The North Blyth Biomass Power Station Order 2013

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Piling and vibration

29.—(1) No piling works may be commenced until a piling method statement (which may form part of the CEMP) has been submitted to and approved by the relevant planning authority following consultation with Natural England, the Environment Agency and the MMO regarding the mitigation of the impact of piling and other construction works that are significant in terms of noise generation likely to impact on ornithology and aquatic and marine animals. The piling method statement must—

(a)conform with the provisions set out in paragraphs 4.5.80 and 4.5.81 of the environmental statement and the letter from the undertaker to Natural England dated 26 June 2012;

(b)fully reflect paragraphs 11.6.5 to 11.6.19 of the environmental statement and include provision ensuring that noise levels will be monitored during the construction phase to ensure levels are as predicted;

(c)include details of mitigation to be employed to ensure that the noise from piling activities does not exceed 55 dB(A) LA Max at the locations of the agreed measurement points during the months of August to March inclusive (unless otherwise previously agreed with the relevant planning authority in consultation with Natural England, the Environment Agency and the MMO);

(d)stipulate that any percussive piling may only be undertaken if the volume emissions of such works are to be increased on a gradual basis;

(e)demonstrate that piling activities will not have a resultant unacceptable impact on groundwater;

(f)include provision that no piling shall be undertaken in connection with Work Nos. 1(u) to (w) (inclusive) during the months of October to March inclusive; and

(g)include a programme for reporting noise measurements and proposals for reporting on the effectiveness of the mitigation contained within the method statement including, in the event that predicted noise levels during the construction phase are exceeded, a process for any necessary remedial action being approved by the relevant planning authority and thereafter implemented within a stated timescale following such approval.

(2) Notwithstanding any measures approved pursuant to sub-paragraph (1), no pile driving shall take between the hours of 17.30 and 07.00 on any day.

(3) The authorised development must be carried out in accordance with the provisions of the approved piling method statement and this Order.

(4) No piling works may commence as part of the construction of the authorised development until steps have been taken to ensure that vibration monitoring will be carried out (including for test piling) in accordance with details which have been submitted to and approved by the relevant planning authority. Thereafter details of monitoring must be submitted to and approved by the relevant planning authority in writing prior to commencement of any piling works for the authorised development and a record of vibration must be maintained at all times during the construction works and made available to the relevant planning authority on request.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources