The Able Marine Energy Park Development Consent Order 2014

Programming of Works

21.—(1) The undertaker must not commence construction of the quay (Work No. 1) less than 7 months after commencing construction of the compensation site referred to in paragraph 4(a) of Schedule 1 (authorised development)).

(2) The undertaker must use all reasonable endeavours to create the Cherry Cobb Sands breach no more than 15 months after commencing construction of the quay (Work No. 1).