18.7.—(1) This rule applies for the purposes of sections 92A and 104A(1) and prescribes the periods for which reports must be made.
(2) The liquidator’s progress reports in a voluntary winding up must cover the periods of—
(a)12 months starting on the date the liquidator is appointed; and
(b)each subsequent period of 12 months.
(3) The periods for which progress reports are required under paragraph (2) are unaffected by any change in the liquidator.
(4) However where a liquidator ceases to act the succeeding liquidator must, as soon as reasonably practicable after being appointed, deliver a notice to the members (in a members’ voluntary winding up) or to members and creditors (in a creditors’ voluntary winding up) of any matters about which the succeeding liquidator thinks the members or creditors should be informed.
(5) A progress report is not required for any period which ends after the date to which a final account is made up under section 94 or 106(2) and is delivered by the liquidator to members (members’ voluntary winding up) or to members and creditors (creditors’ voluntary winding up).
(6) The liquidator must send a copy of each progress report within two months after the end of the period covered by the report to—
(a)the registrar of companies (who is a prescribed person for the purposes of sections 92A and 104A);
(b)the members; and
(c)in a creditors’ voluntary liquidation, the creditors.
Section 92A is amended by section 136(2) and paragraph 16 of Schedule 9 to the Small Business, Enterprise and Employment Act 2015 (c.26) and section 104A is amended by section 136(3) and paragraph 27 of that Schedule.
A new section 94 is substituted by paragraph 18 of Schedule 9 to the Small Business, Enterprise and Employment Act 2015 and a new section 106 is substituted by paragraph 29 of that Schedule.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: