing between the applicant and the local planning authority.

(3) In this article “valid application” means an application which consists of—

(a)an application which complies with the requirements of article 5 or article 6, as the case may be;

(b)in a case to which article 8 applies, the design and access statement;

(c)the certificate required by article 12;

(d)subject to paragraph (4), the particulars or evidence required by the authority under section 62(3) of the 1990 Act (applications for planning permission)(2); and

(e)any fee required to be paid in respect of the application and, for this purpose, lodging a cheque for the amount of a fee is to be taken as payment,

and a valid application shall be taken to have been received when the application, and such of the documents, particulars or evidence referred to above as are required to be included in, or to accompany, the application have been lodged with the appropriate authority mentioned in article 10(1) and the fee required to be paid has been paid.

(4) Paragraph (3)(d) only applies if—

(a)before the application is made the local planning authority publish, for the purposes of paragraph (3), a list of requirements on their website; and

(b)the particulars or evidence that the authority require to be included in the application fall within that list.

(5) Where a fee due in respect of an application has been paid by a cheque which is subsequently dishonoured—

(a)sub-paragraph (a) or (b) of paragraph (2), as the case may be, shall have effect as if, for “the application is received by the local planning authority”, there were substituted “the local planning authority are satisfied that they have received the full amount of the fee”; and

(b)sub-paragraph (c) of that paragraph shall have effect as if, at the end, there were added “once the authority are satisfied that they have received the full amount of the fee”.

(6) A local planning authority shall provide such information about applications made under article 5 or 6 (including information as to the manner in which any such application has been dealt with) as the Secretary of State may by direction require; and any such direction may include provision as to the persons to be informed and the manner in which the information is to be provided.

(7) Subject to paragraph (8), a local planning authority shall not determine an application for planning permission, where any notice of, or information about, the application has been—

(a)given by site display under article 11 or 13, before the end of the period of 21 days beginning with the date when the notice was first displayed by site display;

(b)served on—

(i)an owner of the land or a tenant of an agricultural holding under article 11; or

(ii)an adjoining owner or occupier under article 13,

before the end of the period of 21 days beginning with the date when the notice was served on that person; or

(c)published in a newspaper under article 11 or 13 or on a website under article 13, within the period of 14 days beginning with the date on which the notice or information was published,

and the periods in this paragraph are periods prescribed for the purposes of section 71(1) of the 1990 Act (consultations in connection with determinations under section 70)(3).

(8) Where, under paragraph (7), more than one of the prescribed periods applies, the local planning authority shall not determine the application before the end of the later or latest of such periods.

(1)

In relation to an application for EIA development, see S.I. 1999/293.

(2)

Section 62 was substituted by section 42(1) of the 2004 Act.

(3)

Section 71(1) was substituted by section 16(2) of the Planning and Compensation Act 1991.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources