PART 10ROMP Applications

Determination of conditions and right of appeal on non-determination

50.—(1) Where it falls to—

(a)a mineral planning authority to determine a Schedule 1 or a Schedule 2 application, paragraph 2(6)(b) of Schedule 2 to the 1991 Act, paragraph 9(9) of Schedule 13 to the 1995 Act or paragraph 6(8) of Schedule 14 to the 1995 Act shall not have effect to treat the authority as having determined the conditions to which any relevant planning permission is to be subject unless either the mineral planning authority has adopted a screening opinion or the Secretary of State has made a screening direction to the effect that the ROMP development in question is not EIA development;

(b)a mineral planning authority or the Secretary of State to determine a Schedule 1 or a Schedule 2 application—

(i)section 69 (register of applications, etc), and any provisions of the Order made by virtue of that section, shall have effect with any necessary amendments as if references to applications for planning permission included ROMP applications under paragraph 9(1) of Schedule 13 to the 1995 Act and paragraph 6(1) of Schedule 14 to the 1995 Act(1); and

(ii)where the relevant mineral planning authority is not the authority required to keep the register, the relevant mineral planning authority must provide the authority required to keep it with such information and documents as that authority requires to comply with section 69 as applied by sub-paragraph (i), with regulation 23 as applied by regulation 42, and with regulation 49(4).

(2) Where it falls to the mineral planning authority or the Secretary of State to determine an EIA application which is made under paragraph 2(2) of Schedule 2 to the 1991 Act, paragraph 4(4) of that Schedule shall not apply.

(3) Where it falls to the mineral planning authority to determine an EIA application, the authority shall give written notice of their determination of the ROMP application within 16 weeks beginning with the date of receipt by the authority of the ROMP application or such extended period as may be agreed in writing between the applicant and the authority.

(4) For the purposes of paragraph (3) a ROMP application is received by the authority when it receives—

(a)a document referred to by the applicant as an environmental statement for the purposes of these Regulations;

(b)any documents required to accompany that statement; and

(c)any additional information which the authority has notified the applicant that the environmental statement should contain.

(5) Where paragraph (1)(a) applies—

(a)paragraph 5(2) of Schedule 2 to the 1991 Act, paragraph 11(1) of Schedule 13 to the 1995 Act and paragraph 9(1) of Schedule 14 to the 1995 Act (right of appeal) shall have effect as if there were also a right of appeal to the Secretary of State where the mineral planning authority have not given written notice of their determination of the ROMP application in accordance with paragraph (3); and

(b)paragraph 5(5) of Schedule 2 to the 1991 Act, paragraph 11(2) of Schedule 13 to the 1995 Act and paragraph 9(2) of Schedule 14 to the 1995 Act (right of appeal) shall have effect as if they also provided for notice of appeal to be made within 6 months from the expiry of the 16 week or other period agreed pursuant to paragraph (3).

(6) In determining for the purposes of paragraphs—

(a)2(6)(b) of Schedule 2 to the 1991 Act, 9(9) of Schedule 13 to the 1995 Act and 6(8) of Schedule 14 to the 1995 Act (determination of conditions); or

(b)paragraph 5(5) of Schedule 2 to the 1991 Act, paragraph 11(2) of Schedule 13 to the 1995 Act and paragraph 9(2) of Schedule 14 to the 1995 Act (right of appeal) as applied by paragraph (26)(b),

the time which has elapsed without the mineral planning authority giving the applicant written notice of their determination in a case where the authority have notified an applicant in accordance with regulation 10(1) that the submission of an environmental statement is required and the Secretary of State has given a screening direction in relation to the ROMP development in question no account shall be taken of any period before the issue of the direction.

(1)

These provisions are not applied to applications under paragraph 2(2) of Schedule 2 to the 1991 Act as they are applied by paragraph 9 of Schedule 2 to the 1991 Act.