The East Anglia THREE Offshore Wind Farm Order 2017

Details of licensed marine activities

3.  Such activities are authorised in relation to the construction, maintenance and operation of—

(1) Work No. 4 (phase 2) – up to two cables to connect Work No. 2 with the East Anglia ONE Offshore Wind Farm.

(2) In connection with such Work No. 4 and to the extent that it does not otherwise form part of any such work, further associated development comprising such other works as may be necessary or expedient for the purposes of or in connection with the relevant part of the authorised scheme and which fall within the scope of the work assessed by the environmental statement and the provisions of this licence.

(3) In connection with such Work No. 4, ancillary works within the Order limits which have been subject to an environmental impact assessment recorded in the environmental statement comprising—

(a)temporary landing places, moorings or other means of accommodating vessels in the construction and/ or maintenance of the authorised scheme; and

(b)marking buoys, beacons, fenders and other navigational warning or ship impact protection works.