xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULE 1E+W+SAuthorised project

PART 3E+W+SRequirements

Control of noise during operational phaseE+W+S

36.—(1) Work No. 25 shall not commence operation until a written scheme for noise management including monitoring and attenuation for the use of Work No. 25 has been submitted to and approved by West Sussex County Council.

(2) The noise management scheme shall be implemented as approved and maintained for the duration of use of the authorised development.

Commencement Information

I1Sch. 1 para. 36 in force at 6.8.2014, see art. 1