16.—(1) The authorised development must not be commenced until a detailed drainage plan showing all new surface water drainage has been approved by the relevant planning authority in consultation with the lead local flood authority. The details must be in accordance with the details of paragraph 5.4.6 of the flood risk assessment and demonstrate that:
(a)all discharges to watercourses from railway drainage systems should be attenuated to a rate not exceeding the existing rate of runoff, that is 5 litres per second per hectare; and
(b)all discharges made from railway drainage systems should be discharged downstream of existing watercourse culverts wherever possible to reduce any impact on the capacity of each of the respective culverts.
(2) The authorised development must be constructed in accordance with the approved details.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: