SCHEDULE 1Authorised project

PART 3Requirements

Construction hours29

1

Construction work for the onshore works and any construction-related traffic movements to or from the site of the relevant work must take place only between 7 a.m. and 7 p.m. on Monday to Saturday, with no activity on Sundays, public or bank holidays, except—

a

where continuous periods of operation are required, such as concrete pouring and drilling;

b

for the delivery of abnormal loads to the onshore works, which may cause congestion on the local road network;

c

where works are being carried out on the foreshore;

d

where works are required to be carried out in an emergency; or

e

as otherwise agreed by the relevant planning authority as required outside of these hours pursuant to details submitted and approved under any other Requirement.

2

All construction operations that are to be undertaken outside the hours referred to in sub-paragraph (1) must be agreed by the relevant planning authority in advance and must be carried out within the hours agreed by the relevant planning authority.