Search Legislation

The Southampton to London Pipeline Development Consent Order 2020

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Prior approvals

65.—(1) No specified work may commence until—

(a)the programme of works has been approved by Highways England, such approval not to be unreasonably withheld or delayed;

(b)the following details relating to the specified work have been submitted to and approved by Highways England, such approval not to be unreasonably withheld or delayed–

(i)the detailed design information;

(ii)details of any proposed road space bookings with Highways England;

(iii)(if details have been supplied pursuant to sub-paragraph (ii)) a scheme of traffic management; and

(iv)the identity of the contractor and nominated persons.

(c)(if the carrying out of a specified work requires the booking of any road space with Highways England) a scheme of traffic management and a process for stakeholder liaison has been submitted by the undertaker and approved by Highways England, such scheme to be capable of amendment by agreement between the undertaker and Highways England from time to time;

(d)any stakeholder liaison that may be required has taken place in accordance with the process for such liaison agreed between the undertaker and Highways England under paragraph (c);

(e)any further information that Highways England may reasonably request within 14 days of the submission of the detailed design of a specified work has been supplied to Highways England; and

(f)a condition survey and a reasonable regime of monitoring the structures, assets and pavements that were surveyed under the condition survey has been submitted to and approved, acting reasonably, by Highways England.

(2) Highways England must provide the undertaker with a list, which is to be agreed between the parties acting reasonably, of all the structures, assets and pavements to be subject to both a condition survey and reasonable regime of monitoring pursuant to sub-paragraph (1)(f) and paragraph 68(1) of this Part before the first condition survey is conducted and the reasonable regime of monitoring is implemented.

(3) Highways England must prior to the commencement of a specified work inform the undertaker of the identity of the person who will act as a point of contact on behalf of Highways England to consider the information required under sub-paragraph (1) and of the identity of the person or persons who are authorised to give consent or approval on behalf of Highways England for any matter requiring approval or consent in these provisions.

(4) Any approval of Highways England required by this paragraph—

(a)must not be unreasonably withheld or delayed;

(b)in the case of a refusal must be accompanied by a statement of grounds for refusal;

(c)is deemed to have been refused if it is neither given or refused within 56 days of the submission of the relevant information (if further information is requested by Highways England any such request must be submitted to the undertaker within 28 days of submission of the relevant information under this sub-paragraph (c) and the provision of such further information by the undertaker will not be deemed to constitute a new application for approval pursuant to this paragraph); and

(d)may be given subject to any reasonable conditions as Highways England considers necessary.

(5) If the undertaker requires entry onto land which forms part of the trunk road network to exercise the powers over that land set out in article 20 (authority to survey and investigate the land) of this Order, the undertaker must supply details of any proposed road space bookings (in accordance with Highways England’s Asset Management Operational Requirements (AMOR) including Network Occupancy Management System (NOMS) used to manage road space bookings and network occupancy) and submit to Highways England and obtain the approval of Highways England of a scheme of traffic management prior to the exercise of the power.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources