Programming of Works
21.—(1) The undertaker must not commence construction of the quay (Work No. 1) less than 7 months after commencing construction of the compensation site referred to in paragraph 4(a) of Schedule 1 (authorised development)).
(2) The undertaker must use all reasonable endeavours to create the Cherry Cobb Sands breach no more than 15 months after commencing construction of the quay (Work No. 1).