SCHEDULE 12E+W+SProtective provisions

PART 1E+W+SFor the protection of railway interests

8.  Network Rail shall at all times afford reasonable facilities to the undertaker and its agents for access to any works carried out by Network Rail under this Schedule during their construction and shall supply the undertaker with such information as it may reasonably require with regard to such works or the method of constructing them.E+W+S

Commencement Information

I1Sch. 12 Pt. 1 para. 8 in force at 6.8.2014, see art. 1