SCHEDULE 13Deemed licence under Marine and Coastal Access Act 2009 – array

PART 2Conditions

Pre-construction plans and documentationI112

1

Any archaeological reports produced in accordance with condition 11(1)(h)(iii) are to be agreed with English Heritage.

2

Each programme, statement, plan, protocol or scheme required to be approved under condition 11 shall be submitted for approval at least four months prior to the intended start of construction, except where otherwise stated or unless otherwise agreed in writing by the MMO.

3

The licensed activities shall be carried out in accordance with the approved plans, protocols, statements, schemes and details approved under condition 11, unless otherwise agreed in writing by the MMO.