Un-metered transport supply: electricity
20.—(1) Sub-paragraph (2) applies where—
(a)A has consumed a supply of electricity for the purposes of transport; and
(b)part of that supply so consumed was not measured by a meter of any sort (“un-metered electricity transport supply”).
(2) Where this sub-paragraph applies, A may decide that un-metered electricity transport supply is not consumed for the purposes of transport.
(3) A decision made under sub-paragraph (2)—
(a)may be made in respect of—
(i)qualifying electricity in the qualification year of a phase and where so made, applies also to supplies of electricity during the phase;
(ii)a phase where it was not made in respect of the qualification year, where such a decision is made on or before the participant submits its footprint report;
(b)must not be altered during the phase.