The Network Rail (Redditch Branch Enhancement) Order 2013

Landscaping

5.—(1) The authorised development must not be commenced until a written landscaping scheme reflecting the visual impacts report and landscape plan/strategy has been submitted to and approved by the relevant planning authority.

(2) The landscaping scheme must reflect the mitigation measures described in the visual impacts report and landscape plan/strategy and must include details of—

(a)location, number, species, size and planting density of any proposed planting;

(b)cultivation, importing of materials and other operations to ensure plant establishment;

(c)implementation timetables for all landscaping; and

(d)proposals to take account of the presence of trees with trunks of a diameter of 100 mm or more and to minimise the loss of such trees.